1 / 26

D.Manglunki presenting the work of

Primary Ion Beams in the North Area: Design of the Safety Interlock Information for SPS-OP 14/2/2014. D.Manglunki presenting the work of T. Hakulinen, F. Havart , S.Hutchins , P. Ninin , P.Odier , S.Reignier , F. Valentini , D. Vaxelaire , & colleagues. Motivation.

binh
Download Presentation

D.Manglunki presenting the work of

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Primary Ion Beams in the North Area:Design of the Safety InterlockInformation for SPS-OP 14/2/2014 D.Manglunki presenting the work of T. Hakulinen, F. Havart, S.Hutchins, P. Ninin, P.Odier, S.Reignier, F. Valentini, D. Vaxelaire, & colleagues.

  2. Motivation • Until recently, primary ion beams could be sent towards the North Area only during periods where no protons could be present in the SPS (ex: Pb ions at 13 & 80 GeV/u in December 2010, during PS proton injection septum fault). • For the forthcoming Ar, Xe, and Pb runs, it is foreseen to intermix both proton and ion cycles in the same super-cycle. • Although highly unprobable, it itnot impossible in these conditions to extract a high intensity primary proton beam to the North Area, exposing personnel to a radiation hazard: • Wrongly programmed injection of protons on an ion cycle • Accidental firing of the extraction elements during a high intensity proton cycle • Installation of a slow extraction proton cycle (SFTPRO) during primary ion operations • The principle of an interlock based on BCTs, preventing the extraction of a beam more intense than 2x1011 charges, has been proposed by the SPS OP team leader, and approved by the Beams Department Safety Officer in March 2009.

  3. Technical Solution • Two BCTs installed in BA5, measure the beam intensity and give veto signal if I>2x1011 charges. • The interlock acts on the power supplies of extraction magnets MST and MSE in BA2, forcing them to quasi-zero current if the interlock gives a veto signal. • The interlock function is activated by an “Ion-mode” key in the CCC • Diversely redundant designat the level of measurement, control, transmission & action

  4. Implementation • Respect norms IEC 61511 (process industry) and IEC 61513 (nuclear installations). • Two interlock chains: PLC and wired interlock(response time < 200 ms). • PLC chain based on SIEMENS S7 300 CPU and remote I/O with fiber optic cabling. • Wired chain based on HIMA Planar 4 modular wired logic. • See technical spec EDMS 1146023.

  5. BCTs • Pure hardware solution for maximum reliability and availability • 2 new DCCTs, designed and made at CERN, installed in June 2012 in SPS point 5 • Identical and independent systems • Permanent monitoring of the circulating beam intensity (IB) • Comparator on the analogue signal • threshold @ 2x1011charges • Self-check system to assess the DCCTs performance • 2 status sent to the interlock system indicating • whether IBis > or < 2x1011 charges • whether the DCCTs are available or under test • Real-time software for remote monitoring

  6. Self-check principle • Continuous check: • Performed in the DIAGNOSTIC UNIT • Assessment of important DCCT parameters: • Current consumption • Demodulation signal amplitude • etc. • Quick Check: • Performed automatically once per cycle before injection in the CHECK & COMPARATOR UNIT • Verification of the DCCT and comparator responses to a sequence of 6 calibrated current pulses injected into the monitor • Results stored until the next Quick Check • Validity period fixed to 60s One should tune the right balance between check severity and system availability

  7. Status delivered to the Interlock System Each DCCT delivers 2 status and their complements to the 2 different inputs of the Interlock System (PLC and wired) Galvanic insulation by opto-couplers • LOW_IB_STATUS • TRUE IF Ib < 2x1011charges • AND Self-Check result is OK • AND NOT_IN_CHECK_STATUS is TRUE • NOT_IN_CHECK_STATUS • TRUE when the DCCT and the comparator are available, i.e not in quick check process

  8. Acting on the REF-in of the converter to prevent extraction, forcing it to Imin Feedback to check I=Imin Check if system actually prevented an accident, in which case DSO action is required Actuator card between the Mugef and the Converter control crate -> direct control on the current reference MSE-MST power supplies

  9. Normal behaviour: extraction of low intensity beam • The reference simply passes through the card (REF-OUT=REF-IN) as the NO_EXTRACT_VETO signal from the Interlock is high, allowing extraction. Status NO_REF_FAULT DCCT2 Ierreur - + Idcct I> Carte Ions/Protons Interlocks REF-OUT (Control crate) REF-IN (Mugef) I0 REF Imin REF Imin INTL-FAULT REF – IN < I0 NO_EXTRACT_VETO (PLC) Reset with Key AND NO_EXTRACT_VETO (Wired)

  10. Normal behaviour: high intensity beam, no extraction The BCTs detect an intensity I>2x1011 charges: One of the NO_EXTRACT_VETO signal from the interlocks (PLC and Wired) is low The reference is forced to Imin=(720A for MSE ; Imin=225A for MST), minimum current reference given by the CCC, inhibiting the pulse converter. Status NO_REF_FAULT DCCT2 Ierreur - - + + Idcct I> Carte Ions/Protons Interlocks REF-OUT (Control crate) REF-IN (Mugef) I0 REF Imin REF Imin INTL-FAULT REF – IN < I0 NO_EXTRACT_VETO (PLC) Reset with Key AND/OR NO_EXTRACT_VETO (Wired)

  11. Abnormal behaviour • First Case: The signals NO_EXTRACT_VETO are low. The current reference REF-OUT is forced to Imin. • In the second step, a reference REF-IN (above I0) is still received. • This abnormal case should be analysed: A signal INTL-FAULT is generated and the converter is stopped. • Second Case: The converter of a pulse cycle is allowed, the REF-IN is greater than I0. • In the second step, the signals NO_EXTRACT_VETO become low: This abnormal case should be analysed. The associated actions are: • The reference REF-OUT is forced to Imin. • A signal INTL-FAULT is generated and the converter is stopped. • If either of these cases occurs, a fault in the converter will be activated, which can only be reset with a key. This key will be available to authorized persons competent to reset this fault (DSO), after an analysis of the fault event.

  12. Abnormal behaviour First Case: The signals NO_EXTRACT_VETO are low. The current reference REF-OUT is forced to Imin. In the second step, a reference REF-IN (above I0) is still received. This abnormal case should be analysed: A signal INTL-FAULT is generated and the converter is stopped. Second Case: The converter of a pulse cycle is allowed, the REF-IN is greater than I0. In the second step, the signals NO_EXTRACT_VETO become low: This abnormal case should be analysed. The associated actions are: The reference REF-OUT is forced to Imin. A signal INTL-FAULT is generated and the converter is stopped. If either of these cases occurs, a fault in the converter will be activated, which can only be reset with a key. This key will be available to authorized persons competent to reset this fault (DSO), after an analysis of the fault event. Status NO_REF_FAULT DCCT2 Ierreur - - + + Idcct I> Carte Ions/Protons Interlocks REF-OUT (Control crate) REF-IN (Mugef) I0 REF Imin REF Imin INTL-FAULT REF – IN > I0 NO_EXTRACT_VETO (PLC) Reset with Key FAULT AND/OR NO_EXTRACT_VETO (Wired)

  13. Status as of today (February 2014) • 2 BCTs installed in BA5 and tested with beam • Design of power supply safety system done; implementation being done TE/EPC • Interlock design done and internally tested. • Interface to BCTs tested. • NOW: approbation of the Technical Spec. • Final version of the BCT/Comparator electronics • MST/MSE power supply interlocking electronics • Installation of one Fast BCT (additional beam monitoring) • Global BCT/Comparator system commissioning without beam • Interface to MSE/MST final testing. • Inter-site cabling: • BA5, CCC, CCR done. BA2 planned for March. • All Fiber-optics cabling finished • Integration tests with all components will be connected early 2014. • Finalization of installation and test documentation. • DSO-tests to be scheduled before SPS start-up.

  14. Thanks for your attention!

  15. Typical SPS Super-cycle North Area Ion cycle with slow extraction HiRadMat proton cycle LHC proton cycle

  16. Geographical Layout

  17. Interlock Schematic System monitoring interface using TIM

  18. Development Model

  19. SIF 1: Avoid high intensity proton beam extraction to north area in ION mode TRIGGERING EVENT- DCCT 1 CHECK WATCHDOG INVALIDATION: TRIGGERING EVENT- SAFETY VETO REMOVAL FROM MST/MSE TRIGGERING EVENT- DCCT 2 CHECK WATCHDOG INVALIDATION:

  20. SIF 2: Send and maintain veto to BIS in case of MSE/MST malfunction TRIGGERING EVENT- SPS SAFETY BEAM DUMP REQUEST:

  21. General layout In red: Minimum system required to fulfil the initial specification In green: Monitoring, remote diagnostic tools + acquisition + logging

  22. Time diagram 4 Cases Range 3 Extraction Permitted NO Extraction NO Extraction NO Extraction Will be NOT_IN_CHECK_STATUS in the final version

  23. Acquisition, monitoring and logging • Acquisition via a RT program running in the FEC (Front End Computer) • 1 FEC per DCCT • ADC • 16 signals per system (Beam intensity on 4 ranges, system 1 and 2, status, etc.) • Sampling rate: 100 S/s • Start 900ms before injection • Stop ~20ms after ejection • Reading after ejection • Input Register • 17 status per DCCT (result of every elementary check, etc.) • Reading after ejection • Data publication via a FESA class once per cycle after ejection • Logging • Timber system • To be decided: • Which signal (Beam intensity, LOW_IB_STATUS, NOT_IN_CHECK_STATUS?) • What time resolution?

  24. Test with beam (SPS.LHC4; 12.10.2012) Real signals seen via the FESA Navigator ADC bin Will be NOT_IN_CHECK_STATUS in the final version Time [ms]

  25. BCT Planning • March 2009 Specification draft • April 2010 ECR 1075945 v1 • Jan 2011 Cable pulling for provisional location (BB5) • May 2011 Writing the technicalspecification (v1) • June2012 ECR 1075945 v2 • Sept 2011-May 2012 Manufacturing of mechanics • March - June2012 Building the electronic prototypes • June 2012 Installation of 2 monitors in point 5 • Since August 2012 Test of DCCT & Soft RT programme • Jan-Feb 2013Tests with the Interlock system • LS1-Cable pulling for final location (BA5) -Approbation of the technical specification -Make final version of the electronic -Installation of one Fast BCT (additional beam monitoring) -Global System Commissioning without beam • After LS1 -Global System Commissioning with Beam -Operation with Ions Beam in North Hall Now Required for the next step

  26. Actuator card between the Mugef and the Converter control crate -> direct control on the current reference • However, setting the current reference to Imindoes not guarantee that in the case of a malfunction of the electronic control of this converter, the current in the circuit is actually Imin • Supplementary DCCT measures the converter output current • compared to the input reference current “REF-IN”, giving us an error signal “Ierror”. • If difference too large, comparator drives a relay into fault (open) position and cause action on the beam(signal NO_REF_FAULT). • DCCT status managed by “Ion/Proton actuator card”: • DCCT dry status contact connected in series with relay contact -> any problem with the DCCT will also cause appropriate action on the beam (signal NO_REF_FAULT). Idcct DCCT2 Crate Status Mugef INTL-FAULT REF-IN Crate Ions/protons Interlocks NO_EXTRACT_VETO (PLC) NO_EXTRACT_VETO (Wired) REF-OUT RESET with KEY NO_REF_FAULT Converter control crate

More Related