An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Data Center Commissioning:Lessons Learned in a Design/Build Environment 2014 Commissioning Energy Conference Las Vegas, NV Derek De Jesús, CxA, LEED AP Jeff Jameson, PE

  2. Learning Objectives • Identify potential conflicts between the Commissioning Agent and the design/build team. • Identify the process implemented, scope required, and the value added for the Owner. • Highlight the challenges encountered and modifications to the Commissioning process that occurred in order to achieve the project goals. • ASHRAE 90.4P review

  3. Interesting Facts • How many data centers exist? • 2011 – 509,147 1 • Electricity Consumption • Doubled from 2000 to 20052 • Increased 56% from 2005 and 2010 2 • Range 100W to 400W /sqft3 • Operating temperatures4 • 2004 – 72 deg F • 2008 – 81 degF 1 – Emerson Network Power (http://www.emersonnetworkpower.com/en-US/About/NewsRoom/Pages/2011DataCenterState.aspx) 2 – Jonathan Koomey, July 2011, http://www.koomey.com/post/8323374335 3 – Data Center Knowledge, April 2012, http://www.datacenterknowledge.com/archives/2012/04/25/6-questions-for-your-next-data-center-provider/ 4 - ComputerWorld, January 2010, http://www.computerworld.com/s/article/9144466/Data_center_density_hits_the_wall

  4. Design/Build Cx Approach • ACG Process but Speak up and be heard • Integrate Commissioning early and often • Expect the same project goals • PUE (Power Usage Effectiveness) • CFD (Computational Fluid Dynamics) • OPR (Owner’s Project Requirements) • Tier rating • More meetings; site attention

  5. Design/Build Cx Challenges • Contracting – Owner or DB/C? • OPR, BOD developed? • Blended phases! • Fast paced…ambiguous schedule • Reduced documentation trail

  6. Design/Build Cx Opportunities • Improved access to team and owner • Eager and attentive installing contractors • Cooperation • Identifying gaps, supporting the team!

  7. Cx Scope of Service Challenges • Design reviews • How many and when? • Comment responses • Submittal reviews • Approved unless otherwise stated • Schedule Integration Startup FPT PFC Acceptance BAS Pt-Pt TAB

  8. Cx Added Value • Expand the systems to be Commissioned • Grounding, lightning protection • Life safety systems • VESDA • Pre-Action • Energy management systems • Interface(s) to BAS • Reliability, stability for equipment operations

  9. More Added Value • Electrical testing support • Witness and document NETA testing • Support the scheduling of these tests • Test equipment • Data logging • Trending • IR Scanning • Load banking • Beyond vendor startup PDU Testing and Trending

  10. Case Study Review • 57,509 sqft renovation • 6 Pods • 4 Pods built out; 2 for future • 6MW of electrical power • N+1 design for all systems • DB/C = Owner

  11. Challenges Encountered • Brought on AFTER final design • Still performed a design review • Brought on AFTER equipment had started getting delivered • Still performed a submittal review • Immediate ramp up • Estimated schedule to turnover: 6 months • Vague scheduling

  12. Challenges Encountered • Reviewing documents AND developing documents at the same time • Addressing design concerns • Electrical test witnessing not in Cxscope • Schedule coordination for startup • No one had Cx in budget, but it was a data center…

  13. Challenges Encountered • B phase CT was broke from factory • Testing should have found it • Caused breaker to trip at 75% load

  14. Challenges Encountered • Weather delays • Existing building conditions • Leaking roof • Strike delays • No O&M staff on-board during project • No training • No witnessing of testing Inadequate service ground

  15. Mechanical System • Two SMARDT 200-ton Oil free centrifugal chillers, R-134a, 45° CHW, 400 gpm • Each chiller with dual (100-ton each) VFD compressors • Evaporative Condenser with spray pump • Economizer pump package • Dedicated chiller primary pumps • Additional spare in case of emergency replacement • Two VFD secondary pumps • Sized for future data center expansion • Chilled water load monitoring (BTU meter) • Package system controller

  16. Mechanical System • Operational benefits • Secondary pump speed control set up to maintain critical branch temperature (or pressure) • Reliability • The system has safety modes of operation to maintain continuous operation (sump dump, emergency sump heating, react to temperature control problems, emergency operation, stand-alone operation, etc.)

  17. Energy Savings/Goals • Year round consistent, cooling capability • High efficiency using the evaporative condenser- • Dry condenser operation for low outside air temperature (<40° adj.) operation • Wet condenser operation for warmer OAT (>45° (adj.) operation • Monitoring of system energy consumption

  18. Modified Process • Spent more time with contractors completing the PFCs than just reviewing • Cx meetings became scheduling coordination meetings • Cx documents proved readiness • Maintained 3 levels of testing to prove acceptance • FPTs • ISTs • ISOTs

  19. Added Value • Systems outside of Scope • Do what you can when you have the time • Show the value, even if its free • Be reasonable • Greatest single value for electrical Cx…. • Advocate for primary current injection testing • Witness the testing • Document the results • Set the breakers per the FINAL Coordination Study

  20. ASHRAE 90.4P • Energy Standard for Data Centers and Telecommunications Buildings • First Advisory Public Review • November 2013 • Comments are still in review

  21. ASHRAE 90.4P • 4.2 – Compliance • Either use 90.4P or 90.1 • 4.2.2 – Compliance Documentation • Many of the requirements the CxA can support • Labeling of equipment, O&M, Inspections

  22. ASHRAE 90.4P • 4.2.4 – Inspections • Requires AHJ to inspect • wall insulation after the insulation and vapor retarder are in place but before concealment • roof/ceiling insulation after roof/insulation is in place but before concealment • slab/foundation wall after slab/foundation insulation is in place but before concealment • fenestration after all glazing materials are in place • continuous air barrier after installation but before concealment • mechanical systems and equipment and insulation after installation but before concealment • electrical equipment and systems after installation but before concealment

  23. ASHRAE 90.4P • Section 5 Building Envelope • No methods or standards except to comply with 90.1

  24. ASHRAE 90.4P • 6.4.1 – PUE • Only provides Mechanical PUE • Defined by cities yet some major metro areas are missing 1 2 1 – 42U, 2014, http://www.42u.com/measurement/pue-dcie.htm#What-is-PUE 2 – ASHRAE 90.4P, Page 29, 2013

  25. ASHRAE 90.4P • Summary • No specific mention of Commissioning • No mention of testing to prove energy consumption • No mention of any Measurement & Verification • Nothing with regards to improving PUE rating over time • Its all based on Day 0 performance

  26. Conclusion • Engage in a discussion to clarify and define expectation upfront • Advocate for Electrical Cx beyond “standard” services • Understand the potential of 90.4P

  27. Question & Answer

  28. Contact Information Derek De Jesús National Commissioning Manager KJWW Engineering 312-931-3703 dejesusdw@kjww.com Jeff Jameson Mechanical Commissioning Agent KJWW Engineering jamesonjj@kjww.com