1 / 17

SWG Resource Team: Supply-side Resources for the 2022 Common Case

SWG Resource Team: Supply-side Resources for the 2022 Common Case. Thomas Carr Western Interstate Energy Board July 21, 2011. Outline. Task: Identify the 2022 generation portfolio Load Assumptions BA load forecasts Loads applicable to states/provinces RPS renewable energy requirements

benny
Download Presentation

SWG Resource Team: Supply-side Resources for the 2022 Common Case

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SWG Resource Team:Supply-side Resources for the 2022 Common Case Thomas Carr Western Interstate Energy Board July 21, 2011

  2. Outline Task: Identify the 2022 generation portfolio • Load Assumptions • BA load forecasts • Loads applicable to states/provinces • RPS renewable energy requirements • RPS statutes/regulations • Deriving total RPS energy • Specifying the renewable portfolio • IRP/Resource planner survey by LBNL • CA CPUC modeling • Loads and resource balance • Subregional spreadsheet model • Meeting peak loads • Planning margins

  3. SWG Resource Team: Identify the 2022 generation portfolio • TEPPC develops assumptions to run a production cost model (Promod) of the western power grid for the year 2022 (Generation, Loads, Transmission) • Generation • New generation – Resource Team of SWG • Existing generation – TEPPC database • Retirements – • Standard retirements – LRS, Data WG, LBNL • OTC policy (Data WG, CA stakeholders)

  4. 1. Load Assumptions • Start with Balancing Authority (BA) loads supplied to WECC’s Loads and Resources Subcommittee (LRS) • BAs submit new 10-year forecasts to WECC in March • TEPPC load assumptions based on BA load forecasts • 36 BAs with loads • SPSC’s DSM Work Group & WECC effort to refine BA loads to identify DSM state/federal policies that may or may not be in the BA load forecasts

  5. BA Loads reported to LRS

  6. 1. Load Assumptions cont. • Convert to state load forecast 2022 • Most BAs fully within a state or province • But 8 BAs cover 2 or more states • Data on BA split among states • Investor Owned Utilities (IOUs) – FERC Form 1 • BPA and Western Area Power Administration – provided information on splits • Adjust for line losses to estimate retail sales

  7. 2. RPS Requirements to Renewable Energy • RPS statutes / regulations • 10 states in the Western Interconnection with RPS • AZ, CA, CO, MT, NV, NM, OR, TX, UT, WA • BC and AB have policies but not the RPS-type • Many similarities but all different • DSIRE website summarizes RPS provisions by each state • http://www.dsireusa.org/ • Develop a summary table for reference

  8. SWG precedents on RPS • RPS% with discrete jump (e.g. 15% to 20%); • Pro rate with linear path • For 2022, applies to NV, OR and UT • UT RPS sets 2025 target without interim requirements • Prorate with linear path • NV RPS allows ¼ to be met through energy efficiency • Assume ¼ of gross RPS met by energy efficiency • CO grants 125% credit to instate generation • Assume all instate with 125% credit to RPS

  9. Methodology to Derive RPS Energy • Derived state load forecast 2020 from BA loads • State RPS rules may differ by sectors • IOUs, Coops, Publics/Municipals, Others • Adjust state load by % shares using EIA data • Multiply each share by appropriate RPS%

  10. 3. Specifying the Renewable Portfolio for the Common Case • Specify TEPPC base case resources to meet RPS requirements in applicable states • Strategy to specify renewables for the TEPPC base case • IRP/Plans • Utility IRP information, resource planners • LRS data on renewable projects • California • CA PUC modeling

  11. LBNL IRP/Resource Planner Review • LBNL reviewing IRPs of LSEs • Resource Planners’ Forum presentation and contacts developed • Studies WG to use LBNL data/results into specification of resources by state

  12. Example of Incremental Generation Worksheet: 2011-2022

  13. Example of Retirements Worksheet: 2011-2022

  14. 4. Load & Resources Balance • General peak load methodology • Gap = [Peak load + planning margin] – Generation at peak • 2007/2008 relied on WECC-wide peak load-resource balance without transmission constraints • 2009 shifted to Subregional analysis of loads & resources

  15. Subregional Loads & Resource Analysis • Subregional Load-Resource Methodology • WECC staff developed spreadsheet model with 7 subregions • Summer and winter subregional coincident peaks • planning margins for each subregion • discounted capacity factors for each subregion. • Model derives an initial gap for each subregion • Adjustment for trade flows between subregions • Flows identified on major transmission paths at peak period • Estimated net imports to derive an adjusted gap • Lack of data on firm trade flows between regions • Did not rely on subregional model to set generation limits

More Related