An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Project Management

  2. Learning Objectives • Discuss the behavioral aspects of projects in terms of project personnel and the project manager. • Discuss the nature and importance of a work breakdown structure in project management. • Give a general description of PERT/CPM techniques. • Construct simple network diagrams.

  3. Learning Objectives • List the kinds of information that a PERT or CPM analysis can provide. • Analyze networks with deterministic times. • Analyze networks with probabilistic times. • Describe activity “crashing” and solve typical problems.

  4. Projects Build A A Done Build B B Done Build C C Done Build D Ship JAN FEB MAR APR MAY JUN On time! Unique, one-time operations designed to accomplish a specific set of objectives in a limited time frame.

  5. Project Management • What are the Key Metrics • Time • Cost • Performance objectives • What are the Key Success Factors? • Top-down commitment • Having a capable project manager • Having time to plan • Careful tracking and control • Good communications

  6. Project Management • What are the Major Administrative Issues? • Executive responsibilities • Project selection • Project manager selection • Organizational structure • Organizational alternatives • Manage within functional unit • Assign a coordinator • Use a matrix organization with a project leader

  7. Project Management • What are the tools? • Work breakdown structure • Network diagram • Gantt charts • Risk management

  8. Planning and Scheduling Gantt Chart Locate new facilities Interview staff Hire and train staff Select and order machine Installation / Remodel Move in/startup MAR APR MAY JUN JUL AUG SEP OCT NOV DEC

  9. Key Decisions • Deciding which projects to implement • Selecting a project manager • Selecting a project team • Planning and designing the project • Managing and controlling project resources • Deciding if and when a project should be terminated

  10. Project Manager Responsible for: Work Quality Human Resources Time Communications Costs

  11. Ethical Issues • Temptation to understate costs • Withhold information • Misleading status reports • Falsifying records • Comprising workers’ safety • Approving substandard work

  12. Project Life Cycle Feasibility Planning Management Concept Execution Termination

  13. Work Breakdown Structure Project X Level 1 Level 2 Level 3 Level 4

  14. PERT and CPM PERT: Program Evaluation and Review Technique CPM: Critical Path Method • Graphically displays project activities • Estimates how long the project will take • Indicates most critical activities • Show where delays will not affect project

  15. The Network Diagram • Network (precedence) diagram – diagram of project activities that shows sequential relationships by the use of arrows and nodes. • Activity-on-arrow (AOA) – a network diagram convention in which arrows designate activities. • Activity-on-node (AON) – a network diagram convention in which nodes designate activities. • Activities – steps in the project that consume resources and/or time. • Events – the starting and finishing of activities, designated by nodes in the AOA convention.

  16. The Network Diagram (cont’d) • Path • Sequence of activities that leads from the starting node to the finishing node • Critical path • The longest path; determines expected project duration • Critical activities • Activities on the critical path • Slack • Allowable slippage for path; the difference the length of path and the length of critical path

  17. A Comparison of AON and AOA Network Conventions A comes before B, which comes before C A C (a) B A B C A A A and B must both be completed before C can start (b) C C B B B B and C cannot begin until A is completed B A (c) A C C Activity on Activity Activity on Node (AON) Meaning Arrow (AOA)

  18. A Comparison of AON and AOA Network Conventions C and D cannot begin until A and B have both been completed A C B A C (d) D B D A C A C B D B D Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) C cannot begin until both A and B are completed; D cannot begin until B is completed. A dummy activity is introduced in AOA (e) Dummy activity

  19. A Comparison of AON and AOA Network Conventions B A C D Activity on Activity Activity on Node (AON) Meaning Arrow (AOA) B and C cannot begin until A is completed. D cannot begin until both B and C are completed. A dummy activity is again introduced in AOA. A B D (f) C Dummy activity

  20. Project Network – Activity on Arrow AOA 4 Order setup 2 Locatefacilities Remodel 1 5 6 Move in Interview Hire andtrain 3

  21. Project Network – Activity on Node Order setup Locatefacilities 2 6 1 Move in Remodel 5 S 7 Hire andtrain Interview 4 3 AON

  22. Time Estimates • Deterministic • Time estimates that are fairly certain • Probabilistic • Estimates of times that allow for variation

  23. Computing Algorithm • Network activities • ES: earliest start • EF: earliest finish • LS: latest start • LF: latest finish • Used to determine • Expected project duration • Slack time • Critical path

  24. Determining the Project Schedule Earliest start (ES) = earliest time at which an activity can start, assuming all predecessors have been completed Earliest finish (EF) = earliest time at which an activity can be finished Latest start (LS) = latest time at which an activity can start so as to not delay the completion time of the entire project Latest finish (LF) = latest time by which an activity has to be finished so as to not delay the completion time of the entire project Activity Description Time (weeks) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Total Time (weeks) 25 Perform a Critical Path Analysis Table 3.2

  25. AON Example Milwaukee Paper Manufacturing'sActivities and Predecessors

  26. AON Network for Milwaukee Paper Activity A (Build Internal Components) A Start Activity B (Modify Roof and Floor) B Start Activity

  27. AON Network for Milwaukee Paper Activity A Precedes Activity C A C Start B D Activities A and B Precede Activity D

  28. AON Network for Milwaukee Paper F A C E Start H B G D Arrows Show Precedence Relationships

  29. AOA Network for Milwaukee Paper C (Construct Stack) 4 2 F (Install Controls) A (Build Internal Components) E (Build Burner) H (Inspect/ Test) Dummy Activity 7 1 6 B (Modify Roof/Floor) G (Install Pollution Device) D (Pour Concrete/ Install Frame) 3 5

  30. Determining the Project Schedule Activity Description Time (weeks) A Build internal components 2 B Modify roof and floor 3 C Construct collection stack 2 D Pour concrete and install frame 4 E Build high-temperature burner 4 F Install pollution control system 3 G Install air pollution device 5 H Inspect and test 2 Total Time (weeks) 25 Perform a Critical Path Analysis

  31. Determining the Project Schedule Activity Name or Symbol A Earliest Finish Earliest Start ES EF LS LF Latest Finish Latest Start 2 Activity Duration Perform a Critical Path Analysis

  32. ES/EF Network for Milwaukee Paper (Forward pass) ES EF = ES + Activity time Start 0 0 0

  33. ES/EF Network for Milwaukee Paper EF of A = ES of A + 2 ESof A A 2 0 2 Start 0 0 0

  34. ES/EF Network for Milwaukee Paper EF of B = ES of B + 3 A 2 ESof B 0 2 0 3 Start 0 0 B 3 0

  35. ES/EF Network for Milwaukee Paper A 2 C 2 0 2 2 4 Start 0 0 0 B 3 0 3

  36. ES/EF Network for Milwaukee Paper A 2 C 2 0 2 2 4 Start 0 0 = Max (2, 3) D 4 0 3 B 3 0 3 7

  37. ES/EF Network for Milwaukee Paper A 2 C 2 0 2 2 4 Start 0 0 0 B 3 D 4 0 3 3 7

  38. ES/EF Network for Milwaukee Paper A 2 C 2 F 3 0 2 4 7 2 4 E 4 H 2 Start 0 0 4 8 13 15 0 B 3 D 4 G 5 0 3 3 7 8 13

  39. LS/LF Times for Milwaukee Paper (Backward pass) A 2 C 2 F 3 0 2 4 7 2 4 E 4 H 2 Start 0 0 4 8 13 15 13 15 0 LS = LF – Activity time B 3 D 4 G 5 0 3 3 7 8 13 LF = EF of Project

  40. LS/LF Times for Milwaukee Paper A 2 C 2 F 3 0 2 4 7 2 4 10 13 E 4 H 2 Start 0 0 LF = Min(LS of following activity) 4 8 13 15 13 15 0 B 3 D 4 G 5 0 3 3 7 8 13

  41. LS/LF Times for Milwaukee Paper LF = Min(4, 10) A 2 C 2 F 3 0 2 4 7 2 4 2 4 10 13 E 4 H 2 Start 0 0 4 8 13 15 13 15 4 8 0 B 3 D 4 G 5 0 3 3 7 8 13 8 13

  42. LS/LF Times for Milwaukee Paper A 2 C 2 F 3 0 2 4 7 2 4 2 4 10 13 0 2 E 4 H 2 Start 0 0 4 8 13 15 13 15 0 0 4 8 0 B 3 D 4 G 5 0 3 3 7 8 13 4 8 8 13 1 4

  43. Computing Slack Time After computing the ES, EF, LS, and LF times for all activities, compute the slack or free time for each activity • Slack is the length of time an activity can be delayed without delaying the entire project Slack = LS – ES or Slack = LF – EF

  44. Computing Slack Time Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS – ES Path A 0 2 0 2 0 Yes B 0 3 1 4 1 No C 2 4 2 4 0 Yes D 3 7 4 8 1 No E 4 8 4 8 0 Yes F 4 7 10 13 6 No G 8 13 8 13 0 Yes H 13 15 13 15 0 Yes

  45. Critical Path for Milwaukee Paper A 2 C 2 F 3 0 2 4 7 2 4 2 4 10 13 0 2 E 4 H 2 Start 0 0 4 8 13 15 13 15 0 0 4 8 0 B 3 D 4 G 5 0 3 3 7 8 13 4 8 8 13 1 4

  46. ES – EF Gantt Chartfor Milwaukee Paper 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test

  47. LS – LF Gantt Chartfor Milwaukee Paper 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 A Build internal components B Modify roof and floor C Construct collection stack D Pour concrete and install frame E Build high-temperature burner F Install pollution control system G Install air pollution device H Inspect and test

  48. Critical Path Example Activity Immediate Predecessors Time (weeks) A - 6 B - 7 C A 3 D A 2 E B 4 F B 6 G C, E 10 H D, F 7 Perform a Critical Path Analysis

  49. 21 0 0 21 A 6 C 3 F 6 0 6 7 13 6 9 12 14 8 11 8 14 2 8 E 4 H 7 Start End 0 21 21 0 7 11 13 20 14 21 7 11 0 0 B 7 D 2 G 10 0 7 6 8 11 21 0 7 11 21

  50. Computing Slack Time Earliest Earliest Latest Latest On Start Finish Start Finish Slack Critical Activity ES EF LS LF LS – ES Path A 0 6 2 8 2 No B 0 7 0 7 0 Yes C 6 9 8 11 2 No D 6 8 12 14 6 No E 7 11 7 11 0 Yes F 7 13 8 14 1 No G 11 21 11 21 0 Yes H 13 20 14 21 1 No