Board of Education Update February 09, 2012 . Good Evening!. Board of Education Project Update. MEET HOLLIS + MILLER. Overall Project Schedule Jan 2012 - Construction Documents Wrapping Up Feb 2012 - Final “Quality Control” procedures Mar 2012 - Bidding + Negotiating
E N D
Board of Education Update February 09, 2012 Good Evening!
Board of Education Project Update MEET HOLLIS + MILLER Overall Project Schedule • Jan 2012 - Construction Documents Wrapping Up • Feb 2012 -Final “Quality Control” procedures • Mar 2012 - Bidding + Negotiating • Aug 2012 – Park Hill High School Cafeteria • Aug 2013 - Construction Complete Staff Input Process • Overall “Master Plan” Approach • Building Level Faculty and Staff Input • District Leadership Team Scope of Projects • Park Hill High School $3,320,000 • Congress Middle School: $2,537,000
Park Hill High School Additions A-High School Café Expansion -Expanded Student Dining (144) -New Staff Dining Area (36) -Staff Development Room (110/130) -Designed for Community Use (after-hours) View of addition from Barry Road
Park Hill High School B-Classroom Expansion -Expanded Student Classrooms (6) -New Science Labs + Prep Area (2) -Two Story Classroom Additions View of addition from the South
Park Hill High School C-Counseling Suite Renovation -Provide for Additional Counselor -Improved Registrar location/storage -Improved Reception + Work areas -Additional Conference Room
Congress Middle School Additions A-Classroom + Activity Spaces -New Student Classrooms (6) -New Team Activity Spaces (2) -Design for improved daylighting
Congress Middle School Additions B-Band + Science Labs -New Science Labs (renovated space) -Band + Storage Room (renovated space) C-Speech / Publications -New Lab Space (renovated band rooms)