160 likes | 279 Views
Utility Policy Issues Affecting Distributed Generation & CHP Deployment. Getting the Rules Right. CHP in the Pacific Northwest Seattle Hilton Hotel Seattle, Washington October 15, 2002. Presenter: John Nimmons, J.D. John Nimmons & Associates, Inc. Sustainable Energy Strategies
E N D
Utility Policy IssuesAffecting Distributed Generation & CHP Deployment Getting the Rules Right CHP in the Pacific Northwest Seattle Hilton Hotel Seattle, Washington October 15, 2002 Presenter: John Nimmons, J.D. John Nimmons & Associates, Inc. Sustainable Energy Strategies Mill Valley, CA 415.381.7310
Rank Barriers Explanation Barriers to DG (from DPCA’s 1999 member survey)
Barriers to DG (from DPCA’s 1999 member survey) Rank Barriers Explanation 1 Interconnection Inconsistent standards, complex process, high cost 2 Utility tariffs Stranded costs, exit fees, standby, general rate design 3 Interconnect technology Sometimes poorly understood, inadequate or costly 4 Lack of familiarity E.g., with DG technologies, environmental benefits 5 Permitting process Long, cumbersome, costly & often inappropriate 6 Assigning DG value Hard to identify, quantify & allocate among parties 7 Stakeholder confusion Utilities & consumers unfamiliar with DG benefits 8 High first cost Discourages DG adoption, despite life-cycle benefits 9 Electricity restructuring Creates uncertainty, complexity & inconsistency 10 Few DG case studies Little experience, especially w/ grid support, impacts
Rank Barriers Explanation 1 Interconnection Inconsistent standards, complex process, high cost 2 Utility tariffs Stranded costs, exit fees, standby, general rate design 3 Interconnect technology Sometimes poorly understood, inadequate or costly 4 Lack of familiarity E.g., with DG technologies, environmental benefits 5 Permitting process Long, cumbersome, costly & often inappropriate 6 Assigning DG value Hard to identify, quantify & allocate among parties 7 Stakeholder confusion Utilities & consumers unfamiliar with DG benefits 8 High first cost Discourages DG adoption, despite life-cycle benefits 9 Electricity restructuring Creates uncertainty, complexity & inconsistency 10 Few DG case studies Little experience, especially w/ grid support, impacts Barriers to DG (from DPCA’s 1999 member survey)
Interconnection Barriers • The Problem • DG can strengthen the grid, & vice-versa • utilities responsible for grid safety & reliability … but often have disincentives to connect DG • The Challenge • create appropriate utility incentives • develop objective, uniform technical standards • simplify procedural requirements to connect • reduce costs for small, low-impact resources
Interconnection Progress • National efforts • IEEE 1547 - uniform technical standards • FERC - Standardized procedures & agreements • Generator Interconnection • over 20 MW [RM02-1-000, 4/24/02] • Small Generator Interconnection • up to 20 MW [RM02-12-000, 8/16/02] • www.ferc.gov/electric/gen_inter.htm#Stand%20Inter • State efforts • California, New York, Ohio, Texas • NARUC Model DG Interconnection Procedures & Agreement • www.nrri.ohio-state.edu/programs/electric/distributedgeneration
Tariff Barriers to DG • Universal tariff issues facing DG • ‘Stranded’ utility costs (bypass charges, exit fees, etc.) • ‘Cogen deferral’ rates (or ‘flexible pricing’) • Standby charges • Fixed vs. usage-based charges • Location- & time-sensitive pricing
Tariff Barriers to DG • Stranded costs • Issue: Will DG ‘strand’ utility assets, shifting their costs to utility shareholders or other ratepayers ? Yes,and a death spiral will surely follow. • Utility view: No,and DG’s not responsible for utility investments. • DG view: • Analysis: • Assets dedicated to a single customer and not re-usable shouldbe customer responsibility (whether or not a DG customer) • ‘Stranding’ doesn’t apply where assets remain in ratebase, and utility can continue to use and earn a return on them • Assets may be temporarily underutilized, but used later; distinguish normal revenue fluctuation from ‘stranding’
Tariff Barriers to DG • ‘Flexible pricing’ or ‘cogen deferral’ rates • Issue: Should utilities ‘compete’ with DG by undercutting their otherwise applicable tariffs? • Utility view: Yes, keeping DG customer protects others, and some revenues are better than none • DG view: No, invites monopoly abuse, and thwarts DG that could benefit the system and other customers • Analysis: • Reasonable in principle but too often used as a sword, not a shield • Short-term response to a long-term problem • Benefits of encouraging DG innovation and utility collaboration may outweigh short-term benefits of flexible pricing
Tariff Barriers to DG • Standby charges • Issues: • Should utilities or their customers decide what level & type of standby services each customer needs, & whether they’re worth buying? • What costs should be included in standby charges?
Tariff Barriers to DG • Standby charges • Utility view: DG customer may need its full requirement, and the utility must provide distribution capacity • DG view: DG customer should decide what service it needs, when it needs it, and what it’s willing to pay for it • Analysis: • Most agree that standby charges should be ‘cost-based’ – the question is how to calculate costs • Costs differ as a function of quantity, firmness, location and time, and efficient standby pricing should reflect that • Contractual arrangements can supplant utility obligation to meet full requirements, and empower customers to choose what they need
Tariff Barriers to DG • Fixed vs. usage-based charges • Issue: which vary with usage; Which grid costs are fixed; and what rate designs which can DG reduce; ensure fair cost recovery, yet encourage sensible DG? • Utility view: T&D costs are fixed regardless of customer usage, so T&D rates should comprise mainly fixed charges • DG view: T&D costs reflect customer usage over time, so rates should be usage-based and ‘avoidable’ by customer action • Analysis: • DG may not avoid T&D costs in the short-run, but long-run incremental costs drive rates • Those costs are a function of load growth – i.e., customer usage • Usage-based charges better reflect costs, but are more volatile
Tariff Barriers to DG • Location- & time-sensitive pricing • Issue: Should T&D rates reflect that costs differ by location and time of use, to signal high-value DG? • Utility view: T&D costs do differ by location and time, but T&D rates must be averaged to ensure universal service • DG view: T&D costs differ by location and time, and rates should signal those differences to influence customer behavior • Analysis: • Averaged rates mute cost signals and undermine economic efficiency • De-averaged location- and time-specific rates are more efficient, but more volatile, harder to administer, and threaten universal service • Other approaches (such as locational credits or riders, or 2-part rates) can achieve similar benefits more simply, and advance sensible DG
Conclusions • Interconnection & tariffs are key to DG success • Considerable progress on interconnection • Less attention to rate design so far • Rate design rhetoric often oversimplifies & obscures • Rate issues are rarely black & white, but focusing on specifics instead of generalities will help resolve them • DG is still a small percentage of supply: utilities & regulators can afford to innovate a little, to learn a lot