This briefing provides a comprehensive update on unfinished water and sanitation infrastructure projects, including augmentation projects, strategic asset management, and sanitation initiatives. Details are outlined for the Northern Cape and Free State provinces, highlighting progress, challenges, and solutions for completing critical infrastructure. Key focus is on bucket eradication programs and regional bulk infrastructure projects.
E N D
BRIEFING THE PORTFOLIO COMMITTEE ON WATER AND SANITATION ON UNFINISHED INFRASTRUCTURE PROJECTS DDG: IBOM
TABLE OF CONTENTS • AUGMENTATION PROJECTS • STRATEGIC ASSET MANAGEMENT (DSRP) • SANITATION (BUCKET ERADICATION PROGRAMME) • RBIG PROJECTS
BUCKET ERADICATION PROGRAMME Status Report • NORTHERN CAPE PROVINCE • DWS resolved to utilise it Internal Construction Unit for the completion of 4of the 6 Projects of which; • 4 projects require Sewer Collectors and Bulk Mains to allow for functional sanitation services. • Of which 2 projects will require Pump stations; • A further 2 projects will be completed by the Water Services Authority (as a WSIG Schedule 5B grant allocation). • (DawidKruper LM, LouisvalePS: a PSP is already appointed, contractor is planned to be appointed in Feb 2019. • Siyancuma LM, Breipaal PS: PSP / Contractor already appointed. Planned to start with construction in Feb 2019. 9
FREE STATE PROVINCE • A turnkey contractor was appointed to complete the Bucket Eradication Programme in the Free State Province • the Department issued a notice of intention to terminate the relationship after the contract lapsed in March 2018; • 1 out of 12 projects remains incomplete • Senekal requires the completion of internal reticulation; • The Department resolved to utilise Internal Construction for the completion of Bulk infrastructure of which; • 7 projects requires bulk services to enable the flushing of new toilets;