V12.00.00 Retail Market Release (ROI & NI) Detailed Co-Ordinated Cutover Plan – Walkthrough Thursday 4th April 2019
Retail Market Release v12.00.00 (ROI & NI) Update Thursday4thApril 2019
Market Release v.12.00.00 (ROI & NI) - Plan 1st May 26th June 5th Dec 27th 16th Jan 16th 7th 7th 30th 4th 3rd 25th 29th 3rd 13th 6th Mar Publication of v.12.00.00 Schema Mon 28th Jan (ROI & NI) - Design/Build/Test Final RA Engagement IPT Prep IPT Exec Go Live Easter 2019 Go live Aug B/H v Other (ROI Only) Market Assurance Unicode Conversion SAP Hana Go Live Easter 2019 SAP IS-U Enhancement Pack (8.0) Go Live Easter 2019 Smart Enablement for Meter Installation Go Live Easter 2019 Market Engagement Apr 2019
Market Release V12.00.00 (ROI & NI) – Status • IPT • IPT Execution Completed – Friday 15th March 2019 • IPT Exit Reports issued to RAs – Friday 5th April 2019 • No concerns raised by Market Assurance bodies based on outcome of Market Assurance Engagement • Co-Ordinated Cutover • Co-Ordinated Detailed Cutover Plan published via ReMCoDS Friday 29th March • Schema Instruction Guides (Cutover and Rollback) shared by ATOS – Wednesday 3rd April 2019 • Cutover Workshop with Market Participants – Thursday 4th April 2019 • Cutover/Go-Live • Final RA engagement prior to Cutover – Monday 8th April (ROI & NI) • Cutover Commences Thursday 18th April (ROI) & Friday 19th April (NI)
Cutover Weekend - Overview • V12.00 Retail Market Release – Co-Ordinated Cutover (ROI &NI): • The Cutover weekend schedule will be managed through a detailed list of planned tasks that will progress through a number of key milestones along the way • Critical Cutover activities involving ESB Networks, NIE Networks, ATOS and all Market Participants are planned over the course of the weekend including: • Message Reconciliation activities pre Outage • Self Service EMMA Schema upgrades • MP Backend system updates • A co-ordinated and aligned Cutover approach is critical to ensure a successful outcome • All communication between ESB Networks, NIE Networks and Market Participants throughout Cutover Execution will be managed via ReMCoDS
When will it happen? • In Month Before (i.e. Up To Fri 12th Apr) 2. Week Before (i.e. Mon 15th Ap – Thu 18th Apr (ROI)/Fri 19th Apr (NI)) 3. Cutover Weekend (i.e. From Thu 18th Apr (ROI) and Fri 19th Apr(NI) Until Mon 23rd Apr) 4. Post Cutover • Cutover will be take place over four distinct stages:
Tasks – In Month Before Key Market Tasks RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website • Additional Notes: • Market Participants (ROI & NI): • Market Participants to ensure any Business continuity mechanism is in place for Outage • MPs submit any queries on v12 Schema Self Service pack to ATOS by – Friday 12th April @ 17:00 • ReMCoDS • Each MP will be provided their respective SFTP login details to download their Self Service pack – Monday 8th April
Tasks – Week Before Key Market Tasks RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website
Cutover Weekend – Plan on a Page ……. 8 AM 9 AM 10AM 12PM ……. ……. 6 PM 7 PM 8 PM 9 PM 10 PM 11PM …. …. System Isolation - RoI System Isolation - NI 2 4 1-5 Pre-Cutover Tasks 19 6 7 Central Hub Update Suppliers Apply V12 Schema 5 7 Point of No Return 9 8 6 Supplier STOP MM / RoI Supplier STOP MM / NI 11 NI SUPPLIER – 602 Reconciliations 3 13 10 RoI SUPPLIER – 602 Reconciliations Cutover Completed 12 8 1 Key Market Task - (KMT) Key Market Milestone – (MS) RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website
Tasks – Cutover Weekend Key Market Tasks (Thursday 18th April) RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website
Tasks – Cutover Weekend Key Market Tasks (Friday 19th April) RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website
Tasks – Cutover Weekend Key Market Tasks (Saturday 20th April) RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website
Tasks – Cutover Weekend Key Market Tasks (Sunday 21st April) RMDS website - v12.00.00 Detailed Cutover Plan on RMDS website • Additional Notes (Sunday) • ESBN and NIE Networks: After Milestone 7 has been achieved, activities are undertaken in the following sequence • ESBN and NIE Networks Business Validation Testing • ESBN and NIE Networks confirm the completion of cutover to ReMCoDs
Summary • The dates and timings of individual Key Market Task and Milestones are subject to change based on progress of Cutover • Flexibility is required from all market participants to ensure a successful cutover and resumption of normal market services as planned by Mon 21st Apr @ 23:59 • During cutover all Market Participants are required to update their EMMA via the agreed self service approach in order to be able to send and receive messages • Do not send market messages using Schema Version v11.00.00 after the following times: • Key Market Task 8 - Stop sending Market Messages (ROI) – Thu 18th Apr @18:00 • Key Market Task 9 - Stop sending Market Messages (NI) – Fri 19th Apr @18:00 • Market Participants are requested to be contactable until formal notification of successful Cutover Completion has been confirmed by ReMCoDS • ReMCoDs will inform Market Participants when they can start sending MM’s following achievement of Milestone 8 - Notification that cutover is complete. Resumption of normal services
Contingency Approach • Contingency approach for cutover will be to fix any issues encountered until a specified cut-off time whereby a decision will be made to roll back • In the unlikely event of a rollback being required: • ATOS will provide an instruction guide to MPs to roll back their EMMAs to Schema v11.00.00 • Market Participants will need to roll back their EMMA upgrade, and any associated changes made to their respective backend systems. • A rollback scenario can only be invoked up to: Milestone 7 - Network Operator Testing commences (POINT OF NO RETURN) Sun 21st Apr • The contingency approach after this milestone is a “Fix and go Forward” strategy • ESBN and NIE Networks will collaborate closely withReMCoDSthroughout the cutover period and should the need for a rollback scenario arise, this will be flagged as appropriate via ReMCoDS • ESBN & NIE Networks cutover approaches have been proven via IPT and multiple Dress Rehearsals in their internal testing • MPs EMMA upgrade to V12.00.00 Schema in Cutover mirrors that validated via IPT
V12.00.00 EMMA Self Service Upgrade Refresh & Lessons Learned from IPT
Schema Upgrade Steps • Market participants need to follow the following steps as part of the upgrade - • Pre upgrade check • Download upgrade script from the SFTP site • Running the schema upgrade script as administrator • Upload the upgrade script output log to the SFTP site for Atos to review • Post upgrade check (TIBCO and Additional webforms codes) • Send 999 test message • Confirm that the version number of the 999 message is version 12.00.00 • Confirm that the 999 message sent successfully • Send an email to ATOS to confirm completion of all the EMMA upgrade tasks above (dl-uk-niebusinessappstibco@atos.net)
Self Service – Schema Update Guide • Walkthrough of Market Participant Self Service Schema Upgrade – Instruction Guide Note: In the unlikely event of a Schema rollback being required, a Schema Roll Back Guide will be provided by Atos.
Self Service – Schema Update Guide • Support will be provided by ATOS to Market Participants throughout the Schema Cutover window • Schema Cutover Approach used during Cutover mirrors that used in IPT • Lessons learned from IPT have been incorporated into the cutover plan and Instruction Guide • It is recommended that the same resources who executed the IPT Schema update on the Test EMMA do the same for Production EMMA at Cutover • Support will be provided, if required, by ATOS • Market Participants should not carry out any changes to any EMMA in relation to the v12.00.00 Retail Market Release in advance of formal instruction via ReMCoDS i.e. • Milestone 5- Notification that Central Hub upgrade is complete – Sat 20th Apr • MPs commence EMMA upgrade as per agreed schedule – Sat 20th Apr Note: Do not start this EMMA upgrade task until Milestone 5 has been confirmed by ReMCoDS • On completion of EMMA Upgrade MPs should e-mail ATOS to confirm 999 sent and Log uploaded
V12.00.00 Retail Market Release (ROI & NI) Hypercare Arrangements
Hyper Care - Overview • What is Hypercare? • Hypercare is the stabilisation period after cutover which focuses support for the v12.00.00 Retail Market Release (ROI & NI) implemented over Easter Weekend • Purpose of Hypercare is to ensure and support resumption of normal BAU market operations following cutover • When is it? • Hypercare begins immediately after cutover and runs for a period of up to 2 weeks
Hyper Care - Arrangements • Week 1 Post Go-Live – Tue 23rd to Fri 26th April • ReMCoDS will schedule two conference calls in the first week with Market Participants, to provide a general status update and discuss any items raised or queries that Market Participants may have: • Wed 24th April – Time TBC • Fri 26th April – Time TBC • Week 2 Post Go-Live – Mon 29th April to Fri 3rd May • TBC – based on checkpoint on Fri 26th April
V12.00.00 Retail Market Release (ROI & NI) Post Cut Over
Facilitate energy efficiencies in Local Authority Public Lighting Market Release v12.00.00 - Published on RMDS Website • The Schema Release v12.00.00 is due to be published on the RMDS website on Tuesday 23rd April 2019. This release will implement the following Schema and Non Schema items.
Eircodes – Batch Update Process • Approach • ESB Networks plan to process the set of 1.5 Million Eircodes • This approach has been validated by ESB Networks performance testing • Update Period Update Schedule will commence on Wed 1stMay and run for a period of 12 weeks • Schedule & Volumes • Weekdays - Monday to Friday • From: 8.00 p.m. Until : 9.00 p.m. • Estimated Volumes: ~ 15K MPRNs/Day • Weekends - Saturday to Sunday • From: 6.00 a.m. Until: 7.00 a.m. • Estimated Volumes: ~ 50K MPRNs/Day Refer to the v12.00.00 Market Release FAQ page on the RMDS website for further details. Link here