140 likes | 288 Views
Engineering Perspectives on First Year of New Reactor Construction. Mohamed Shams, Ph.D., PE Structural Engineering BC US NRC, Office of New Reactors July 23, 2013. Purpose.
E N D
Engineering Perspectives on First Year of New Reactor Construction Mohamed Shams, Ph.D., PE Structural Engineering BC US NRC, Office of New Reactors July 23, 2013
Purpose • Present NRC staff view, from an engineering perspective (civil/structural), on construction inspection efforts and license amendment requests.
Background • AP1000 Rev. 19 certification on December 30, 2011 • Vogtle Units 3 & 4 license issuance February 10, 2012 • Summer Units 2 & 3 license issuance on March 30, 2012
License Amendment Requests Issued 17 License Amendments
Basemat Technical Issues Shear Reinforcement (T-heads) • Inspection of basemat rebar identified two issues for the concrete slabs below the elevator and sump pits • Headed shear reinforcement not demonstrated to comply with ACI 349-01 Appendix B • Shear reinforcement spacing exceeded d/2 Typical T-head Installation Source: Headed Reinforcement Corporation (HRC) Website
Headed Reinforcement Licensing Basis • Shear stirrups have T-headed anchors at each end • T-headed anchors are used where rebar mechanical anchorage is required • Criteria of ACI 349 Chapter 12 are applied for rebar development Source: AP1000 DCD, Rev 19
Commitments / Guidance • ACI 349, Section 12.6, Mechanical Anchorage • Appendix B, Anchorage to Concrete • ASTM A970 • Staff open to alternative approaches to demonstrate adequate anchorage • Manufacturer literature • Research and testing • Alternative models (Strut-and-tie) • Other relevant codes (e.g., ACI 318) Objective - Ensure adequate anchorage for ductile rebar behavior
Headed Reinforcement Resolution • Approved License Amendment Requests • ACI 318-11 provisions for headed reinforcement • Increase elevator and sump pits thickness • Revise shear design of walls
Basemat Technical Issues • Basemat Hooked Reinforcement During a March 2012 inspection, NRC staff identified a deviation in the detailed/installed nuclear island basemat rebar relative to the typical reinforcement depicted from the AP1000 DCD.
Licensing Basis Design and analysis procedures for seismic Category I structures are in accordance with ACI 349. Foundation walls act integrally with the basemat to provide stiffness and distribute foundation loads. Basemat designed as a two-way slab. Basemat considered as a diaphragm, as such is part of the lateral-force resisting system. Hooked Reinforcement
Commitments / Guidance • ACI 349-01 • Chapter 13 – Negative moment reinforcement must be developed at support • Chapter 12– #14 bar splices are prohibited • Chapter 21 • Ductile connections • Cannot invoke excess reinforcement provision (12.5.3.4) for elements in lateral force-resisting system. Objective - Ensure ductile behavior of connection of perimeter walls to the basemat
Basemat technical Issues Resolution • Re-constitution of reinforcement hooks in basemat design. • Approved License Amendment Requests • Increase in basemat concrete compressive strength to decrease required development length.
Lessons Learned • Provide quantitative technical justifications for LARs • Adhere to codes and standards in all areas of the design • Detailed design must satisfy both the DCD and code commitments • Perform detailed engineering analysis sufficiently in advance of installation • Institute consistency checks • Balance specificity and flexibility in licensing basis