1 / 24

SOLAR IMPACT ON FYI

SOLAR IMPACT ON FYI. Kevin Meikle, Architect Airports Planning Manager 4995 E. Clinton Way Fresno, Ca 93727 (559) 621-4536 kevin.meikle@fresno.gov. Rental Car Facility. Consolidated QTA – Increased Efficiency. Rental Car Ready and Return.

bin
Download Presentation

SOLAR IMPACT ON FYI

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. SOLAR IMPACT ON FYI Kevin Meikle, Architect Airports Planning Manager 4995 E. Clinton Way Fresno, Ca 93727 (559) 621-4536 kevin.meikle@fresno.gov

  2. Rental Car Facility Consolidated QTA – Increased Efficiency

  3. Rental Car Ready and Return No Busing, Solar-Ready, & Increased Customer Service

  4. Nation’s Largest Airport Solar Farm 58% of FYI Energy Demand

  5. Overview • 4.2 MW Hours Per Year Production • Online June 15, 2008 • Operating at Full Capacity • 11,700 panels totaling 2.4 MW • Twenty (20) Acre Site • No Alternative Use • Over $19 Million in Projected Energy Savings Solar Project By the Numbers

  6. The Process • Research Delivery Opportunities • Minimal or No Airport Capitol = PPA • Provider Owns, Operates, Maintains System • Other Options Necessitated Airport Capitol • Evaluate Site Options • Best Use of Land • Engage FAA Solar Project Process

  7. Solar Project Process

  8. Solar Project Process

  9. The Process • Apply for CPUC Incentives • Through PG&E • Refundable Deposit • SGIP and CSI Programs • Generate RFP • Clear and Concise • Commitment to Project and Provide Project Schedule • On Street 4 weeks, Conduct a Pre-submittal Meeting • Not a Public Works Project Solar Project Process

  10. The Process • Pre-submittal Meeting • Competition is the Grid • Overview of Your Expectations • Site Visit • Submittal Evaluation/Consultant Selection • Best Value • Financial and Technical Ability • Interviews Solar Project Process

  11. Solar Project Comparative Data

  12. Airport executes Power Purchase Agreements (PPA) • Fixed Price for 20 years • Reversionary Clause for Installed Equipment • Airport and World Water Participate in PG&E/CPUC Programs • 2006 Self-Generation Incentive Program • 2007 California Solar Initiative • 2006 SGIP • Fixed Price 20 years • $0.187 per KwH Guaranteed by PPA #1 • Projected Savings to Begin at year 7.5 (Actual at Year 2) • 2007 CSI • Fixed price 20 years • $0.1390 per KwH. Guaranteed by PPA #2 • Projected Savings to Begin at year 2.4 (Actual at Year 2) Solar Project Key Deal Points

  13. The Process • Contract Execution • PPA – Due Diligence • Board Approval • Environmental – NEPA/CEQA • Work With FAA on Appropriate NEPA Process • For Our Site – Biological and Cultural Resources Studies • CATEX – determined appropriate • Work with Local Body for Appropriate CEQA Process Solar Project Process

  14. The Process • FAA Involvement • Communicate Often and Early • 7460 – Do Your Homework • Reflectivity – Was a Non-Issue • Design and Construction • Stay Close to the Process • Coordinate on the Local Level as Necessary • Commissioning • Provider Took Lead • 30 Days Solar Project Process

  15. Partner Contributions & Benefits • PG&E • State Level Implementation for this Region • CPUC Incentives Flow Thru • Positive Image & Reduced Demand on Grid • World Water & Solar Technology • Technology • Financing • Long-Term System Operations and Maintenance Contract • Airport • Strong Local Political Commitment • Excellent Reuse of 20 Acres of Land (in approach zone) • No Financial Risk/$19 Million in Energy Savings Solar Project Public Private Partnership

  16. Solar Project FAA Processes

  17. Solar Project Photos

  18. Solar Project Photos

  19. System Performance Life-To-Date • 7,482,092 kwh produced • Savings of 7,484.2 tons of carbon dioxide • Projected performance of 4,200,000 kwh annually Last Month • 486,808 kwh produced • Planting of 1,921 trees • Driving 281,761 miles Solar Project webkiosk.mypvdata.net/c/fresno_airport/

  20. Solar Supports the Airfield LED Lighting

  21. Solar Supports the Terminal Energy Efficient Design, Common Use

  22. Future Opportunities • State CSI Incentive Program (now very low) • PPA • 2010 RFO – 1.5 MW Minimum • Land Lease Based RFP • Facility Based RFP • Google PG&E 2010 RFO • Airport Owned and Maintained – Capitol $$$ BecomingSustainable One Green Step at a Time!

  23. BecomingSustainable One Green Step at a Time!

  24. Environmental StewardshipSustainability IntegrationOne Step at a TimeOngoing Process Thank You webkiosk.mypvdata.net/c/fresno_airport

More Related