Data Center Commissioning: Lessons Learned in a Design/Build Environment. 2014 Commissioning Energy Conference Las Vegas, NV. Derek De Jesús, CxA, LEED AP Jeff Jameson, PE. Learning Objectives. Identify potential conflicts between the Commissioning Agent and the design/build team.
E N D
Data Center Commissioning:Lessons Learned in a Design/Build Environment 2014 Commissioning Energy Conference Las Vegas, NV Derek De Jesús, CxA, LEED AP Jeff Jameson, PE
Learning Objectives • Identify potential conflicts between the Commissioning Agent and the design/build team. • Identify the process implemented, scope required, and the value added for the Owner. • Highlight the challenges encountered and modifications to the Commissioning process that occurred in order to achieve the project goals. • ASHRAE 90.4P review
Interesting Facts • How many data centers exist? • 2011 – 509,147 1 • Electricity Consumption • Doubled from 2000 to 20052 • Increased 56% from 2005 and 2010 2 • Range 100W to 400W /sqft3 • Operating temperatures4 • 2004 – 72 deg F • 2008 – 81 degF 1 – Emerson Network Power (http://www.emersonnetworkpower.com/en-US/About/NewsRoom/Pages/2011DataCenterState.aspx) 2 – Jonathan Koomey, July 2011, http://www.koomey.com/post/8323374335 3 – Data Center Knowledge, April 2012, http://www.datacenterknowledge.com/archives/2012/04/25/6-questions-for-your-next-data-center-provider/ 4 - ComputerWorld, January 2010, http://www.computerworld.com/s/article/9144466/Data_center_density_hits_the_wall
Design/Build Cx Approach • ACG Process but Speak up and be heard • Integrate Commissioning early and often • Expect the same project goals • PUE (Power Usage Effectiveness) • CFD (Computational Fluid Dynamics) • OPR (Owner’s Project Requirements) • Tier rating • More meetings; site attention
Design/Build Cx Challenges • Contracting – Owner or DB/C? • OPR, BOD developed? • Blended phases! • Fast paced…ambiguous schedule • Reduced documentation trail
Design/Build Cx Opportunities • Improved access to team and owner • Eager and attentive installing contractors • Cooperation • Identifying gaps, supporting the team!
Cx Scope of Service Challenges • Design reviews • How many and when? • Comment responses • Submittal reviews • Approved unless otherwise stated • Schedule Integration Startup FPT PFC Acceptance BAS Pt-Pt TAB
Cx Added Value • Expand the systems to be Commissioned • Grounding, lightning protection • Life safety systems • VESDA • Pre-Action • Energy management systems • Interface(s) to BAS • Reliability, stability for equipment operations
More Added Value • Electrical testing support • Witness and document NETA testing • Support the scheduling of these tests • Test equipment • Data logging • Trending • IR Scanning • Load banking • Beyond vendor startup PDU Testing and Trending
Case Study Review • 57,509 sqft renovation • 6 Pods • 4 Pods built out; 2 for future • 6MW of electrical power • N+1 design for all systems • DB/C = Owner
Challenges Encountered • Brought on AFTER final design • Still performed a design review • Brought on AFTER equipment had started getting delivered • Still performed a submittal review • Immediate ramp up • Estimated schedule to turnover: 6 months • Vague scheduling
Challenges Encountered • Reviewing documents AND developing documents at the same time • Addressing design concerns • Electrical test witnessing not in Cxscope • Schedule coordination for startup • No one had Cx in budget, but it was a data center…
Challenges Encountered • B phase CT was broke from factory • Testing should have found it • Caused breaker to trip at 75% load
Challenges Encountered • Weather delays • Existing building conditions • Leaking roof • Strike delays • No O&M staff on-board during project • No training • No witnessing of testing Inadequate service ground
Mechanical System • Two SMARDT 200-ton Oil free centrifugal chillers, R-134a, 45° CHW, 400 gpm • Each chiller with dual (100-ton each) VFD compressors • Evaporative Condenser with spray pump • Economizer pump package • Dedicated chiller primary pumps • Additional spare in case of emergency replacement • Two VFD secondary pumps • Sized for future data center expansion • Chilled water load monitoring (BTU meter) • Package system controller
Mechanical System • Operational benefits • Secondary pump speed control set up to maintain critical branch temperature (or pressure) • Reliability • The system has safety modes of operation to maintain continuous operation (sump dump, emergency sump heating, react to temperature control problems, emergency operation, stand-alone operation, etc.)
Energy Savings/Goals • Year round consistent, cooling capability • High efficiency using the evaporative condenser- • Dry condenser operation for low outside air temperature (<40° adj.) operation • Wet condenser operation for warmer OAT (>45° (adj.) operation • Monitoring of system energy consumption
Modified Process • Spent more time with contractors completing the PFCs than just reviewing • Cx meetings became scheduling coordination meetings • Cx documents proved readiness • Maintained 3 levels of testing to prove acceptance • FPTs • ISTs • ISOTs
Added Value • Systems outside of Scope • Do what you can when you have the time • Show the value, even if its free • Be reasonable • Greatest single value for electrical Cx…. • Advocate for primary current injection testing • Witness the testing • Document the results • Set the breakers per the FINAL Coordination Study
ASHRAE 90.4P • Energy Standard for Data Centers and Telecommunications Buildings • First Advisory Public Review • November 2013 • Comments are still in review
ASHRAE 90.4P • 4.2 – Compliance • Either use 90.4P or 90.1 • 4.2.2 – Compliance Documentation • Many of the requirements the CxA can support • Labeling of equipment, O&M, Inspections
ASHRAE 90.4P • 4.2.4 – Inspections • Requires AHJ to inspect • wall insulation after the insulation and vapor retarder are in place but before concealment • roof/ceiling insulation after roof/insulation is in place but before concealment • slab/foundation wall after slab/foundation insulation is in place but before concealment • fenestration after all glazing materials are in place • continuous air barrier after installation but before concealment • mechanical systems and equipment and insulation after installation but before concealment • electrical equipment and systems after installation but before concealment
ASHRAE 90.4P • Section 5 Building Envelope • No methods or standards except to comply with 90.1
ASHRAE 90.4P • 6.4.1 – PUE • Only provides Mechanical PUE • Defined by cities yet some major metro areas are missing 1 2 1 – 42U, 2014, http://www.42u.com/measurement/pue-dcie.htm#What-is-PUE 2 – ASHRAE 90.4P, Page 29, 2013
ASHRAE 90.4P • Summary • No specific mention of Commissioning • No mention of testing to prove energy consumption • No mention of any Measurement & Verification • Nothing with regards to improving PUE rating over time • Its all based on Day 0 performance
Conclusion • Engage in a discussion to clarify and define expectation upfront • Advocate for Electrical Cx beyond “standard” services • Understand the potential of 90.4P