1 / 14

Information on the IBR-2M reactor first power

Information on the IBR-2M reactor first power. Content: Physical start-up summary Preparation for the first power and for first physical experiments at n-beams T erms and tasks under the reactor research program at the first power stage The plan of the main activities in 2011.

nishan
Download Presentation

Information on the IBR-2M reactor first power

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Information on the IBR-2M reactor first power

  2. Content: • Physical start-up summary • Preparation for the first power and for first physical experiments at n-beams • Terms and tasks under the reactor research program at the first power stage • The plan of the main activities in 2011

  3. Physical start-up summary : • All works on “The IBR-2M physical start-up research program” have been successfully completed on June 9, 2011 in accordance with the plan. • Some malfunctions of ASCS -12R’ channels for control of a power pulse have been revealed, which are being debugged by the developers. • Experimentally measured characteristics of the IBR-2M reactor correspond to calculated design values.

  4. Preparation for the first power and for first physical experiments at n-beams

  5. Program of physical experiments will started at mean power of the reactor of 200÷300 kW (~ since July 8) IBR-2M spectrometers complex Spectrometers ready to start experiments : DIN-2PI, YuMO, HRFD, REMUR, REFLEX, FSD, DN-12 Spectrometers under modernization until the end of 2011: SKAT/EPSILON, NERA-PR, DN-2 New spectrometers in construction: DN-6, GRAINS (basic configurations should be finished by the end of 2011)

  6. Tasks and terms of work at the first power stage

  7. Program of the reactor characteristics research at power levels of 500 kW, 1000 kW, 1500 kW, 2000 kW

  8. Displays of IBR-2M reactor parameters at the operator control desk

  9. Start of the reactor first power Display of IBR-2M reactor parameters at the operator control desk Mean power (W) of the reactor is 300 kW (July 8)

  10. Start of first test experiments at the reactor. Mean power is 300 kW (July 8). Indication of the beams shutters at the operator control desk. Beam 5 is open.

  11. The plan of the main activities in 2011

  12. The plan of the main activities in 2011 (continued) Cryogenic moderators

  13. The plan of the main activities in 2011 (continued)

  14. Main tasks of 2011 Completion of the IBR-2M reactor first power. Realization of the research program at n-beams. Work on installation of the cryogenic moderator for beams 7-11 to the reactor. Preparation for the licensing on regular operation of the reactor since 2012.

More Related