An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Pump Design & Selection • Dick Hawrelak • Presented to UWO CBE 497 • 16 Oct 01

  2. Good Design References • Flow of Fluid Through Valves and Fittings by Crane. Technical Paper No. 410-C. • Centrifugal Pumps and System Hydraulics, Chem Eng’g, 4 Oct 82, p-84, by Karassik. • Chem Eng Handbook, Perry 6, Sections 5 and 6 • Primer software by Durco http://www.durcopump.com • PumpSel 6.2™ (rev .07) by Durco http://www.durcopump.com

  3. Pump Design Stages • Phase 2 – Process alternatives & optimization. • Phase 3 – P&IDs, preliminary layout, approx design, specification, pre-selection, cost estimate. • Phase 4 – detailed design. • Final layout – check piping & elevations. • Final detailed hydraulic design & selection. • Suitability (NPSH, SSS, Re-circulation). • Final cost estimate.

  4. Excel Pump Design Program • Plant Design Programs on CD-ROM • Quick Pump Design V1.3 • Contains Following Features • Line Sizing • Control Valve Sizing • Check Valve Sizing • Orifice Plate Sizing • NPSH, NS, SSS, HP calculations • System Head Curve • Limited Pump Selection • Used along with Durco’s PUMPSEL and PRIMER

  5. Draw Sketch of Pump System • Collect physical property data (density, viscosity, vapor pressure). • Show line details, size, schedule or wall thk, check valves, control valves, block valves, reducers/expanders (may have to take a WAG). • Show origin (min.) and destination pressures (max.). • Show origin and destination elevations for static head. • Combine services where practical & economical.

  6. Typical Pump Sketch

  7. Size Suction and Discharge Lines • Break lines into sizable sections. There may be different sizes in any one branch. Eg 4”, 6” and 8” sections. • Estimate the number of elbows, block valves, fittings, etc. (WAG in Ph 2). “Fitting” pgm in Phase III. • Expand line sizing routine for record keeping. This will simplify phase 4 checking.

  8. Line Size Equations • Re No. = 6.31 ( W ) / ( d ) / ( cP ) • Darcy friction factor f = 4 ( f Fanning ) f Darcy by “all-in-one” Chen Equation • DP100 = 0.000336 ( f )( W )^2 / ( DL ) / ( d )^5 • Max Dp100 usually limited to 1.0 psi per 100 ft. • K = ( f ) ( L / D ) for pipe • K = ( f Turb ) ( L / D ) for valves and fittings • K total = K pipe + K valves & fittings • DP = 2.8E-07 ( K total )( W )^2 / ( DL ) / ( d )^4 • Abs roughness e = 0.00015 for clean pipe, ft. • Abs roughness e = 0.0004 for dirty pipe, ft.

  9. Size Check Valves in Each Discharge Line Branch • Line sizing program built-into Pump pgm. • Check pipe spec for type of check valve. • Check minimum line velocity to keep ChV in open position. Prolonged operation at reduced rates may cause ChV chatter and damage to ChV. • Operation with damaged ChV is extremely hazardous.

  10. Typical Check Valve Equation • For a Swing Check Valve (see Crane, page A-27) • K = 100 ( f Turb ) for pressure drop • Minimum Velocity, fps = 35 / ( DL )

  11. Size Orifice Plates in Each Branch • See Line sizing routine. • Orifice Plate pressure drop usually in three ranges. • Typically 0.5, 1.0 or 2.0 psi

  12. Typical Orifice Equation • Beta = d1 / d2 should be in range 0.2 to 0.7 • d1 = orifice dia., d2 = pipe dia., inches • Re No. based on d2, the pipe diameter • W = 1891 ( d1 )^2 ( C ) (( DP )( DL))^0.5 • C = Flow Coefficient for square edged orifices (see Crane, page A-20) • C = Function of Re No. and Beta ratio • C should be in range 0.6 to 0.8

  13. Control Valves • Select each branch with control valves and use line size routine to size control valves assuming Fisher Equal Percentage type valves. • Poor CV selection – no control, pump running on by-pass…may need two control valves. • If too large DP taken across control valve, it may be better to trim impeller, save CV wear & energy. • Pump program should use CV in controlling line. • DP CV / (DP CV + DP fric) = approx 0.1 to 0.3. Default DP control valve = 10 psi.

  14. Typical Control Valve Equations • Cv = ( USGPM )( SG / DP )^0.5 • Cv = Liquid Sizing Coefficient. • SG = Specific Gravity. • DP = Pressure Drop (10 psi default) • Typical control valve is an equal percentage type valve. • Cv depends on valve size, % valve opening, and flow.

  15. Blocked-in Operation. • Determine features required for blocked-in operation. • Low flow shut-down. • High temperature shut-down. • Recycle plus cooling. • Pumps can explode in a short period of time if left running while blocked-in and no high temperature shut-down is provided. • Pump explodes, pieces rocket 275m, hits truck, kills driver. • Pump leaks under high pressure, liquid catches fire and destroys plant.

  16. Suction Conditions • Determine NPSH available. • NPSH = SP – VP + HL – DP friction all in ft of liq. • Boiling liquids, SP = VP. Raise height or reduce DP. • Poor NPSH causes pump cavitation, high vibration & ultimately pump failure (hazard). • Pump fails to perform as designed without NPSH available greater than NPSH required. • Typically, NPSH avail 12 ft. vs 10 ft. req’d. • Pump Vendor will tell you NPSH required based on pumps selection.

  17. System Head Curve • Determine Controlling Branch – I.e the one that requires the maximum differential head. • Determine the system curve for all items except the control valve. • For Dp at reduced USGPM, assume DP is proportional to the square of the flow. • Include static head.

  18. Pump Selection • Hundreds of pumps to select from. • Which selection is best? • Which RPM to use? • What HP size & type of motor to select, explosion proof, TEFC? • Download Durco PUMPSEL and PRIMER on internet (program is free). • http://www.durcopump.com

  19. Durco PUMSEL Program Input • From Quick Pump Design V1.3 enter: • Design USGPM • System head, in ft. • Specific Gravity • Pumping temp, Deg F • Viscosity in Centipoise • NPSH available in ft. • 3 points from system curve.

  20. PUMPSEL Output • Selects all available pumps • Gives Impeller sizes • Gives HP and NPSH Required • Gives a cost estimate (PRIMER) • Gives options for types of pumps • Gives all kinds of help on all features. • PUMPSEL is a must for any design group. • Program also available from Gould.

  21. Typical Pump Head Curves

  22. Selected Pump

  23. Suction Specific Speed, SSS • SSS is an Index number descriptive of the suction charateristics of a pump impeller. • SSS = (rpm)(Q @ BEP)^0.5 / (NPSH @ BEP)^0.75 • Pumps operating at SSS greater than 11,000 had a high failure frequency (hazard). • Low capacity operation causes inlet recirculation, impeller erosion, shaft deflections, bearing failures and seal problems which lead to leakage. • Pump program predicts recirculation as % of SSS.

  24. Dissolved Gases • Absorbed gas follows Henry’s Law xa = (pp / Pt) / H. • Dissolved gases are like entrained bubbles. Residence time in suction vessel may be too short. • Dissolved gases causes problems similar to NPSH cavitation. • Prevent vapor entrainment with vortex breakers.

  25. Material Transfer • Need multiple checks on quantity of material transferred to storage. • Weigh scales, level checks, mass = (flow rate)(time) on computer. • Time control EBVs to minimize Water Hammer problems.

  26. Excess Flow Protection • Pumps cannot be allowed to run out on the impeller curve, may burnout motor if motor not selected for runout. • May need excess flow protection.

  27. Repeat Design in Phase IV • All of the above details are checked again in Phase IV Engineering. • Necessary to have good documentation. • Poor Phase III Design & Selection means rework during expensive Phase IV stage.