MAMM Readiness Review Acquisition Plan
MAMM Acquisition Plans • Three plans, all identical. First data take: • orbit 73-105, 19:35:57 UTC 3 Sept • orbit 74-105, 19:35:57 UTC 27 Sept • orbit 75-105, 19:35:057 UTC 21 Oct • 4 “replans” since final delivery. • 3 F1 acquisitions extended, 2 F1 acquisitions connected (all ascending) • Any replanning done in first cycle will become “nominal” plan for remaining two.
SAR, OBR & Station Usage • Total SAR on-time: 1506.5 min. • RTM: 910.5 min • OBR: 596.0 • Total Number of Data Acquisitions: 818 • RTM: 532 • OBR: 286 • Fairbanks: 105 • Gatineau: 104 • Prince Albert: 77
Acquisition Plan Errata • Standard-5 used on 3 occasions in ascending plan. • 172.78056 • 174.77696 • 315.77602 • No data acquisition on 4 orbits: • 82, 83, 229 and 296