1 / 18

Electronic Weld Record (eWR) for Pipe Welding Process Change

This ongoing project aims to replace paper-based pipe weld records with an Electronic Weld Record (eWR) application. The eWR will streamline the welding value stream by eliminating manual processes, reducing errors, and improving efficiency. The project aligns with Newport News Shipbuilding's Integrated Shipbuilding Strategy and targets VCS, Columbia, and Aircraft Carriers (New Construction and Overhaul) programs. Estimated potential savings are significant.

bstark
Download Presentation

Electronic Weld Record (eWR) for Pipe Welding Process Change

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. S2703 - Electronic Weld Record (eWR) - Pipe Process Change – Under Cognizance of Industry Ongoing Project Derek Hassell Newport News Shipbuilding NSRP Presentation March 13, 2019 DCN# 43-5036-19

  2. Project Team (Organization Chart) Paul Huang – Program Officer PMS 450 Dale Orren – Deputy Director Warren Southerland – Project Manager Tim Wallace – Project Technical Representative Charles McNamara – PMS 450 Dave Hart – LCE Traci Jones – ManTech Project Manager Derek Hassell – Quality Manager (Project Lead) Ross Gambill – Prod Planning Sched Manager (Technical Lead) Joe Sabol – Director (Sponsor) Dale Bell – Quality Engineering Manager (Sponsor)

  3. ManTech Project • Electronic Weld Record (eWR) - Replace paper-based pipe weld records with an Electronic Weld Record Application • Start Date/End Date: Nov 2016/Aug 2019 • Aligns with Newport News Shipbuilding Integrated Shipbuilding Strategy • Programs Targeted: VCS, Columbia, Aircraft Carriers (New Construction, Overhaul) • Estimated potential savings: • VCS: Estimated $1.5M per hull, per year $2.9M (based on working 9 VCS in-process hulls per year), and 5 years is $14.5M. • Carriers: Estimated $1.9M per new construction hull and $1.1M per carrier overhaul. Per year savings of $280K (for each carrier)

  4. eWR – Overall Vision

  5. Project Objectives/Benefits • The objective of this project is to develop an Electronic Weld Record System that will utilize the following electronic features throughout the welding value stream. • Signature, workflow, real time data access, certification, storage • eWR will provide process improvements that will eliminate/reduce the following for VCS/CVN pipe numbered weld joints: • Welding/NDT paper based forms (6 VCS/CVN Pipe Weld Records) • Routing and transporting forms for collecting signatures/data • Manual data input into ERS and SAP • Manual tracking/updates/review/status reporting • Printing paper forms and making copies • Paper record storage (boxes, file cabinets, warehouse) • Unnecessary fields and duplication of data • Editorial issues (e.g., missing, incorrect) caused by handwritten errors • Rework caused by loss of paper records • Time to hand deliver, certify, review, verify, monitor and track records

  6. Interesting Project Data • Assumptions (in-process per year): • 9 VCS Hulls • 1 Carrier New Construction (X2) • 1 Carrier Overhaul • Project Data: • # of weld/NDT paper records currently used at NNS = over 25 (e.g, Nuc, Non-Nuc, Carrier, VCS, carrier, pipe) • Initial project focus = 6 pipe weld/NDT records (includes Nuc/Non-Nuc & VCS/Carriers) • Handwritten signatures & data entry per VCS/Carriers weld records = Signatures can be over 25 and data entry over 50 per record by 5 different departments • Record Review VCS 905 = each record can be reviewed by up to 5 different persons • # of records processed per year for 6 records = Est. 36,000 • # of pcs of paper printed per year for 6 records = Est 126,000 • Total time (in hours) per year spent processing 6 records = Est. 50,000 • # of non-value added process steps for VCS records = Est. 119

  7. Current State Process Map

  8. Project Schedule • Period of Performance: 12/07/2016 – 8/30/2019 3/13/2019

  9. eWR Application • Uses SAP and eWICC (uses LX and Welder Work Assignment data) as data sources • Connects to SAP to read and write back • Allows users to enter data and sign at work location • Allows inspectors to accept/reject a weld joint • Allows record review to certify a joint • Allows work to progress to next step in process with signature • Can be used by desktop, laptop, tablet and/or phone (future) • User roles - fitter, welder, foreman, inspector, record review, general users

  10. eWR Application – Fitter Screen

  11. eWR Application – Fitter Screen

  12. eWR Application – Fitter Screen

  13. eWR Application – Welder Screen

  14. eWR Application – Foreman/Inspector Screen

  15. Transition / Implementation Status • Technology Transition Plan (TTP) • Original signed TTP completed (3/30/17) • Draft updated TTP based on changes to POP and NNS Management currently being routed for review/comments. • Implementation Status • The project is not implemented, as it is still in active development • An implementation plan will be developed during Phase II of the project (based upon research discoveries) and will be a deliverable of Task 9 • On the next slide is a table with the high level summary of known implementation requirements with place holders for unknown requirements

  16. Implementation Plan - VCS

  17. Implementation Plan - CVN

  18. Near-Term Activities • Near-Term Milestones to be Addressed • Subtask 6 – Onsite deployment and configuration – Due 3/6/2019 (In-Process) • Risk Reduction Items to be Addressed • Continue heightened awareness of the schedule to minimize future delays • Implementation Actions to be Addressed • None; project is in active development