Conduct of LCLS Accelerator Operations. John Seeman Assistant Director LCLS Directorate Head of the Accelerator Systems Division LCLS Directorate. Topics. Accelerator System Division Maintenance management Down time planning Overall schedule Scheduling beam time
E N D
Conduct ofLCLS Accelerator Operations John Seeman Assistant Director LCLS Directorate Head of the Accelerator Systems Division LCLS Directorate
Topics • Accelerator System Division • Maintenance management • Down time planning • Overall schedule • Scheduling beam time • Delivered beam specification
Accelerator Systems Division (ASD) • ASD has operated accelerators at SLAC for well over 30 years. The accelerators are: • Linac (50 GeV) • PEP-I • SPEAR-I and II • SLC • PEP-II • FFTB • LCLS Injection and Linac • Programs, training, and documentation in place to carry out the programs carefully, safely, and with full technical rigor. • The staff is trained to carry out these programs, holding all accelerators to the same standards. • Formal procedures are in place to deal properly with DOE safety standards, Operations Directives, and the Citizen Committees.
ASD Documentation • Guiding documents: • SLAC Guidelines of Operations (Under constant updating) • ASD Operations Directives • LCLS/LINAC SAD • LCLS/LINAC ASE • Accelerator Safety Assessment Documents • ES&H documentation • Un-reviewed Safety Items (USI) handled by Guidelines of Operations and LCLS SAD • ASD Operational documents
USIs • LCLS SAD: • Safety issues that are not covered in the above documentation, and for which a safety analysis has not been performed, could arise. Such an issue would constitute an Unreviewed Safety Issue under DOE Order 420.2B Section 4c. Activities that involve unreviewed safety issues must not be performed if significant safety consequences could result from either an accident or a malfunction of equipment that is important to safety. Such activitites would be formally reviewed and be subject to the approval of the appropriate safety officers and citizen safety committees, as required by SLAC Guidelines for Operations. Activities involving identified unreviewed safety issues must not commence before DOE has provided written approval. • A Working Group has been formed as follow up to the DOE ISMS Effectiveness Review in August 2008 with the aim of improving USI definition at SLAC with inputs from other laboratories programs with the target of Spring 2009.
Operations Authorization • Authorization of operating the Linac Related Accelerators at SLAC follow the organization of the SLAC laboratory: • SLAC DOE Site Office • Laboratory Director • Deputy Directors for LCLS • Head of the Accelerator Systems Division • Head of the Operation Group • Engineering Operator In Charge (EOIC) in the Control Room
ASD Staff • Admin: 4 • Safety office: 1 • Physicists: 9 • Mechanical engineers: 3 • Operations and reliability: 2 • Operators: 23 • Area managers: 7 • Technicians: 3 • Total = 52
Linac Operating Modes in FY2009 • LCLS beam: • 4 to 14 GeV e- beam to 120 Hz to 1 x 1010 • Linac capabilities (if needed): • e- to 49 GeV at 120 Hz at 2 x 1010 • e+ to 49 GeV at 120 Hz at 2 x 1010
Control Room Staffing • Program Deputy • Duty rotates among Accelerator Division physicists. • Oversees program for 3 or 4 day period. • Not always present in the control room. • Operations Engineer • 1 EOIC per shift (from a group of 7), on rotating 7-week cycle. • Responsible for safely carrying out the scheduled program. • Exempt position; directs the Accelerator Systems Operators. • Must be present if accelerator is capable of producing beam. • All have experience as accelerator systems operators. • Accelerator Systems Operators Typically 3 operators per shift on rotating 5-week cycle:
Operator Safety Procedures • Operators are trained to carry out certain well-defined tasks, following formally controlled procedures. • Examples: • Interlock Checklists • Search Procedures • Entry and Exit Procedures • Safety Inspection Checklists • Safety procedures: • undergo a formal review and approval process. • are updated as conditions change. • are available on the AD Documentation web site, although the signed originals are preserved in paper form • Completed checklists and log books are archived.
Planning with Accelerator Users and Maintenance Staff • 8:00 Meeting every day, seven days a week, in MCC conference room. • Operations report by EOIC, including run time statistics, progress in carrying out scheduled program, descriptions of problems, etc. • Reports by representatives of major experimental user groups. • Attended by PPA, Accel Div, and Operations management reps, Program Deputy, System Physicists, Area Managers, and representatives of user groups and major technical support departments; typical attendance: 45 persons. • 8:15 Maintenance Meeting, five days each week. • Run by Accelerator Operations Department maintenance managers. • Attended by supervisors of all maintenance groups, Area Managers, and interested physicists and engineers. • Attendance: typically 45 persons. • Accelerator Plans Meeting, weekly. • Review of operational progress, problems, and plans. • Attended by Accel Systems Div and Dept Heads, Program Coordinators, Accelerator Section Heads and ADSO.
Accelerator Maintenance • Planned Maintenance Days • Whenever possible, identified maintenance, repair, and installation jobs are pre-planned. • Coordination • Daily 8:15am meeting. • Coordinated by Operations Maintenance Office. • Area Managers are advocates for their areas. • Standby Maintenance List (SML) • Jobs that are planned and can be launched on short notice. • Provides options for EOIC to take advantage of unscheduled interruptions. • ARTEMIS/CATER Electronic Database records items.
ARTEMIS/CATER • ARTEMIS (Accelerator Remedy Trouble Entry and Maintenance Information System) is an Oracle database with a Remedy interface, accessible over the internet by everyone involved with SLAC accelerator maintenance. • Operators report problems as they occur by making entries in ARTEMIS. • Repair work is launched immediately if the problem is inhibiting the scheduled accelerator program. • Jobs are tracked using ARTEMIS until they are finally closed. • ARTEMIS entries since Jan 1989: ~84000. • ARTEMIS entries in one year (2006): • 3166 new problems (8.7 per day). • 3296 problems closed (9.0 per day).
Long Down Time Planning • Long Down Times usually occur once each year and typically last two to three months. • Area Managers collect job requests from system physicists, project engineers, maintenance groups, and the ARTEMIS database. • A comprehensive schedule is prepared, updated, and reviewed at weekly meetings, starting about four months before the down time. • This schedule lists each job with an assigned shop, and lists the Project or Group Manager, Responsible Task Person, and Area Manager. • Schedule specifies time and duration of each job (with 1 day time resolution), and number of persons required. • Schedule specifies authorizations required (WAF, RSWCF, EWP, etc.). • Detailed (shift by shift) schedule of pre-run testing, safety certifications, and turn-on activities is prepared by the Operations Dept and revised as needed on a real-time basis.
Goal for what typical LCLS operations will look like in two years.
LCLS Installation and Commissioning Time-Line InstallUndulators First Light in FEH PPS Cert. LTU/Dump LTU/Und Install X-Rays in NEH First Light in FEE CD-4 (7/31/2010) FEE/NEH Install FEH Hutch BO PEP-II run ends now J F M A M J J A S O N D J F M A M J J A S O N D J F M A M J J D M D A 2008 2009 2010 Down Down? PPS LTU/Und Comm. NEH Ops & Commissioning Linac/BC2 Commissioning Re-establish e- to SL2 FEL/FEE Commissioning Nov. 3, 2008
X-ray User Performance Drivers for ASD • Reliable operation with high uptime (>95%). • Steady beam parameters when operating. • Rapid but reasonable change of beam parameters when needed by the user. • Maintain alternate user programs when expected user program changes.
Proposed Initial Beam Parametersfor Users J. Galayda
Conclusions • Linac operations are managed by the Accelerator Systems Division under the LCLS Directorate. • Documented policies and procedures exit for all safety-related activities. • Maintenance and installation work is accomplished through a matrix organization, drawing on engineers, technicians, and ES&H and shop services from the ETS Directorate. • We have developed organizational structures, software tools, and documentation that enable us to manage an ambitious accelerator-based science program safely and effectively. • A beam-time scheduling mechanism is being developed to resolve operational beam parameter specifications and changes. • We are ready to operate the LCLS LTU, Undulator, and e- Beam Dump.