Indirect Gasification of Municipal Solid Waste Team Bravo EleftheriosAvtzis David Garcia Bryan Isles Zack Labaschin Alena Nguyen Mentor Dan Rusinak Che 397 - Team Bravo
Process Review Indirect gasification of RDF using TBE process Providing Syngas to Team Alpha Location: Newton County Landfill in Brooke, IN Environment, Economy and Energy Che 397 - Team Bravo
Indirect Gasification The TBE process is a three unit, indirect gasification process The oxidizing agent is steam, therefore no air or ASU is required Olivine is cycled between the three units: gasification, combustion and gas conditioning Che 397 - Team Bravo
Engineering Specifications Che 397 - Team Bravo
Location Newton County Landfill 265 Acres Room for expansion Access to MSW of South Chicago Transportation No river access
The Three E’s Eco-friendly: low NOx, no dioxins and landfill cleanup lowers methane Economical: great IRR, get paid to remove trash, provides electricity and steam Energy: synthesis gas sent to Team Alpha becomes gasoline Che 397 - Team Bravo
PFD - Main Che 397 - Team Bravo
PFD - Main Che 397 - Team Bravo
PFD - Main Che 397 - Team Bravo
PFD – TBE Che 397 - Team Bravo
PFD – TBE Che 397 - Team Bravo
PFD – Reformers Che 397 - Team Bravo
PFD – Reformers Che 397 - Team Bravo
Sinks and Loads Che 397 - Team Bravo
Capital Investment Overview Che 397 - Team Bravo
Salaries and Fringes Che 397 - Team Bravo
Rough NPV- Annual/Rev. Costs Che 397 - Team Bravo
Rough NPV- One Time Costs Che 397 - Team Bravo
Economic Overview Che 397 - Team Bravo
Economic Sensitivity Analysis Che 397 - Team Bravo
Report Outline • Executive Summary - Done • Discussion - IP • Recommendations - IP • Appendices - IP • Design Basis - Done • Block Flow Diagram - Done • Process Flow Diagram - IP • Material and Energy Balance - Done • Calculations - Done • Annotated Equipment List - IP • Economic Evaluation - IP • Utilities - IP • Conceptual Control Scheme - IP • General Layout of Major Equipment - IP • Distribution and End-Use Issue Review - IP • Constraints Review - IP • Applicable Standards - IP • Project Communications File - IP • Information Sources and References - IP Che 397 - Team Bravo
References • Municipal Solid Waste (MSW) to Liquid Fuels Synthesis, Volume 1: Availability of Feedstock and Technology (PNNL-18144) • Municipal Solid Waste (MSW) to Liquid Fuels Synthesis, Volume 2: A Techno-economic Evaluation of the Production of Mixed Alcohols (PNNL-18482) • www.taylorbiomassenergy.com - TBE • www.rentechinc.com – Rentech • Engineering Toolbox • Heats of formation: http://cccbdb.nist.gov/hf0k.asp • Municipal Solid waste Generation, Recycling, and Disposal in the United States: Facts and Figures for 2008 – EPA • Higman, Christopher and van derBurgt, Maarten. Gasification 2nd Edition. Gulf Professional Publishing. Oxford, 2008. • Paisley, Mark A., Corley, Ralph N. and Dayton, David C. Advanced Biomass Gasification for the Economical Production of Biopower, Fuels, and Hydrogen. Taylor Biomass Energy
Back up: Ash Material Balance Che 397 - Team Bravo
Backup: Economic Sens. Analysis Che 397 - Team Bravo
Aspen Flowsheet Che 397 - Team Bravo
Aspen Flowsheet Che 397 - Team Bravo
Aspen Flowsheet Che 397 - Team Bravo