1 / 24

Progressive Design-Build: Examining the Basics

Progressive Design-Build: Examining the Basics. Michael C. Loulakis, Esq., DBIA President/CEO Capital Project Strategies, LLC mloulakis@cp-strategies.com. September 25, 2017. Introduction. Project delivery studies show benefits of Design-Build Done Right: Early contractor involvement

boothf
Download Presentation

Progressive Design-Build: Examining the Basics

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Progressive Design-Build: Examining the Basics Michael C. Loulakis, Esq., DBIA President/CEO Capital Project Strategies, LLC mloulakis@cp-strategies.com September 25, 2017

  2. Introduction • Project delivery studies show benefits of Design-Build Done Right: • Early contractor involvement • Highly qualified teams • Group cohesion and team integration • Most private sector owners readily understand these benefits • Qualifications dominated procurement practices • Collaborative development of design • Negotiation of ultimate project price

  3. Introduction (cont’d) • Unfortunate reality – many public sector owners do not use Design-Build Done Right • Price is often dominant selection factor • Use bridging documents vs. performance requirements • Little meaningful collaboration prior to contract award

  4. Introduction (cont’d) • Challenges created by these practices • Bridging documents can stifle innovation • Owners susceptible to change orders for problems in their design documents • Competitive procurements are costly and take time for all parties • Is there a way for owners to exercise substantial design control and comply with Design-Build Done Right principles?

  5. Progressive Design-Build’s Core Features • Design-builder retained by owner early in project’s life • Design-builder selected primarily, if not exclusively, on qualifications • Final project cost and schedule commitment is not established as part of the selection process • Two phases of work • Preliminary services • Final design and construction, once the parties have agreed upon price and other commercial terms

  6. Core Features (cont’d) • Design-builder collaborates with owner during Phase 1 to create or confirm project’s basis of design • Design-builder advances design • Decisions based on cost, schedule, operability, life cycle and other considerations • Ongoing, transparent, cost estimates to achieve budget requirements

  7. Core Features (cont’d) • Formal commercial proposal for Phase 2 • “Appropriate” level of definition, often at 40-60% design completion • Dependent on amount of control owner desires to maintain over design definition and reduction of contingency • Phase 2 initiated upon acceptance of commercial proposal

  8. Core Features (cont’d) • Owner right to exercise “off-ramp” • End relationship and use design to advance project • Right to have designer complete design and become designer-of-record • Early work packages for discrete work elements

  9. Why Owners Choose Progressive Design-Build • Interest in contracting with design-builder very early in design process • Complex projects requiring high level of collaboration • Higher degree of cost certainty and transparency during design development • Owner wants to remain actively involved in making design decisions • Avoids time and expense of owner creating design baselines for procurement • Streamlines and simplifies procurement process • Reduced or limited need for stipends

  10. Why Owners Choose Progressive Design-Build (cont’d) • Ability to use early work packages and fast track • Removes some of owner’s time pressures in reviewing and acting upon design submittals • Allows owner participation in subcontractor and supplier selection • Offers transparency into design-builder’s proposal cost • Provides collaborative way to establish “single point of responsibility” – there is no design “handover”

  11. Why Owners Choose Fixed Price Design-Build • Interest in awarding contract with full competition • Opportunity for more creative technical approaches • Opportunity for multiple technical approaches • Opportunity for best value and lower prices • Restrictive procurement regulations • Prohibit progressive design-build • Preclude early involvement of subcontractors

  12. Why Owners Choose Fixed Price Design-Build (cont’d) • Concerns over attributes of progressive design-build (e.g., negotiating price or exercising “off-ramp”) • Marketplace concerns with progressive design-build • Success and comfort in using fixed price design-build – procurement infrastructure already developed

  13. CMAR vs. Progressive Design-Build • Benefits of CMAR • Ability of owner to have a direct contract with a designer who is independent of contractor • Easier ability to exercise “off-ramp” • Benefits of progressive design-build • Owner does not have to manage/procure designer • Slight schedule benefit • Ability to obtain performance guarantee and other benefits of design-build

  14. Progressive Design-Build Procurement • Pick the right team through streamlined and simple procurement • The right team is the one that: • Will work well and collaboratively with owner • Offers best chance to meet owner’s project goals and required outcomes • Owner believes is trustworthy, fair, qualified and transparent

  15. QBS and Best Value • Qualifications based selection • Solely non-price factors • Team qualifications and past performance • Innovative ideas • No price information • Best value • Both price and non-price factors • Price factors might include Phase 1 services and overall design-build fee (low weighting)

  16. Other Procurement Decisions • One-step or two-step • Statutory requirements? • Deliverables required for shortlisted proposers? • Pricing information? • Proprietary meetings • Interviews • Stipends

  17. Lessons Learned from Procurement of Progressive DB Projects • Process may benefit in having Phase 1 services divided into 2 or more components • Confidential meetings are extremely valuable in obtaining real insights from proposers • Owners often try to resolve too many commercial and contractual details during procurement • Process benefits from post-award discussions • Contract will essentially be subject to modifications once contingency and risk pricing are developed

  18. Unique Contracting Issues • Scope of Phase 1 services, including cost modeling • Ability of design-builder to rely upon owner-furnished information • Early work packages • Design-builder self-performance • Subcontractor and vendor procurement and involvement in Phase 1 • Commercial proposal • Exercising off-ramp • Contract should reflect collaborative nature of relationship

  19. What Should an Owner Do to Prepare for Implementing Progressive DB? • Assess appropriateness of process • Use experienced consultants • Understand procurement limitations • Have a strong cost estimator on team • Make early decision on subcontractor procurement and design-builder self-perform • Ensure the team is willing and able to collaborate and trust

  20. Dulles Rail, Phase I • $1.6 billion contract for first phase of WMATA extension to airport • Virginia PPTA procurement process • Investment by design-builder in the preliminary engineering through unsolicited proposal • Negotiated lump sum price at completion of 30% design (preliminary engineering) after open book process • Project on line 2014 • Allowances used to overcome certain pricing issues • Interim agreements used to address ROW/utility/design issues pending federal funding

  21. DC Water Headquarters • New HQ to be built over an operating pumping station • 2-phase procurement with shortlist of 3 • Design competition – iconic design that would satisfy permitting agencies, based on $55MM budget • $75,000 stipend • Skanska USA Building, with Smith Group as lead architect • Weighted criteria approach used for technical approach • Solicitation of only lead constructor and lead designer • Pricing information provided for informational purposes • Single contract with two phases • GMP proposal will be provided at 80% design

  22. City of Houston, Northeast Water Purification Plant Expansion Project • 320 MGD treated water facility • Estimated cost in excess of $1B • Approximately two years of preliminary engineering expected • Completion by 2024 • Two step procurement with shortlist of 3 • Best value approach, with price proposal to include: • Design-builder’s fee and Basis of Design services • Indicative pricing • Full contract approach • Early work packages expected • Solicitation of full teams

  23. Other Progressive Design-Build Projects • Substantial number of water/wastewater projects • Northern Treatment Plant, Colorado • South Florida Water Management District • Los Angeles World Airports • Port of Seattle International Arrivals Facility

  24. Progressive Design-Build: Examining the Basics Michael C. Loulakis, Esq., DBIA President/CEO Capital Project Strategies, LLC mloulakis@cp-strategies.com September 25, 2017

More Related