An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. MuTr Installation Tasks • Should be done prior to shutdown: • Install South Chambers • Trial fit magnet buss • Configure scaffolding for FEE Mechanics Installation • Install in-magnet FEE mechanics • Install eyebrow and racks • Make plumbing and electrical connections to racks • Install Glink/Clink crates (back of magnet • for St.2 + 3, on lower lampshades for St. 1) • Make connections from Glink/Clink crates to racks • Install Cross Rib Assemblies (St. 2 + 3 FEE) • Install Station 1 FEE Plate • Install Station 1 chassis • Re-install magnet buss • Roll in and make connections • ALSO: • Need to start preparing North magnet for chamber • installation the next shutdown

  2. MuTr Installation Tasks • Install South Chambers (should be done prior to shutdown)-------------finish ~Aug 22 • Trial fit magnet buss---------------------------------------------------------------- Aug 22 - Aug 29 • Configure scaffolding for FEE Mechanics Installation • Install in-magnet FEE mechanics----------------------------------------------- Aug 31 - Sep 6 • Install eyebrow and racks -------------------------------------------------------- Sep 7 - Sep 13 • Install Glink/Clink crates (back of magnet------------------------------------- when available • for St.2 + 3, on lower lampshades for St. 1) • Install Cross Rib Assemblies----------------------------------------------------- Sep 20 - Dec 12* • Can start installation in Sept. only if we order boards soon • Had 3 months to install 16 cross-rib assemblies (3.75 days/assembly) • If need to keep Nov. 12 deadline, need to assemble and install 2 CRAs/week • Install Station 1 FEE Plate • Install Station 1 chassis • Re-install magnet buss • Roll in and make connections • ALSO: • Need to start preparing North magnet for chamber • installation the next shutdown

  3. MuTr Installation Tasks--People • Install South Chambers • Trial fit magnet buss---------------------------------------------------------------- Charlie + Co. • Configure scaffolding for FEE Mechanics Installation--------------------- ? • Install in-magnet FEE mechanics----------------------------------------------- 1 week of techs • Install eyebrow and racks -------------------------------------------------------- 1 week of techs • Install Glink/Clink crates (back of magnet------------------------------------- Manlift • for St.2 + 3, on lower lampshades for St. 1) • Install Cross Rib Assemblies----------------------------------------------------- ~2 weeks of crane • and techs • Install Station 1 FEE Plate-------------------------------------------------------- 1 day of crane • Install Station 1 chassis ----------------------------------------------------------- physicists • Re-install magnet buss • Roll in and make connections • ALSO: • North magnet for chamber ------------------------------------------------------- 2 techs, 3-4 mos.

  4. FEE Status • Review postponed because of problems achieving consistent digitization results from sample to sample • Current delay in schedule is ~1 month from schedule that predicted we would be finished installing into magnet on Nov. 10 • Measurments of analog noise meet specs • Also indications that digital noise measurements are within spec (given FPGA uncertainty) • Looking at scheduling review as soon as next week

  5. FEE Assembly Hall Infrastructure Needs • Water to check out FEE cooling systems • Air to check out FEE dry-air systems • Power for racks • Connection to some number of DCMs (in the counting house?) • Connection to T+FC (in the counting house?) • ARCNet communication capabilities • LV control

  6. FEE Installation Tasks • Make connections from Glink/Clink crates to racks • 40 T+FC cables from T+FC fanout in rack to Glink/Clink crates • 100 DCM fibers from Glink/Clink crates to patch panel in rack • Install CRAs. For each CRA: • connect 60(64) analog cables from chambers to chassis at Station 2(3) • connect 8(10) T+FC cables to Glink/Clink crates • connect 4(6) DCM cables to Glink/Clink crates • connect 12(8) HV cables to HV supplies in racks • connect HV cables between dist. boxes and chambers • connect 8(10) LV lines to LV distribution cards in racks • connect 1 ARCNet line to ARCNet hub • connect 3(2) calibration lines to chamber • connect 3(2) calibration lines to calibration crate in rack • connect 1 line to air • connect 1 supply and 1 return line to water • connect chamber gas lines (1 supply, 1 return per chamber) • Checkout of CRAs: • Run cooling water and dry air • turn on LV; download preamps, AMUADCs, FPGAs; collect calibration data • Install Station 1 chassis. For each chassis ~1/4 of above FEEcables; HV and calibration can be done separately from chassis installation.