E N D
1. 1
2. 2 Outline
3. 3 City of Pickering
4. 4 Design Objectives Design a new Sewage Pumping Station and Forcemain in Pickering, Ontario
Provide additional sewage pumping capacity to accommodate future population growth
Comply with current engineering standards, and health and safety regulations
Design Criteria (year 2031)
Population: 4,760
Future Drainage Area: 121.3 ha
Estimated Peak Flow: 138 L/s
5. 5 Forcemain
6. 6 Sewage Pumping Station
7. 7 Floor Plan
8. 8 Side View Explain why duty pumps not in the same chamber, guide railsExplain why duty pumps not in the same chamber, guide rails
9. 9 Wet Well and Valve Chamber Explain flow of sewage even with a water arrowExplain flow of sewage even with a water arrow
10. 10 Outline
11. 11 Pumping Station Layout
12. 12 Design Flow and Hydraulic Calculations
Design flow = 138 L/s (year 2031 flow)
TDH = Static Head + Friction Head
Hydraulic Calculations:
Used Hazen-Williams Formula
Assigned C values based on peak flow conditions
Flow guidelines of the Ontario MOE
13. 13 Station Head Loss Station Piping
Standard Weight (ANSI B36.10) Steel Pipe
Nominal Size = 250 mm (10)
C= 100
Total head loss = 0.2 m
14. 14 Forcemain Head Loss Existing Forcemain
MOE Velocity range 0.6 3.0 m/s
Minimum velocity to re-suspend solids is 0.8 m/s
Utilize both old pipes to reduce fluid velocity
Nominal pipe size = 250 mm (10)
Total length = 1,030 m
C=100
At peak flow, v = 1.5 m/s in each
Total head loss = 16.0 m
15. 15 Forcemain Head Loss New HDPE pipe
1000 Series Driscopipe HDPE SDR17
Nominal size 350 mm (14)
Length= 285 m
C= 120
v= 1.4 m/s
Total head loss = 1.7 m
16. 16 Valves and Fittings Inventory
17. 17 Total Dynamic Head (TDH)
18. 18 Pump Selection ITT Flygt Pumps
Used by pumping stations in Durham Region
Model Number NP3202.185 HT
Three identical pumps: 2 duty, 1 standby
Constant speed: 1,175 rpm
Motor power: 70 hp
19. 19 System and Pump Performance Curves
20. 20 Pump Selection Checking for cavitation:
Therefore, cavitation is unlikely to occur
21. 21 Outline
22. 22 Instrumentation and Control Designed for unattended operation
Supervisory Control and Data Acquisition (SCADA) system
A Remote Terminal Unit (RTU) will be installed The pumping station is designed for unattended operation
An operator might be required for routine checks and in response to alarms
For that reason, a SCADA system is most appropriate to use
A RTU will be installed at the PS
The RTU is capable of independently controlling the station in case communication is lost with the Master Terminal Unit (MTU)The pumping station is designed for unattended operation
An operator might be required for routine checks and in response to alarms
For that reason, a SCADA system is most appropriate to use
A RTU will be installed at the PS
The RTU is capable of independently controlling the station in case communication is lost with the Master Terminal Unit (MTU)
23. 23 Piping & Instrumentation The piping and instrumentation diagram shows key piping and instrumentation details [shows some of our control mechanisms]The piping and instrumentation diagram shows key piping and instrumentation details [shows some of our control mechanisms]
24. 24 Instrumentation and Control
25. 25 Power Main utility supply
Complemented by a series of step-down transformers
An emergency diesel generator
Rated at 200 kW
In the event of power failure
Commercial silencer
Powered through the main utility supply and a series of step-down transformers
An emergency diesel generator provides backup power for the pumps and electrical equipment in the event of power failure
Powered through the main utility supply and a series of step-down transformers
An emergency diesel generator provides backup power for the pumps and electrical equipment in the event of power failure
26. 26 Outline
27. 27 Environmental Concerns
28. 28 Outline
29. 29 Mitigation Measures
30. 30 Short Term Mitigations
31. 31 HDD: Horizontal Directional Drilling
32. 32 Long Term Mitigations Architecture
Blend in with the surrounding neighbourhood
Reclamation
New Site
Petticoat Creek
33. 33 Outline
34. 34 Total Capital Investment Breakdown
35. 35 Annual M&O Cost Breakdown
36. 36 Outline
37. 37 Conclusion New Submersible Sewage Pumping Station
3 submersible pumps (2 duty, 1 standby)
Meet projected sewage flow demands
Maximize operational efficiency
Community and Environment
Safer work environment
Noise and odour control measures
Environmental rehabilitation
Community acceptance
Cost Reduction
Incorporate existing forcemain
Minimize environmental impacts
38. 38 Acknowledgments Dr. Barry Adams (Professor, University of Toronto)
Hugh Tracy (Delcan)
Fabian Papa (Adjunct Professor, University of Toronto)
Kevin Waher (Wardrop)
Steve OBrien (Wardrop)
Brent Galardo (Hudsons Bay Trading Company)
39. 39
40. 40
41. 41 Pumping Station Design Design parameters:
Peak flow: 138 L/s
Forcemain = 1,030 m twin barrel (Old) + 285 m (New)
Static elevation
Ground elevation at proposed site= 82.0 ASL
Highest point of forcemain (discharge)= 88.5 ASL
Invert elevation of inlet sewer to wet well = 77.9 ASL
Assumed wet well depth 1.5 m
Total static lift = 12.1 m (from LWL to discharge)
42. 42 Pumping Station Design Peak Flow: 138 L/s
Forcemain
Section 1A: 10 ID 1,030 m A-C pipe (old, 1961)
Section 1B: 10 ID 1,030 m PVC pipe (new, 1998)
Section 2: 12 ID, 285 m HDPE pipe, joins 1A+1B
At peak flow, velocity in one 10 forcemain = 3.03m/s
MOE velocity range 0.6 m/s 3.0 m/s
Hence, utilize both old forcemain pipes (1A + 1B)
43. 43 Head Loss Calculations TDH = Static Head + Friction Head + Velocity Head
Hazen-Williams Formula (Jones et al., 2006)
hf = Friction head loss in pipe per meter of piping, [m]
Q = Volumetric flow rate, [m3/s]
C = Hazen-Williams C factor, [dimensionless]
D = Internal pipe diameter, [m]
44. 44 Head Loss Calculations Station piping
C= 100 (MOE guidelines)
Total head loss = 0.22 m
Existing Forcemain
To simply, assume identical dimensions
At peak flow, Q= 69 L/s, v= 1.51 m/s in each
Head loss = 0.015 m/m
Total head loss = 15.96 m
New 12 HDPE pipe
C= 120
Total head loss = 4.96 m
45. 45 Velocity Head, Valves and Fittings General head loss equation (m)
hm = Friction head loss due to pipe or fitting, [m]
hv = Velocity head, [m]
K = Constant factor that depends on shape of fitting or valve, [dimensionless]
v = Fluid velocity, [m/s]
g = Gravitational acceleration constant, [9.81 m/s2]
Obtain K values from manufacturers or literature
46. 46 Checking for Cavitation Net Positive Suction Head (Available) for the System
Hbar= Barometric pressure of water column for elevation above sea level.
hs= Static head of intake water above the impeller. Since the pump is submersible, hs is always positive.
Hvap = Vapour pressure of fluid at maximum expected temperature, [m]
To avoid cavitation, NPSHA >> NPSHR
47. 47 Valves and Fittings Inventory
48. 48 Total Dynamic Head (TDH)
49. 49 System H-Q and Pump Curve
50. 50 System H-Q and Pump Curve
51. 51 Pump Specifications ITT Flygt
Model NP3203.180 Submersible Wastewater Pumps
Motor Shaft power 70 hp
Outlet 6 inches
Hydraulic efficiency (2 Parallel) = 71%
Single pump operation flow = 113.1 L/s (71% eff.)
Rated speed 1,175 rpm
Impeller diameter 310 mm (2 blades)
52. 52 Checking for Cavitation Hbar= 10.24 m (measured at 74.9 m ASL)
hs= 0.12 m (from pump AutoCAD drawing)
Hvap = 0.44 m (assumed Max. Temperature = 30C)
NPSHA = 10.24 + 0.12 0.44 = 9.92 m (at LWL)
53. 53
54. 54 Mitigation Strategies in Affected Areas
55. 55 Natural Vegetation in the Creek Area Examples of natural vegetation in the creek area:
Poplar, Trembling Aspen, White and Yellow Birch, Sugar Maple, Chockecherry. Examples of natural vegetation in the creek area:
Poplar, Trembling Aspen, White and Yellow Birch, Sugar Maple, Chockecherry.
56. 56 Rodd Ave. Natural Vegetation Examples of vegetation in the Rodd Ave. area. :
Red Maple
Grey / Red Oiser Dogwwod
Green / Red Ash
Salix Discolor
Arbovitae
Arrorwwood
Special considerations must be taken when allocating planting spots for tall trees. The roots of the trees extent to 1.5 3 times the height hence causing destruction to the existing infrastructures. Special control measures must be taken to minimize infrastructure and tree destructions, and possible future litigations due to infrastructure damage by the tree roots. Examples of vegetation in the Rodd Ave. area. :
Red Maple
Grey / Red Oiser Dogwwod
Green / Red Ash
Salix Discolor
Arbovitae
Arrorwwood
Special considerations must be taken when allocating planting spots for tall trees. The roots of the trees extent to 1.5 3 times the height hence causing destruction to the existing infrastructures. Special control measures must be taken to minimize infrastructure and tree destructions, and possible future litigations due to infrastructure damage by the tree roots.
57. 57 Implementation Schedule