1 / 26

The Control System For LHC Hardware Commissioning

This report discusses the strategy, applications, and common services for the hardware commissioning of the LHC. It also addresses issues and provides conclusions based on the findings.

brunson
Download Presentation

The Control System For LHC Hardware Commissioning

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. The Control System For LHC Hardware Commissioning The Application Infrastructure Eugenia Hatziangeli Reporting on the work of AB/CO and AB/OP

  2. Contents • Our Strategy • Applications for LHC hardware commissioning • Common services • Issues • Conclusions

  3. Our Strategy • Choose appropriate technology • For high level controls, use software developed for TI8,TI2, LEIR • For new systems apply industrial solutions when appropriate • Cryogenics, Quench Protection, Powering Interlocks • Integrate together high level with industrial controls • Develop once, using a simple, iterative development model • Use standard components where possible • Common CO general services (Alarms, Logging, FDs, PM, …) • Validate complete integration of our systems • Build on every possible controls milestone • Dry runs • Improve the functionality • Go from simple to more general • Solutions deployed progressively to meet successive milestones

  4. Contents • The strategy • Applications for LHC hardware commissioning • The Scope • Industrial Controls - UNICOS • High Level Controls - LSA • Common services • Issues • Conclusions

  5. The Scope - LSS8L • LSS8L: commissioning first magnets in LHC • 2 powering subsectors • 29 electrical circuits • Vacuum, Cryogenics, Power converters, Quench protection (QPS), Powering interlocks (PIC) An excellent milestone for controls, “the fun part!”

  6. Circuit Commissioning Controls Middleware (CMW) – The integration glue New for HWC Logging Post-Mortem LHC Ref DB Detailed spec LHC-D-HCP-0005 rev 0.2 (SACEC) Automated Test Procedures (Sequencer) PVSS-CMW Interface PVSS-CMW Interface CMW PVSS Supervision PVSS Supervision Gateway(s) ETHERNET S7 CMW Gateway WorldFIP PC_PERMIT QPS PIC Power Converter CIRCUIT_QUENCH PC_FAST_ABORT POWERING_FAILURE DISCHARGE_REQUEST PC_DISCHARGE_REQUEST

  7. Industrial Controls - Cryogenics • Production Cryogenics (surface, UX, UJ) controls already deployed • Present functionality adequatefor HWC • > 50% developed • 30% deployed • System validation test done and it is operational • Tunnel Cryogenics (QRL, magnets, DFB) controls • Same framework as the Production Cryogenics (AT/ACR & AB/CO) • For supervision no coding, just configuration • 1st version for QRL test ready in Jun ‘05 • 1st version for LSS8L test ready in Nov ‘05

  8. Industrial Controls - PIC • Under development but delayed - lost the fellow responsible for the work • Prototype version ready in Jul ‘05 • First operational version available in Aug ‘05 (lab tests) • Final operational versions is needed for LSS8L Dec ’05 Powering Subsector Management of powering permits

  9. Industrial Controls - QPS • Test setupapplication(AT/MEL)ready May ‘05for surface tests (now) • end May ‘05fully operational • 2nd version supervision, compliant to the LHC naming conventions ready end Aug ‘05 • Full controls will be operational Sep ‘05 • Final operational versions is needed for LSS8LDec ’05 Overview

  10. Industrial Controls - Vacuum • Same application for SPS, TI8 and TI2 • The application for HWC ready - by end May ‘05 • Application must be deployed operationally for QRL tests Jun ‘05 Overview QRL & Cryo vacuum sectors Pressure profile QRL & Cryo Vacuum

  11. High Level Controls - LSA • What is available for the control of electrical circuits • On-line control database • Layout, configuration, settings, equipment description • Settings Generation • Generation of the commissioning functions based on the optics • Settings Management • Functions or values for all parameters (physics to hardware) • All modification recorded, roll-back possible • Hardware Exploitation • Equipment Control, Measurements, Interface to PC • Successfully deployed in TT40, TI8, LEIR Generic Equipment Control Settings Visualization Measurement of PCs

  12. High Level Controls - The Sequencer Sequence Monitoring 24HrsHeatRuns with ramp graph Circuits,PCs and test selection • A dedicated set of instructions developed for HWC • The following tests are implemented • 24 hour heat runs test • PC_permit test • PC_permit including B2 pc_permit1 and 2 • Powering failure • Circuit Quench via QPS • PC discharge request • PIC discharge request • PIC fast abort request via PIC • First version in place and tested Circuit Quench via QPS Battery Tests

  13. Contents • The strategy • Applications for LHC hardware commissioning • Common services • Issues • Conclusions

  14. Common Services for HWC • TT40, TI8, Cryo, Vacuum • TCR, LEIR • CPS,SPS,LEIR • Some experience from TT40 • TI8 • LEIR • CPS, SPS, SM18 • LHC Logging service • Alarm (LASER) system • Timing • Post-Mortem • Data collection • Event analysis • Fixed displays • Console manager • elogbook

  15. Post Mortem - Data Collection • The Process • Source systems push PM data to PM server • PM server saves data in a standard format • PM analysis tools access those files • Where we are now • Data collection chain is testedwith PC system PM data • Prototype PM browserin place • Issues with CMW server seen during PC tests are being investigated

  16. Post Mortem - Analysis QPS PIC PC • Four level analysis • Event analysis • Interaction analysis (QPS-PIC, PIC-PC) • Per system analysis (QPS, PIC, PC) • Data Verification • Where are we now • UR are under discussion (SACEC) • Start with the QPS as a pilot analysis • PM analysis needed in Dec ‘05 for the Interlock & Powering tests

  17. Fixed Displays • Implementation based on TI8 Fixed Displays (FD) • Graphical representation of data in place • Add functionality for text representation • Prototype with PC in Jun ‘05 • 1st basic version in Jul ‘05

  18. Contents • The strategy • Applications for LHC hardware commissioning • Common services • Issues • Data Exchange • New Software Development • User Requirements • Resources • Computer Security • Conclusions

  19. Issues - Data Exchange • Between different systems • QPS to PIC (QPS gives the power permit) • Tunnel Cryogenics system with Vacuum • Sequencer with QPS, PIC, PC • Fixed Displays data collection (Cryo, Vacuum, PC, CV,…) • Communication packages • CMW, AB/CO standard for all CO communications • CMW -> PVSS interface available in Aug ‘05 [FD, Sequencer] • PVSS -> CMW interface available, prototype in place [QPS, PIC] • DIP, CERN-wide for inter-domain data publication • DIP <-> PVSS interface available(IT/CO) but not yet operational [Vacuum, QRL]

  20. Issues - New Software Development • Many new applications under development • Tunnel Cryogenics controls • QPS • PIC • Post Mortem • Fixed Displays • Data exchange communication interfaces • Software will be ready in time for HWC, but a challenge for validation • Use simulation for tests and debugging • Connect to real system when available

  21. Issues - User Requirements • Tight links with SACEC for the cold circuits • All other systems yet to be studied!! • Know what is needed for • Short circuit tests • 24-hour heat run • Interlock tests • Working on • Powering tests • Post Mortem requirements

  22. Issues - Resources • Same people - competing activities • LEIR - HW and beam commissioning [Apr-end ‘05] • CNGS [end ‘05] • LHC Inj. Lines commissioning (TI2) [Jun 05] • CCC [2nd half ‘05] • SPS & CPS start up with major changes [end ‘05] • Due to tight resources, we aim at basicfunctionality and improve progressively • Improvements need qualified software engineers; it takes several months for newcomers to understand accelerator needs

  23. Issues - Computer Security • New security policy on TN from Jan ‘06 -> Isolate from hackers • No major implications on HWC and FCR if on TN • For clients on GN no direct access to equipment on TN • Dedicated Gateways will provide connectivity • Formal authorisation for new equipment on TN • NoWireless & DHCP on TN

  24. Conclusions • The hardware commissioning is a major milestone and a new phase for controls • Controls critical for HWC, LSS8L important for Controls • It is the first time that high level and industrial based controls will be integrated • Integration with CMW is a critical issue • A lot of software is now in place and validated • Use existing software where possible but new software is required and very high pressure on specific resources • Dry runs for all critical systems • Requirements studies for systems not covered by SACEC should start in good time • HWC has a tight schedule but so has AB/CO • Controls availability and automation are essential to meet schedule and save time • Implement basic functionality and improve progressively

  25. Thank you Contributions from R. Billen, P. Charrue, F. Chevrier, B. Frammery, P. Gayet, K. Kostro, G. Kruk, M. Lamont, R. Lauckner, I. Laugier, F. di Maio, L. Mestre, H. Milcent, V. Paris, A. Rijllart, R. Schmidt, M. Zerlauth

  26. FCR in UA83 - Consoles and Fixed Displays Pre-configured laptops Cryogenics Powering tests Interlocks Post-Mortem

More Related