An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. NMDPS - MTD Oversize/overweight Permitting System Project

  2. Request for Implementation Certification Implementation Phase NMDPS - MTD Oversize/overweight Permitting System Project • EXECUTIVE STAKEHOLDERS • Executive Sponsor - Secretary Gregory J. Fouratt • Business Owners • PETE N KASSETAS, Chief DPS • RON BURTON, DPS CIO • Project Manager – Cesario Alvillar

  3. NMDPS - MTD Oversize/overweightPermitting System Project Project Overview MTPD provides trip permits, oversize/overweight permits and routing to commercial carriers that operate on our highways • This project is to replace the current outdated system • Selected vendor is ProMiles Software Development Corporation • System has been used in 5 other states before New Mexico • The system will provide: • Oversize/overweight permits • Accurate routing to carriers • Advanced technologies – mapping, routing, web based • Improved system response time • Timely trip permits • Automated and less labor intensive • System uses map data for routing to be housed at the Earth Data Analysis Center (EDAC)

  4. NMDPS - MTD Oversize/Overweight Permitting System Project Certification History • Project Initiation Certification - 1/2012 • Amount - $50,000 • Funding Source - FFY11 Federal Motor Carrier Safety Administration, Commercial Vehicle Information Systems and Networks, (CVSN) • Planning Certification - 02/2013 • Amount - 0 • Implementation Certification request - 04/23/14 • Amount - $1,434,752 • Funding Source – Taxation and Revenue Tax ID Permit Funds

  5. NMDPS - MTPD Oversize/Overweight Permitting System Project Project Funding History • Funding Source - FFY11 Federal Motor Carrier Safety Administration, Commercial Vehicle Information Systems and Networks (CVISN) • $50,000 • Funding Source - FFY11 Federal Motor Carrier Safety Administration, CVISN • $386,403 • Taxation and Revenue Tax ID Permit Funds • $682,074 • General Fund - 51stLegislature, second session Laws 2014, chapter 63, Section 4, pp. 145-148 • $366,274 Total $1,484,752

  6. NMDPS - MTD Oversize/overweight Permitting System Project Current Status • Selected vendor is ProMiles Software Development Corporation (PSDC) • System is used in 5 states, New Mexico will be number 6 • The vendor, PDSC, will be providing an offsite hosted solution in Las Cruces, NM • Backup site in Dallas, TX • SOW for EDAC map data completed • PSDC Contract ready for review and approval

  7. NMDPS - MTD Oversize/overweight Permitting System Project PCC Request • Request for release of funds in the amount of $1,434,752 for implementation phase

  8. NMDPS - MTD Oversize/overweight Permitting System Project Thank you Questions?