1 / 53

Residential

Residential. Fall. Protection. OSHA’s Mission. To Assure So Far as Possible Every Working Man and Woman in the Nation Safe and Healthful Working Conditions.

Download Presentation

Residential

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Residential Fall Protection

  2. OSHA’s Mission • To Assure So Far as Possible Every Working Man and Woman in the Nation Safe and Healthful Working Conditions...

  3. Hierarchy of Fall Protection • The less human effort for fall protection, the more effective the fall protection EFFECTIVENESS Most Effective Least Effective HUMAN EFFORT Least Effort Most Effort Eliminate Engineered Warning Training PPE

  4. Fall Protection - General Requirements • Where workers on a construction site are exposed to vertical drops of 6 feet or more, OSHA requires that employers provide conventional fall protection in one of three ways before work begins: • Placing guardrails around the hazard area • Deploying safety nets • Providing personal fall arrest systems for each employee

  5. Alternative Procedures • Directive STD 3-0.1A - Plain Language Revision of OSHA Instruction STD 3.1, “Interim Fall Protection Compliance Guidelines for Residential Construction” • Permits employers engaged in certain residential construction activities to use alternative procedures routinely instead of conventional fall protection

  6. Residential unsafe practice • Must be engaged in residential construction andperforming one of listed activities • Not Exempted! • Still obligated to comply with other OSHA standards and conventional fall protection if alternative procedures are not used

  7. Residential Construction • Working environment, materials, methods and procedures are essentially same as single-family homes or townhouses • Characterized by: • Materials: wood framing (not steel or concrete); Wooden floor joists and roof structures • Methods: traditional wood frame construction techniques • Discrete part of a large commercial building

  8. Listed Activities • GROUP 1 - floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting & bracing roof trusses and rafters • GROUP 2 - concrete and block foundation walls and related formwork. • GROUP 3 -when performed in attics and on roofs: installing drywall, insulation, HVAC systems, electrical systems (including alarms, telephone lines, and cable TV), plumbing and carpentry • GROUP 4 - Roofing work - removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper

  9. STD 3-0.1A • Do not need to show conventional fall protection is infeasible • Fall protection plan is still required, but • does not have to be written • not specific to the jobsite • Each activity has its ownset of alternative procedures Written Plan NotRequired

  10. Group 1 floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting & bracing roof trusses and rafters

  11. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Fall protection plan found in Appendix E of Subpart M • Height limitation • Structures up to 3 1/2 stories or 48 feet (including basement, two finished levels, attic) • Measured from the base of the building, at the lowest ground level (including any excavation), to the point of greatest height • Plan communicated to all employees on site subject to fall hazards

  12. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Employee training coverage of the Fall Protection Plan must include: • Requirements of the plan • Understand procedures and follow instructions of supervisor or foreman • Able to recognize unsafe/hazardous conditions and report them to the employer • Recognize when compliance with the Plan would create a greater hazard and inform the Competent Person before proceeding • Concerns raised by employees must be addressed

  13. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Employer must designate: • Competent Person • Qualified Person • Crew Supervisor or Foreman • Supervisor and/or foreman can be the competent and qualified person

  14. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • "Competent person" means one who is capable of identifying existing and predictable hazards in the surroundings or working conditions which are unsanitary, hazardous, or dangerous to employees, and who has authorization to take prompt corrective measures to eliminate them. Ref.1926.32(f)

  15. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Competent person will: • be charged with implementing the plan • continually monitor compliance with the plan including: • provision of training • the proper use of controlled access zones

  16. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • "Qualified" person means one who, by possession of a recognized degree, certificate, or professional standing, or who by extensive knowledge, training, and experience, has successfully demonstrated his ability to solve or resolve problems relating to the subject matter, the work, or the project. Ref. 1926.32(m) • Person is designated • Reviews & approves any changes to the plan

  17. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Designated crew supervisor or foreman • responsible for the immediate correction of any unsafe practice or condition Unstable footing, scaffold re-erected with proper mud sill placement

  18. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Controlled access zone (CAZ) - restricts access to a clearly designated area where a Group 1 activity is taking place • The CAZ must meet the following requirements: • Boundaries - clearly marked eg. signs, wires, tapes, ropes or chains • Crew supervisor/foreman monitors • Restricted access to authorized (trained) entrants • Final check - before work begins, the competent person must ensure that all protective measures in the plan have been implemented unsafe condition

  19. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Plan Administration • Employer Enforcement • Crew supervisor/foreman, Safety and Personnel department have the right to issue disciplinary warnings • Unsafe practices or conditions must be corrected immediately unsafe practice

  20. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters • Plan Administration • Plan Changes/Review To The Plan • Qualified person approves changes to Plan • Review Plan as the job progresses to determine the need for additional practices, procedures or training • Retrain employees on any new procedures • Accident Investigation • All accidents reported and investigated • Investigation documented • Review Plan in event of falls or other serious incidents

  21. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Installing Roof Trusses and Erecting Rafters Additional Requirements • Walls Up To 8 Feet • Use interior scaffolds, below the area where the trusses/rafters will be located • Sawhorse scaffolds acceptable • Walls Over 8 Feet • Falling Objects - restricted access during truss installation • Brace trusses before being used as a support • Designate the trained workers for top plate and peak work • Top plate workers have no other duties during truss erection

  22. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Working on top plate - Additional Requirements • First two trusses set from supported ladders • Once set, worker will climb ladder onto the interior top plate to secure peaks • Use previously stabilized trusses as support while other trusses/rafters are erected

  23. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Working at peak- Additional Requirements • While detaching trusses from cranes or securing trusses at the peaks, worker may: • be positioned at the peak of the trusses/rafters • be stationed on the top of the ridge beam when it is the only feasible way to secure rafters to the ridge beam • Workers at the peak, in the web of trusses, or on top of the ridge beam must work from a stable position • sit on a ridge seat (or the equivalent) or • position themselves in previously stabilized trusses/rafters, and lean into and reach through the trusses/rafters • Do not remain on or in the peak/ridge any longer than necessary

  24. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Roof Sheathing Operations - Additional Requirements • Competent person must determine when the roof system is stable enough to support conventional fall protection system anchorage • Once roof system is stable enough for anchorage, personal fall arrest systems must be used

  25. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Roof Sheathing Operations - Additional Requirements • Provisions that can be apply until the roof system is stable: Qualified Workers Staging of Materials Secure Footing/Weather Slide Guards Falling Objects/Restricted Access

  26. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Roof Sheathing Operations - Additional Requirements • Only qualified workers • Secure Footing/Weather • remove slip hazards • suspend roof sheathing when wet • suspend roof sheathing when winds > 40 mph • Stage materials for quick access • Falling Objects - restricted access during sheathing installation • Provide 4 inch slide guards unsafe practice

  27. Slide guard requirements for roof sheathing are different from those for roof work (Group 4 Activity)

  28. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Installation of Floor Joists and Floor Sheathing Additional Requirements • Designate trained workers • Stage materials for quick access • Restricted access of those not assisting - do not permit within 6 feet from the leading edge unsafe condition

  29. unsafe practice GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Installation Process of Floor Joists - Additional Requirements • First floor joist or truss rolled into position and secured by workers on the ground, ladders, or sawhorse scaffolds • Successive joists/trusses must be rolled into place and secured from platform • Platform is built by laying a sheet of plywood over thepreviously secured floor joists or trusses

  30. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Installation Process of Floor Sheathing Additional Requirements • First row of floor sheathing installed by workers on the ground, ladders, or sawhorse scaffolds • After the first row of sheathing has been installed, workers shall work from the established deck unsafe practice

  31. GROUP 1- Alternative Procedures floor joists, floor sheathing, and roof sheathing; erecting exterior walls; setting and bracing roof trusses and rafters Erection of Exterior Walls- Additional Requirements • Designate trained workers • Stage materials for quick access • Limit fall hazard exposure by cutting material away from edge of deck • Paint warning line 6 feet from the perimeter before any wall erection activities and provide monitor for those working near the unprotected edge unsafe practice

  32. Group 2

  33. unsafe practice GROUP 2- Alternative Procedures concrete and block foundation walls and related formwork • Procedures for protecting employees working at the top surface of block foundation walls, concrete foundation walls and related form work

  34. unsafe practice GROUP 2- Alternative Procedures concrete and block foundation walls and related formwork • Only trained workers allowed to work on the top of the foundation wall/form work, and only as necessary to complete the construction of the wall • All formwork shall be adequately supportedbefore any worker may work on top of the form work

  35. GROUP 2- Alternative Procedures concrete and block foundation walls and related formwork • When adverse weather creates a hazardous condition, operations shall be suspended • Impalement hazards shall be cleared from the area below workers or shall be properly guarded • Stage materials for quick access

  36. Group 3

  37. GROUP 3- Alternative Procedures activities when performed in attics and on roofs drywall, insulation, HVAC systems, electrical systems, plumbing and carpentry • Procedures for activities when performed in attics and on roofs: installing drywall, insulation, HVAC systems, electrical systems (including alarms, telephone lines, and Cable TV), plumbing and carpentry

  38. GROUP 3- Alternative Procedures activities when performed in attics and on roofs drywall, insulation, HVAC systems, electrical systems, plumbing and carpentry • Only trained workers allowed to work in attics and roofs, and only as necessary to complete system being installed • Stage materials for quick access • Impalement hazards shall be kept out of the area below workers or shall be properly guarded • Restrict access to areas below openings in ceilings to reduce falling object hazards • When adverse weather creates a hazardous condition, operations shall be suspended

  39. Group 4 Roofing work

  40. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • Procedures for activities in roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper) unsafe practice

  41. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • Roofs with eave height over 25 feet • Any Slope • Any Roof Type • Alternatives to the Requirements of the Standards are not Available unsafe practice

  42. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • General requirements: • Only workers trained to be proficient in the alternative methods of fall protection shall be allowed onto the roof • Affected employees shall be trained in specific awareness of fall hazards associated with work on roofs with rake edges • Inspect for and eliminate any slipping hazards or take effective measures to have workers avoid slipping hazards • Workers must wear appropriate footwear

  43. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • General requirements: • When adverse weather creates a hazardous condition, operations shall be suspended • Repair any roof deck damage • Cover or guard any holes, including skylight openings unsafe practice

  44. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • General requirements: • Erect and maintain ladders or scaffolds in accordance to Subparts X and L • Trained employees in accordance with the requirements of Subparts X & L • Do not ascend or descend the roof's slope within 6 ft of the rake edge except where limitation would prevent work process unsafe practice

  45. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • General requirements: • Do not store supplies and materials within 6 feet of the rake edge or three feet where tile roof systems are being installed • Keep area below eaves and rakes clear of impalement hazards or properly guard hazards

  46. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • For Roofs With Eave Height of up to 25 Feet • Roof Slope (Any Roof Type): Up to 4 in 12 • Use either safety monitoring system that complies with 1926.502 or roofing slide guards • Roof Slope (Except Tile or Metal Roofs): Over 4 in 12 and up to 8 in 12: • Slide guards are required • Tile or Metal Roofs - safety monitoring system may be used instead of slide guards • Roof Slope over 8 in 12 - Alternatives not available

  47. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • Slide Guards: • Roof Slope: 6 in 12 or less • Constructed of 2"x 6" (nominal) stock • No more than three rows of roofing material (installed across the lower eave) shall be applied before installing the slide guards • Roof jacks (or similar supports) shall be installed using nails long enough to withstand an employee sliding into the guard • Face of the slide guard must be perpendicular to the surface of the roof • Continuous slide guards along the eave

  48. GROUP 4- Alternative Procedures roofing work (removal, repair, or installation of weatherproofing roofing materials such as shingles, tile and tar paper • Slide Guards: • Roof Slope: Over 6 in 12 (up to and including 8 in 12): • Constructed of 2"x 6" (nominal) stock • Continuous slide guards shall be installed along the eave • Install additional slide guards below each work area at intervals not to exceed eight feet • Slide guards at the eave must be at about 90 degrees to the roof surface • Additional slide guards need not be continuous or at 90 degrees to the roof surface

  49. INTERIM FALL PROTECTION COMPLIANCE GUILDELINE FOR RESIDENTIAL ROOFING WORK Slide guard requirements for roofing are different from those for roof sheathing (Group 1 Activity)

More Related