140 likes | 164 Views
Learn about the two-phased development of the LION/LION2 regional cable system, partnerships, technical characteristics, deployment challenges, protection schemes, diversity of landings, and managing delays effectively.
E N D
CHALLENGES AND LESSONS LEARNEDDURING THE TWO PHASED DEVELOPMENT OFTHE LOW INDIAN OCEAN NETWORK SUBMARINE CABLEFrancis Charpentier, Cynthia Perret, Patrick Daniel, Jean-Claude Marc (France Telecom Orange)Caroonanaden Seeneevassen, Pranilsingh Gobin (Mauritius Telecom)Jean-François Glenet (Société Réunionnaise du Radiotéléphone)Paul Lefébure, Vikram Ramgolam (EMTEL Ltd.)Arson Benja (Orange Madagascar)Andrew Kemosi, Vitalis Mwakidedi (Telkom Kenya) Paris, 24 April 2013 2013 SubOptic Conference
The LION / LION2 regional cable system LION LION2 System - Poster Presentation - 24 April 2013
THE LION/LION2 SUBMARINE CABLE SYSTEM CABLES INTERCONNECTED • SAT3 / SAFE • UAE/KENYA (« TEAMS ») • EASSy • SEACOM COUNTRIES INTERCONNECTED • Kenya (LION2) • Mayotte (LION2) • Mauritius (LION) • Madagascar (LION) • La Réunion (LION) TECHNICAL CHARACTERISTICS • 2 fiber pairs • Initial wavelengths 10Gb/s OOK • Initial equipped capacity 2 x 10Gb/s per FP • Initial design capacity 640 Gb/s per FP • Upgradeable with 40Gb/s and 100Gb/s technology • New maximum capacity 2.7 Tb/s per FP LION LION2 System - Poster Presentation - 24 April 2013
Phase 1 : Building LION Kenya 3 100 km anticipated longest link LION Started service in December 2009 dormant BU La Réunion Madagascar Mauritius 800 km repeatered MSP1+1 protection 280 km unrepeatered MSP 1+1 protection LION LION2 System - Poster Presentation - 24 April 2013
Phase 2: Building LION2 (step 1) Kenya Mayotte LION2 under construction BU connexion was last operation of cable laying La Réunion Madagascar Mauritius LION in service MSP1+1 protection MSP1+1 protection LION LION2 System - Poster Presentation - 24 April 2013
Phase 2: Building LION2 (step 2) Kenya Mayotte LION2 started service in April 2012 using « mesh restoration » protection BU switched to final configuration during commissioning La Réunion Madagascar Mauritius LION in service LION changed to « mesh restoration » protection during LION2 commissioning LION LION2 System - Poster Presentation - 24 April 2013
CABLE PARTNERS A second consortium was established to own the LION2 part of the system Both consortia interact closely and share committees (O&M SC, AR&R SC, PG) LION2 consortium Telkom Kenya LION consortium Société Réunionnaise du Radiotelephone (SRR) Orange Madagascar Mauritius Telecom Orange EMTEL Ltd LION LION2 System - Poster Presentation - 24 April 2013
NECESSARY CARE DURING LION2 DEPLOYMENT • Make sure LION2 deployment operations did not impact LION service operation • Possible causes for impacts were identified… • Connection of the LION2 cable to the dormant BU • Switching BU from LION nominal state to LION+LION2 nominal state • … and mitigated • All LION2 was laid before dormant BU connexion • BU connexion was carried out during low traffic hours • BU was switched to its new nominal state during low traffic hours LION LION2 System - Poster Presentation - 24 April 2013
CHANGING THE PROTECTION SCHEME • Initial Protection scheme : MSP 1+1 • It was well adapted for the initial LION configuration (two point-to-point links) • But it doubled capacity use for the purpose of protection • New protection scheme : Mesh restoration • Based on G-ASON (GMLPS) • Classical ring protection on the repeatered part of the system would double the capacity use (like MSP 1+1) • Classical ring protection is not so interesting for the new configuration (the repeatered part is a small ring with 4 nodes) • Mesh restoration offers very good flexibility • A range of protection level are possible • Protection is managed on a VC4 circuit basis LION LION2 System - Poster Presentation - 24 April 2013
DIVERSITY OF LANDINGS AND CABLE STATIONS • Diversity of landing and station was ensured in all three landings were other cables already existed • Mauritius: diversity w.r.t. SAFE • La Réunion: diversity w.r.t. SAFE • Mombasa: diversity w.r.t. UAE-KENYA, EASSy, SEACOM LION LION2 System - Poster Presentation - 24 April 2013
The LION / LION2 Cable System Diverse landings wrt other cables LION LION2 System - Poster Presentation - 24 April 2013
THE MAYOTTE LAGOON • The Mayotte lagoon contained an area (4 km wide) with many coral outcrops (pinnacles) • Around 30 suspensions were observed in that zone after initial cable lay • All suspensions were sucessfully removed by diver teams LION LION2 System - Poster Presentation - 24 April 2013
KEEPING DELAYS UNDER CONTROL PERMITTING DELAYS • Permitting is a process specific to each country and the date of delivery is often difficult to predict • After an initial phase of overconfidence, unexpected delays were observed for one of the landing permits • We came close to a situation where the cable ship would be held up waiting at the limit of the territorial waters • Better anticipation would have been needed • A more flexible contractual framework with suppliers to handle such situations gracefully • We put in place a plan B for the landing site but it was not needed at the end of the day STATION DELIVERY DELAYS • The station site was depending on the landing site • Therefore we also put in place a plan B for an alternative station site • The delivery of the station was also delayed by the permitting delay • The critical point was the delivery of the final energy supply equipment • System commissioning started with a temporary energy supply setup • Final energy was up and running at the end of the commissioning LION LION2 System - Poster Presentation - 24 April 2013
CONCLUSION • The LION+LION2 system is a consortium-owned cable built in two phases • Moving from LION to LION+LION2 implied a significant context change • Extension of the consortium from 3 to 6 co-owners • Changing the protection scheme • The following challenges were successfully met • Ensure landing diversity for landings and sites providing interconnexion to other cables • Avoid any impact to LION operation when deploying LION2 • Keeping permitting and station delivery delays under control LION LION2 System - Poster Presentation - 24 April 2013