WiFi Project Updates

WiFi Project Updates. (P17870) WiFi Vendor Comparison and RFP. Program Agenda. (P17870) WiFi Vendor Comparison and RFP Authentication re-design Roll out plan – Complete FY13 budget $1.7M FY14 budget $3.5M FY15 budget $2.6M. Milestones. Free AP deal – in work with legal now

brady-fry
Download Presentation

WiFi Project Updates

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. WiFi Project Updates (P17870) WiFi Vendor Comparison and RFP

  2. Program Agenda • (P17870) WiFi Vendor Comparison and RFP • Authentication re-design • Roll out plan – Complete • FY13 budget $1.7M • FY14 budget $3.5M • FY15 budget $2.6M

  3. Milestones • Free AP deal – in work with legal now • Authentication pilot design documentation for STR and tech review - no • Authentication pilot in to STR - no • Authentication pilot in to Tech Review - no • Monitoring – in work 10% complete • Reporting - no, legacy reporting still in place • Core team training – complete and on going • Field team training – on going • User training - no • Controllers for other sites – no • ISE for auth pilot – yes • STR for new hardware - Done • Controller install for pilot sites – 90% complete • Access point install for pilot sites – in work 10% complete • AP deployment priority guide – complete • Access point install for other sites – on going • Authentication business case to Uwe and Steve D – complete • Authentication pilot documentation for CSARB - complete • Authentication pilot into CSARB – ready for review • Documentation for AP planning - complete • Documentation for AP install and testing - complete • Documentation for controller install – complete

  4. Access Point, Pilot Sites, Other Sites • . New access point installation - 3602 • HQ region – 39 • AMER – 200 • EMEA – 19 • APAC – 8 Non-pilot sites complete • AMER – 2 • HQ - .5 • EMEA – 0 • APAC - 0 Pilot sites: • Reston – complete • Bozeman – no • NY16 – complete • 401ip2 – complete • SaoPaulo – complete • Cambridge - complete • Dubai – complete • TVP 2F - no • Tokyo Aoyama 0F - no • Taipei 33F - no • Singapore Suntec 4, 23F - no • Bangalore OTP - no • Hyderabad Campus – no

  5. Project Notes • 19-DEC-2012 - https://stbeehive.oracle.com/content/dav/st/CISD%20Data%20Networks/Documents/Global%20Wireless%20Program%20Meeting%20Notes%20-%20APAC_19-Dec-12.pdf • 04-JAN-2013 • No update from last note due to holidays. • 10-JAN-2013 https://stbeehive.oracle.com/content/dav/st/CISD%20Data%20Networks/Documents/Global%20Wireless%20Program%20Meeting%20Notes%20-%20APAC_10-Jan-13.pdf

  6. Backup Slides and Notes

  7. WiFi RFP Update - (P17870) WiFi Vendor Comparison and RFP • RFP complete as of 04-May-2012 • Rollout plan complete and communicated • Access point placement training complete • Hardware STR applied for – expected 11-OCT-2012 • Engineering Package for controllers – Complete and approved, additional engineering package for the actual installation needs to be completed • Controller purchase requisitions are placed – Installed and working HQ,ADC,RMDC,JAPAN, SG-almost complete. EMEA,AU,India may have to wait until after freeze. • Controller installation guide – completed (12-Oct-2012) • Complete pilot sites – in work • Change existing WiFi hardware standards for other locations – Complete • Work with authentication and management team on new design and start pilot – in work • Order other infrastructure components - this includes authentication and management system components • Authentication design package into CSARB and STR – in work • Authentication design package into technical review • Change WiFi design standard • Order authentication and management equipment • Install authentication and management equipment • Implement new authentication method into production