LCLS Operations Plans John Arthur – LCLS Experimental Operations April 21, 2009
LCLS Organization LCLS Director Dale Knutson Accelerator Systems Div John Seeman operate accelerator for science Experimental Facilities Div Jochen Schneider operate instruments for science Business Div Cindy Lowe Engineering Physics Div David Schultz Strategic Projects Div John Galayda LCLS Construction LUSI
LUSI resources matrixed in LCLS Director Instrument scientists Accelerator Systems Div Experimental Facilities Div Business Div Engineering Physics Div Strategic Projects Div Engineers LUSI Controls PMCS
Resources move as instruments turn on LCLS Director Instrument scientists Accelerator Systems Div Experimental Facilities Div Business Div Engineering Physics Div Strategic Projects Div Engineers LUSI
Division of responsibility ASD responsibility Undulator Hall XFD responsibility Near Experimental Hall Front End Enclosure Far Experimental Hall
Experimental Facilities Division (XFD) XFD is the administrative home of the LUSI Instrument Scientists
Experimental Facilities Division Tasks • Manage safe operations in LCLS experimental areas • Manage LCLS user program • Maintain and upgrade X-ray instrumentation • Enable good user science; initiate in-house research
Current XFD Priorities LCLS Construction: Installation in FEE, Hutch 1 Augment scientific and support staff Create structure for safe operations Begin User program LUSI: Accelerate schedule
The LCLS X-ray Beamline X-ray transport tunnel Far Experimental Hall Near Experimental Hall Front End Enclosure
Diagnostics and Offset Mirrors in the FEE Two-phase installation Phase 1 Solid Attenuators Gas Attenuator Calorimeter Beam Direction Slit Gas Detectors K-Mono 5 mm collimator Direct Imager (Scintillator) FEL Offset Mirror Systems Phase 2
FEE installation plan • Phase 1 includes all X-ray diagnostics • Currently shipping to SLAC from LLNL • Installed, wired by late April • First beam by mid May • Phase 2 includes mirrors • Install most component in April • Beam-alignment cameras installed in June
LCLS Offset Mirror Systems 800-2000 eV to Hutch 1 HOMS: Hard x-ray Offset Mirror System SOMS: Soft x-ray Offset Mirror System insertable 800-2000 eV to Hutch 2 insertable 2000-25000 eV to Hutch 3-6
The first two LCLS instruments AMO Soft X-ray beamline without monochromator, for high-field experiments Funded by LCLS Construction Installation June 2009 Commissioning July 2009 SXR Soft X-ray beamline with monochromator, for materials science Funded by SXR Consortium Installation January 2010 Commissioning March 2010
Creating Operations Structure • LCLS Organization • Strong ties between XFD and ASD • XFD directives • XFD training plan and documentation • SAD, ASE to include NEH • Key XFD operations staff • Top managers (Safety Officer, Program Manager) • Area managers • Floor Coordinators • Accelerator Readiness Review • mid-late June
LCLS X-ray Operations plan • Sept-Dec 2009, with 1 instrument (AMO) • Mar-July 2010, with 2 instruments (AMO, SXR) • Aug-Dec? 2010, with 3 instruments (AMO, SXR, XPP) • 2-3 more instruments in 2011 • Steady-state X-ray operations at ~4000 hrs/year • Scheduled in blocks of about 6 months, with periodic brief interruptions for machine studies • Typical experiment will last for about 1 week
Transition of LUSI instruments to XFD • XFD contributes science guidance to instrument planning • LUSI scientists are matrixed from XFD • Transition from Project to Operations is marked by Instrument Readiness Review • Formal in-house review, includes review of standard operating procedures • XFD manages each instrument in operations phase
LCLS User Program • Goal: safe, efficient operation promoting the best science • LCLS will be a DOE-BES User Facility • Access through proposal/review process • LCLS scientific staff frequently collaborate with users, also maintain independent research programs
User Program Management • LCLS and SSRL are combining resources, creating a common User Administration Group • Managed by Cathy Knotts • Manages User training, User agreements, User metrics • LCLS is supporting one added User Administrator
LCLS Proposal Review Panel (PRP) PRP members Christina Back (San Diego) Janos Kirz (LBNL) Magid Chergui (ETH Lausanne) Dwayne Miller (Toronto) Lew Cocke (Kansas) Juerg Osterwalder (University of Zuerich) Gianluca Gregori (Cambridge, UK) Metin Tolan (University of Dortmund) Chi-Chang Kao (BNL) Kyoshi Ueda (Sendai) Steve Kevan (Oregon) Edgar Weckert (DESY) Two representatives of LCLS management without voting rights: Jerry Hastings Jochen Schneider
LCLS User Program: Important dates • First proposal round close 9/1/2008 (AMO only) • 2nd proposal round close 5/15/2009 (AMO, SXR) • 3rd proposal round close ~10/1/2009 (AMO, SXR, XPP)
LCLS User Program: First experiments • First proposal round: 28 proposals from 16 countries (>200 scientists) • PRP met in December, gave highest rank to ~10 proposals • Most highly-ranked proposals will study effects of intense X-ray pulses on atoms or simple atomic clusters • Some highly-ranked proposals will study diffraction imaging of molecules or clusters
Summary • XFD is a new department at SLAC, will run LCLS X-ray experimental facilities • Administrative home for LUSI Instrument Scientists • XFD will be the interface between LCLS and the world user community • Responsible for running User program • XFD will nurture creation of LCLS instruments, then manage them • Close ties with LCLS Construction and LUSI projects • Goal: safe, efficient operation promoting the best science