UNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTS. 6. 4. 2. 1. 5. 3. Phase 1 Works 26 th July 2010 to 15 th October 2010 – 12w Phase 5 Works 1 st August 2011 to 26 th August 2011 – 5w
E N D
UNIVERSITY of DURHAM - SCIENCE SITE ENVIRONMENTAL IMPROVEMENTS 6 4 2 1 5 3 Phase 1 Works 26th July 2010 to 15th October 2010 – 12w Phase 5 Works 1st August 2011 to 26th August 2011 – 5w Phase 2 Works 18th October 2010 to 17th December 2010 – 9wPhase 6 Works 25th June 2012 to 03rd August 2012 – 6w Phase 3 Works 20th December 2010 to 18th March 2011 – 9w Phase 4 Work 21st March 2011 to 29th July 2011 – 19w REV.10 11/06/2010
SSEI PHASE 1 26th July 2010 to 16th October 2010 ACCESS / EGRESS DURING PHASE 1 WORK University to Have Personnel Available During Access & Egress of Wagons