An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MC Beamline Tom lackowski L1 Manager

  2. Project Organization T. Lackowski - MC Beamline

  3. Site Plan T. Lackowski - MC Beamline

  4. Scope • Main Injector type enclosure • 10 feet wide x 8 feet high (typical except near MC-1 where higher ceiling will be required. • Painted walls and ceiling, sealed floor. Floor to have 3” cover over rebar to enable stand anchorage. • Channel inserts walls and ceiling @ 8’ o/c. (no inserts 5’ from floor on aisle side) • Shielding • 13 feet of earth/concrete for M-4 beamline. (w/ beamline 4’ from clg.) • 6 to 9 feet for g-2 beamline. Shielding needed within enclosure between MC-1 building and M-4 / Delivery Ring. • Access is provided from Ring enclosure- lift provided for magnet installation. Shielding hatch provided for magnet installation / replacement. T. Lackowski - MC Beamline

  5. Typical Cross Section T. Lackowski - MC Beamline

  6. Scope • HVAC & Process Water • A concept exits that integrates the requirements for beamline and Mu2e. G-2 is isolated from beamline. • LCW provided by g-2 and Mu2e • Electrical • 500 MCM ground along beamlines. • Quad 120V & duplex 208V utility outlets at 60’ • 480V welding outlets at 400’ • Three 18” cable trays provided (one tray will contain line type heat detection) T. Lackowski - MC Beamline

  7. Cost by Division T. Lackowski - MC Beamline

  8. Preliminary Costs $9,200,000 Planned $9,200,000 Planned T. Lackowski - MC Beamline

  9. Cost Curve T. Lackowski - MC Beamline