Portfolio Committee on Public Works: DPW Turnaround. 9 June 2015 Mr M Govender – Head of BIU. PART A: BACKGROUND & CONTEXT. Mr M Govender 9 June 2015. 1. BACKGROUND.
E N D
Portfolio Committee on Public Works:DPW Turnaround 9 June 2015 Mr M Govender – Head of BIU
PART A: BACKGROUND & CONTEXT Mr M Govender 9 June 2015
1. BACKGROUND • DPW Key Mandate: custodian & manager of State’s immovable assets (under Minister of PW) => directly impacts efficiency and effectiveness of all client departments and service delivery. • Corruption, mismanagement and poor performance led to DPW failing to deliver on its mandate. • Turnaround Strategy (7 Year Business Improvement Plan) was launched Jan 2012 (Ownership with DPW). • Core of the strategy (2 pillars) => • Zero tolerance of fraud & corruption • Improving business (Property Management) • Prior attempts at change failed due to leadership instability and ineffective change management. 7 Year Plan to rebuild DPW
1. BACKGROUND (Cont.) DPW Performance DPW audit PMTE audit 7 Year Plan to rebuild DPW
1. BACKGROUND (Cont.) • In 2011, following adverse audit findings and the then new Minister’s engagements with the Departmentconfirmed that the department was in a dire state, with areas of dysfunction. • High levels of fraud and corruption was evident in the findings of the Special Investigation Unit and the Public Protector. • In November 2011, the Minister requested assistance from the Technical Assistance Unit (TAU) of National Treasury, to provide a rapid diagnostic on the state of affairs within the Department. • The report and findings presented in January 2012, comprehensively detailed problems of mismanagement and misalignment and pointed to the need for fundamental reorganisation, and immediate interventions to stabilise the Department. 7 Year Plan to rebuild DPW
2. TAU’s DIAGNOSTIC FINDINGS Diagnostic findings assisted department to identify and set priorities for stabilisation actions . • Leadership instability - high rate of change of executive and administrative leadership. • Asset Management - Asset Register incomplete and inaccurate; • Prestige– poor planning and management; lacked policy, norms and standards. • Property and Facilities Management – state properties underutilised whilst private sector leasing-in expanding; below market rates for leased-out properties; over-expenditure on maintenance; maintenance backlog; aging properties; lack of professional property management skills; poor lease management systems; large number of bad debtors; and lack of client relations management. 7 Year Plan to rebuild DPW
2. TAU’s DIAGNOSTIC FINDINGS (Cont.) • Construction Project Management – lack of professional and technical skills; cost and time over-runs; poor quality control; under spending and maintenance backlog. • Inner City Regeneration (ICR) – delays in the implementation; partnership not translated into action; and under spending. • EPWP– performing well although there was poor reporting and only 50% of the incentive grant was disbursed in 2010. • Corporate Services – key skills shortage; lack of systems and controls; ICT system not supporting the DPW core business; ineffective management reporting systems; ineffective internal auditing; inappropriate organisational structure; poor controls in SCM; overpriced tenders; and lack of HR plan. • Policy and Regulation – The Department is implementer and regulator => conflict of interest. 7 Year Plan to rebuild DPW
3. STRATEGIC FOCUS • DPW role (MTSF & NDP) => job opportunities and jobs (EPWP) & infrastructure development. • Contribute towards other priorities (social, health, and security) => through accommodation provision. • Reconfigure strategic direction => • Projecting demand by establishing client needs • Address requirement for remedial attention: transparency, accountability, and oversight. • Business Improvement Unit (BIU) created => drive Organisational Review / Turnaround Strategy • initiated short-term stabilisation interventions. • 7 Yr Plan & Business Improvement Programme Three discrete phases: Stabilisation=>Efficiency=>Sustainability & Growth 7 Year Plan to rebuild DPW
4. IMPLEMENTATION PLAN (Time Line) Launched separate projects under the Turnaround umbrella limited to the Stabilisation Phase, others will continue for several years. 7 Year Plan to rebuild DPW 9
4. IMPLEMENTATION PLAN • Stabilisation– focused on immediate challenges. Stabilised areas, create the potential for more fundamental change => large efficiency gains. 2. Efficiency Enhancement – systematic improvements - redesign processes, systems and structural elements. Focus on key strategic areas to improve efficiencies and effectiveness 3 Operational Programmes: Property Management, DPW Business Improvement; and Transversal Business Improvement (PMTE & DPW) 3. Sustainability & Growth– policy review (refresh mandate of DPW family) – Public Works Act. Focus on sustainability & growth. 7 Year Plan to rebuild DPW
PART B:STABILISATION PHASE & ACHIEVEMENTS Mr M Govender 9 June 2015
1. STABILISATION OF MANAGEMENT LEADERSHIP & REVIEW OF ORGANISATIONAL STRUCTURE • Key management positions filled: • Director-General, • Chief Financial Officer, • DDG: Corporate Services, • Acting DDG: Governance, Risk and Compliance, and • Acting Head: Property Management Trading Entity • The review of the organisational structure has been completed. • Separate DPW as regulator from PMTE as implementer • Re-model and professionalize our property business in order to optimally utilise our massive property portfolio productively • To improve service delivery in the context of Government’s priorities and to save costs to the Department and the fiscus 7 Year Plan to rebuild DPW
2. OPERATIONALISATION OF PMTE2.1 Timeline • In 1997, DPW White Paper – User charges • In 1999, Cabinet approved establishment State Property Agency • In 2002, a joint NT/ DPSA Technical Committee recommended a trading entity approach. • In 2006, NT approved PMTE (subject to specified conditions) • Budgets were devolved to user departments • PMTE => became vehicle to effect user charges on accommodation. • NT directive not fully complied with => 8 years under performance culminating in adverse audit findings, (2 consecutive disclaimers by AG largely due to failure to operationalize the PMTE). • In 2012 Minister launched Turnaround Strategy with the operationalization of PMTE at core of strategy. • In 2014Cabinet Approval => Phased Implementation Plan to establish PMTE as a Government Component. Operationalisation of the PMTE
2. OPERATIONALISATION OF PMTE 2.2 Rationale & Focus • To improve service delivery in the context of Government’s priorities and to savecosts to the Department and the fiscusby: • Maintaining the value of Government’s assets • Improving access to and quality of Government’s assets • Optimal utilisation of State stock and move away from leasing-in • Utilise State’s vacant properties productively to create a funding stream for capital maintenance and improvements to extend the life-cycle of existing state properties; • To reclaimmandate of Public Works • develop small proclaimed and unproclaimed harbours • develop Government precincts in small towns and rural areas • safeguarding the State’s assets from vandalism, theft and invasion • reclaiming all misappropriated State land • preserve Government assets, structures, building, land parcels Operationalisation of the PMTE
2. OPERATIONALISATION OF PMTE2.3 Progress - National Treasury Conditions • Operate a separate and complete GRAP-compliant set of accounts – ACHIEVED • Effective financial controls in place – ACHIEVED • Policy and reporting framework in place to track both commitments and cash flow – ACHIEVED • All people and institutional arrangements in place – ACHIEVED 2014 (2015 REVEIW IN PROCESS) • Draft Delegations developed and responsibilities of the departmental key account managers specified – ACHIEVED 2014 (2015 REVEIW IN PROCESS) • DPW must seek approval from National Treasury to establish a Property Management Trading Entity. The PMTE must comply with all the conditions for trading entities contained in Treasury Regulation 19. - ACHIEVED Operationalisation of the PMTE
2. OPERATIONALISATION OF PMTE2.4 Progress - organisational • Acting Head of PMTE & key property management specialists appointed to drive the full operationalization of the PMTE. • Functions and immovable assets were transferred from DPW to PMTE • PMTE Account, moved from a disclaimed to a qualified opinion. • The PMTE business model developed to address the AG’s issues. • PMTE budget programme structure developed with National Treasury • The PMTE SP and APP developed in with DPME, NT, DPSA and Public Service Commission and tabled in Parliament (March 2015). • Business Case for establishing PMTE as Government Component developed and endorsed by Cabinet in August 2014. • PMTE structure developed with DPSA 7 Year Plan to rebuild DPW
3. IMMOVABLE ASSET REGISTER • State assets (land parcels) estimated at approx. 1, 2-million. (+/- 980 000 municipal, 125 000 provincial and 33 000 national). • Lack of clarity on the nature & extent of assets due to magnitude, extent and complexity • Need for mechanism to determine extent => comprehensive / holistic overview to reflect appropriately on the balance sheet of the SA. • Background: • 1995 - 1999, compiled computer-based inventory of immovable assets (national & provincial custodians) • 2005 - 2008 = Enhancement Programme on the identified 33 555 propertiesto address identified gaps • 17 May 2006 = Cabinet approved general land audit (DPW; Agriculture & Land Affairs; Provincial & Local Government; and Public Enterprises) • December 2007 => conduct physical verification, • 2009= put on hold => to verify the authenticity of data. 7 Year Plan to rebuild DPW
3. IMMOVABLE ASSET REGISTER • 2011 Turnaround launched =>IAR Programme (2011-2013) • Focused on the completeness of land parcels. • Moved from a disclaimer to qualification for immovable assets for 2012/13 (Qualification on valuation of immovable assets). • The IAR progressed from modified cash to accrual basis of accounting (GRAP) • Progress • Physical verification commenced in October 2013 => completed end of fin year 2014/15. • To date => verified 99.1% of the properties that were identified in July 2013 (Verification excluded Defence (verified by CSIR). • 37,012 (including deemed Provincial) properties • 6,567 State Domestic Facilities • DPW applied municipal values on approximately 66% of DPW’s immovable assets in 2013/14 - 14/15 • Vested 16,161 of 33 000 (finalise by 31 March 2016). 7 Year Plan to rebuild DPW
4. REAL ESTATE AND FACILITIES MANAGEMENT • Lack of lease-in management systems contributed significantly towards: negative audit outcomes / fraud & corruption. • Stabilisation Intervention focussed on audit of lease-ins and the reengineering of the lease-in business process. • Progress: Real Estate Management • Review of 2,162 office leases has been completed • Physical verification of occupancy and size of 2,143 leased buildings. • NT approved dispensation on renewal for leases that have expired. • As at April 2015, 1455 (92%) out of 1566 leases renewed with fixed 5.5% escalation rate => approx. saving of R33 million p/a • Of 112 NDPW “unoccupied but paid for” were investigated, 41 resolved and 71 handed to the SIU for forensic investigation. • Of 29 “occupied by other” properties, 6 have been resolved and 23 referred for forensic investigation. 7 Year Plan to rebuild DPW
4. REAL ESTATE AND FACILITIES MANAGEMENT • Progress: Real Estate Management (Continued) • Realigned Business Processes => payment of invoices within 30 days • Verification of 10,590 freehold properties for payment of rates & taxes • Verification of 7,700 freehold properties for payments of services • Lease Policy developed • Transferred assets to the PMTE: • 71 397 state owned structures that are leased out to 29 User Departments; • 1840 state owned structures that are privately leased out with 2 294 tenants; • 695 state owned prestige buildings leased out to 1062 prestige clients; • 2671 active leasehold portfolio 7 Year Plan to rebuild DPW
4. REAL ESTATE AND FACILITIES MANAGEMENT • Facilities Management => State’s property portfolio underutilised and neglected => numerous properties vacant, susceptible to theft, vandalism, vagrants, illegal occupation. (Services & security still paid) • PMTE delivery model and associated plans (SP/APP) developed to: • Project demand accurately by establishing client needs => Client Centric Approach • Optimally utilise our property portfolio productively to create funding streams for capital & planned maintenance programmes. • Progress • Worx4You – Single entry contact centre 24/7 (365) internally established (In-house)for Facilities/Prestige/ICT - trained 34 gradates • Needs assessments of key / identified buildings conducted • Cost analyses for key buildings conducted • Pilot energy & water saving initiatives • 50 public buildings retrofitted with energy efficiency technology +/- 672 mil Kwh saved since 2011 • 12 retrofitted with water efficiency technology +/- 7.5 mil kl saved 7 Year Plan to rebuild DPW
5. CONSTRUCTION PROJECT MANAGEMENT • Building technical and professional capacity in construction project management was at the centre of the stabilisation intervention. • 48 professional and technical positions were filled in the 2013/14 • As part of this capacity building programme: • contracts of 50 young professionals were extended, • 11 were absorbed into permanent positions, • 4 mentors were appointed to provide mentorship, and • 148 Water Care personnel were appointed. • With ‘growing our own’ intervention, DPW is running a Schools Programme supporting 10,000 learners for Maths and Science, and • Awarded 182 bursaries to students registered for tertiary level built environment courses. 7 Year Plan to rebuild DPW
6. CLEAN AUDIT Key objectives: • To assist the Department with: • Enhancement of the Financial Management function for both the NDPW (main account) and PMTE to improve audit outcomes • Enhancement of the Supply Chain Management function • Analysis of the challenges in delivering infrastructure projects • Development & implementation of change management strategy • Implementation of a skills transfer programme for existing staff – no unilateral delivering of outcomes (comprehensive involvement of staff in all deliverables) • To appoint unemployed graduates to assist with the implementation of this project. A clearly structured skills development plan for these unemployed graduates must be in place 7 Year Plan to rebuild DPW
6. CLEAN AUDIT Our Approach: Cycle 1 Cycle 2 Cycle 3 Planning & Set up 165 133 82 As-is To-Be Consortium design & implement Policies & Procedures Quality Control Protect-A- Partner Guidelines & Checklist Road Shows Quality Control Consortium Consortium implement On-the-job training DPW Staff Implement Hand over Quality Control Internal audit DPW Staff Implement Consortium Technical guidance 7 Year Plan to rebuild DPW 25
7. FIGHTING FRAUD AND CORRUPTION • The Department has revised and adopted an Anti-Fraud and Corruption Strategy. • Internal investigation backlog of 250 cases has been reduced significantly and investigations are currently instituted within 30 days of receipt of allegations. • Progress • To date => GRC received 296 allegations (39 in 2014/15), • 190 have been completed, • 67 at various stages of investigation, • 39 were referred to other Business Unit/ SIU / SAP • Emanating from investigations, • 156 disciplinary actions were recommended (100 finalised) • Sanctions issued ranges from dismissals, final written warnings, written warnings etc. 7 Year Plan to rebuild DPW
7. FIGHTING FRAUD AND CORRUPTION • To date 121 fraud awareness presentations conducted within DPW • Comprehensive Fraud Risk Assessment 2014/15 • identify, assess, and rate high fraud risks i.t.o. likelihood & impact • to incorporate in Fraud Prevention Plan. • Branches incorporated fraud risk mitigation plans in Business Plans • Implementation of the pilot phase of the Infrastructure Transparency Delivery Model. => roll-out July 2015. • Re-launching OBB (Operation Bring Back). Reclaiming State properties misappropriated or unlawfully occupied • Internal OBB programme to investigate and possibly recover properties: • disposed to other state custodians, private individuals, companies • transferred incorrectly/ unlawfully, • occupied unlawfully or encroached • sold at below market value where not donated for valid reasons. 7 Year Plan to rebuild DPW
8. SCM • SCM Policy aligned with the current procurement regulatory framework • Training on policy conducted across the entire DPW family. • New SCM structure developed to align with core business areas of DPW • SCM operational processes have been reviewed and improvements have been effected in the following areas: • An acquisition framework for both bid administration and quotations have been developed with checklists, templates, registers, etc. to ensure compliance and proper audit trail of SCM processes • Procedures for the registration of suppliers and management of the DPW’s supplier database enhanced. • Procurement aligned and executed in accordance with the DPW’s procurement plan. • Concept of a War Room to track progress of tenders to prevent under-expenditure and improve on service delivery, introduced. 7 Year Plan to rebuild DPW
9. EPWP • EPWP Phase 2 closed out, and planning for implementation for Phase 3 has been completed to give effect to the manifesto commitment to create 6 million work opportunities by 2019. • In November 2013, Cabinet approved the continuation of EPWP into Phase III with a target of creating 6 million work opportunities and commenced on the 1st of April 2014. • The revised Grant disbursement processes have improved Grant disbursement from 50% to 100% in 2012/13 and 2013/14. • Third phase of EPWP has already created 1.24 mill work opportunities against targeted 1,04 mill in first year of Phase III • Over achieved by approx. 120% 7 Year Plan in first year.
10. ICR • In collaboration with the City of Tshwane, the Master Plan for Tshwane Inner City has been completed and provides for the creation of 4 Precincts; • Seventeen (17) departments have been prioritised with high level needs. • Land parcels for development have been identified, and engagements with NT on funding models are being developed • As at February 2015, the Development Framework for Salvokop was completed and the Township Establishment application was submitted for approval. • The vision is to establish 6 – 9 head offices on Salvokop. A consent use for StatsSA Head Office on Salvokop was approved and the building of project is progressing well. 7 Year Plan to rebuild DPW
11. PRESTIGE • Prestige portfolio approx. 250 assets in Western Cape, KZN and Gauteng, (including: Parliamentary Estates, Parliament Precinct, Union Buildings and executive housing). • Key clients include: Presidency, Judiciary (Chief & Deputy Chief Justice), Ministers, Deputy Ministers, DGs (in Cape Town only) • Progress • Management Board established to oversee parliamentary villages. • Prestige services centralised in the Office of Director- General • Prestige structure approved • Norms and Standards developed for consideration by Cabinet. • Backlog on provision of furniture has been significantly reduced • Turnaround times on provision of furniture has been improved 7 Year Plan to rebuild DPW
12. 2012/13 EXPENDITURE REPORT 7 Year Plan to rebuild DPW
12. 2013/14 EXPENDITURE REPORT 7 Year Plan to rebuild DPW
12. 2014/15 EXPENDITURE REPORT 7 Year Plan to rebuild DPW
PART C:FUTURE – TURNAROUND PLANPHASE 2 EFFICIENCY ENHANCEMENT Mr M Govender 9 June 2015
TURNAROUND IMPLEMENTATION PLAN Phase 2: Efficiency Enhancement has been designed to include the 7 key areas identified as priorities for PMTE & DPW
TURNAROUND IMPLEMENTATION PLAN • Turnaround for second phase – Efficiency Enhancement - 2015/16 to 2017/18, to fast track efficiencies within the PMTE / DPW. • Projects will be funded from funding mechanisms within PMTE for a period of three (3) years. • Bulk of projects are specific to areas within the PMTE where improvement in service delivery is critical to the overall Turnaround • The following plans detail the respective project objectives, outputs, outcomes, and the cost associated with the interventions. • The Efficiency Enhancement Business Case and the comprehensive Turnaround plan is yet to be submitted to National Treasury. Once done – we will circulate it to Portfolio Committee. 7 Year Plan to rebuild DPW
TURNAROUND IMPLEMENTATION PLAN SUMMARY • Project 1: Establishment of the Turnaround PMO; • Project 2: Water Management; • Project 3: Small Town Precinct Development; • Project 4: Property rates and municipal services in arrears; • Project 5: Immovable Asset Register; • Project 6: Energy and Water efficiency monitoring &verification; • Project 7: Asset Management System Development; • Project 8: Small Harbours Unit: • Project 9: Public Private Partnership Office; • Project 10: Project “P” Project Office; • Project 11: Fight against fraud and corruption: • Project 12: Development and implementation SDMF; and • Project 13: Efficiency enhancement intervention towards a Clean Audit 7 Year Plan to rebuild DPW
TURNAROUND BUDGET 7 Year Plan to rebuild DPW
PROJECT 1: Turnaround Project Management Office 7 Year Plan to rebuild DPW
PROJECT 1: Turnaround Project Management Office (Cont..) 7 Year Plan to rebuild DPW
PROJECT 2: Water Management 7 Year Plan to rebuild DPW
PROJECT 3: Small Town Precinct Development 7 Year Plan to rebuild DPW
PROJECT 4:Property Rates and Municipal Services in Arrears 7 Year Plan to rebuild DPW
PROJECT 5:Immovable Asset Register 7 Year Plan to rebuild DPW
PROJECT 6:Energy and Water efficiency monitoring &verification 7 Year Plan to rebuild DPW
PROJECT 7:Asset Management System Development 7 Year Plan to rebuild DPW