MuTr Installation Tasks Should be done prior to shutdown: Install South Chambers Trial fit magnet buss Configure scaffolding for FEE Mechanics Installation Install in-magnet FEE mechanics Install eyebrow and racks Make plumbing and electrical connections to racks
E N D
MuTr Installation Tasks • Should be done prior to shutdown: • Install South Chambers • Trial fit magnet buss • Configure scaffolding for FEE Mechanics Installation • Install in-magnet FEE mechanics • Install eyebrow and racks • Make plumbing and electrical connections to racks • Install Glink/Clink crates (back of magnet • for St.2 + 3, on lower lampshades for St. 1) • Make connections from Glink/Clink crates to racks • Install Cross Rib Assemblies (St. 2 + 3 FEE) • Install Station 1 FEE Plate • Install Station 1 chassis • Re-install magnet buss • Roll in and make connections • ALSO: • Need to start preparing North magnet for chamber • installation the next shutdown
MuTr Installation Tasks • Install South Chambers (should be done prior to shutdown)-------------finish ~Aug 22 • Trial fit magnet buss---------------------------------------------------------------- Aug 22 - Aug 29 • Configure scaffolding for FEE Mechanics Installation • Install in-magnet FEE mechanics----------------------------------------------- Aug 31 - Sep 6 • Install eyebrow and racks -------------------------------------------------------- Sep 7 - Sep 13 • Install Glink/Clink crates (back of magnet------------------------------------- when available • for St.2 + 3, on lower lampshades for St. 1) • Install Cross Rib Assemblies----------------------------------------------------- Sep 20 - Dec 12* • Can start installation in Sept. only if we order boards soon • Had 3 months to install 16 cross-rib assemblies (3.75 days/assembly) • If need to keep Nov. 12 deadline, need to assemble and install 2 CRAs/week • Install Station 1 FEE Plate • Install Station 1 chassis • Re-install magnet buss • Roll in and make connections • ALSO: • Need to start preparing North magnet for chamber • installation the next shutdown
MuTr Installation Tasks--People • Install South Chambers • Trial fit magnet buss---------------------------------------------------------------- Charlie + Co. • Configure scaffolding for FEE Mechanics Installation--------------------- ? • Install in-magnet FEE mechanics----------------------------------------------- 1 week of techs • Install eyebrow and racks -------------------------------------------------------- 1 week of techs • Install Glink/Clink crates (back of magnet------------------------------------- Manlift • for St.2 + 3, on lower lampshades for St. 1) • Install Cross Rib Assemblies----------------------------------------------------- ~2 weeks of crane • and techs • Install Station 1 FEE Plate-------------------------------------------------------- 1 day of crane • Install Station 1 chassis ----------------------------------------------------------- physicists • Re-install magnet buss • Roll in and make connections • ALSO: • North magnet for chamber ------------------------------------------------------- 2 techs, 3-4 mos.
FEE Status • Review postponed because of problems achieving consistent digitization results from sample to sample • Current delay in schedule is ~1 month from schedule that predicted we would be finished installing into magnet on Nov. 10 • Measurments of analog noise meet specs • Also indications that digital noise measurements are within spec (given FPGA uncertainty) • Looking at scheduling review as soon as next week
FEE Assembly Hall Infrastructure Needs • Water to check out FEE cooling systems • Air to check out FEE dry-air systems • Power for racks • Connection to some number of DCMs (in the counting house?) • Connection to T+FC (in the counting house?) • ARCNet communication capabilities • LV control
FEE Installation Tasks • Make connections from Glink/Clink crates to racks • 40 T+FC cables from T+FC fanout in rack to Glink/Clink crates • 100 DCM fibers from Glink/Clink crates to patch panel in rack • Install CRAs. For each CRA: • connect 60(64) analog cables from chambers to chassis at Station 2(3) • connect 8(10) T+FC cables to Glink/Clink crates • connect 4(6) DCM cables to Glink/Clink crates • connect 12(8) HV cables to HV supplies in racks • connect HV cables between dist. boxes and chambers • connect 8(10) LV lines to LV distribution cards in racks • connect 1 ARCNet line to ARCNet hub • connect 3(2) calibration lines to chamber • connect 3(2) calibration lines to calibration crate in rack • connect 1 line to air • connect 1 supply and 1 return line to water • connect chamber gas lines (1 supply, 1 return per chamber) • Checkout of CRAs: • Run cooling water and dry air • turn on LV; download preamps, AMUADCs, FPGAs; collect calibration data • Install Station 1 chassis. For each chassis ~1/4 of above FEEcables; HV and calibration can be done separately from chassis installation.