An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Overview of VTX Strip Group Activities Abhay Deshpande SUNY-SB For Si Strip Group Si VTX Strip Overview

  2. Active Sub-Groups R&D Ongoing • Junji/Atsushi et al. RIKEN • Vince et al. ORNL • Doug/Martin et al. UNM • Kieran/Junkichi et al. BNL/SBU Testing Facilities Getting Ready Si VTX Strip Overview

  3. A.D. & J.T. February04 1 day meeting RIKEN-ORNL Activities • Stripixel sensor development • The 1st prototype fabricated and tested • Expected position resolutions. • S/N and charge sharing property is needed to be improved. • The 2nd prototype fabricated • Finer stripixel structure. • Charge sharing property is expected to be improved. • S/N will be tested with SVX4 by April 2004. • Test production in SINTEF and Hamamatsu under development. • Sensor + SVX4 chip (+AC coupling) test by Apr. 2004. • SVX4 readout board development done by the end of Feb. • ROC (w/ SVX4s) prototype by Oct. 2004. • Sensor + ROC tests by the end of 2004. • Ladder test by the middle of 2005. Si VTX Strip Overview

  4. Status of Test Wafers from CNTF and HMMTS • CNTF wafers (17) arrived at RIKEN last week • To be sent to BNL and UNM for testing • 1 at RIKEN, 8 at BNL/SBU and 8 at UNM • Presently to confirming adequate storage capacity at UNM and BNL (see Junji’s slides) • HMMTS wafers expected by the end of September 2004 • To be sent out for testing to BNL and UNM • Both are on schedule Si VTX Strip Overview

  5. UNM Ready End of September’04 • Probe card and testing facility (probe station) is ready to start doing measurements as soon as they get: • Pico-ammeter, voltmeter etc. etc. etc. • Atsushi will send them to UNM from RIKEN in the coming week • Likely that UNM ready and will start doing test measurements by End of September 2004 Si VTX Strip Overview

  6. BNL/SBU not quite ready, but.. Will be Mid-End October’04 • Kieran + Junkichi are testing setup in the Instrumentation lab with the semi-automatic probe station (details in Junkichi’s talk) • Comparison of manual vs. semi-automatic probe station on wafers with Cone design (spiral design for future) • That facility is planned to move to RBRC/205 lab for about 1 year or so (until SBU lab becomes available) for us to do the test production wafer testing. • Plan to get the BNL/RBRC facility ready by Mid-End of October (~2-3 week delayed) • Details and reasons follow…. Si VTX Strip Overview

  7. The plan A --> B • Appx. 1/3 of RBRC 205 lab to converted in to a clean room • Kieran, Junkichi, Yuji, Rich Hutter (SBU), Atsushi & Abhay made initial plans • Cleanliness needed, needed asked for estimates for cost of emptying, cleaning 2-205 and setting up clean room • BNL: union estimate came 1.5 months late and WAY beyond our limits (time wasted!) • Plan B is in progress and will be ready in about 5-6 weeks (from now) Si VTX Strip Overview

  8. The plan B…(cont) • To order from Clean Air Products Series 577 vertical flow soft-wall modular clean room • 12 ft x 12 ft x 8.6 ft • Class 100 • Internal filters, lighting etc. etc. • Delivery 2 weeks, Cost about $14.0k • Ordered the cleaning of the ceiling in 2-205 will take 1 day, order pending for 4-5 weeks. • Safer solution with cheaper option of the clean room • We should be ready to go by October (mid-end) 2004 Si VTX Strip Overview

  9. SBU plans on track: • SBU-HEP group getting ready for their tests • We will contribute and learn • Si Lab with the probe station for PHENIX by Spring 05 as expected • Movement on finding a Bonding Machine • Rich & Abhay: K&S 8060 (identical to RIKEN’s new purchase) got the initial quote • Supporting letter from PHENIX vtx group --> PHENIX --> would be requested soon (this or next week) • AD will approach funding sources local, details to be finalized as soon as PHENIX VTX group makes their statement clear: that we would want it. • In future to be included along with the Semi-Automatic probe station as a complete Si lab facility at SBU dedicated to PHENIX and D0 Si VTX Strip Overview