ECS status and PLANS Xavier Vilasis-Cardona Calo Commissioning Meeting - Xvc
Outline • Schedule is tight and there is a lot of work to do • Achievements • Current issues • Plans Calo Commissioning Meeting - Xvc
Schedule is tight • There is a lot of work to do • Aim at a working detector • ECS to be ready to check there are no HW errors • Refine later • Commissioning weeks as milestones • 4 - 8 February • 3 - 7 March • 31 March - 4 April • 5 - 9 May Calo Commissioning Meeting - Xvc
Achievements • C-Side • HCAL DAQ – HV installed and working • ECAL DAQ – HV installed and working with some issues (see next transparency) • PRS installed • A-Side • HV projects are installed • LEDTSB boards are installed • DCS • Rack Control Project • Calo Power Supply projects • Temperature Monitoring of VFE (PS) Calo Commissioning Meeting - Xvc
Issues • CROC configuration and reset • LEDTSB – CROC • PRS-SPD • PRS project • Massive configuration problems • LED system status ? • TELL1 component problems • Should be fixed • Power Supplies • Check Alarm Action matrix • Delay times and MVPS disconnection Calo Commissioning Meeting - Xvc
Other • Integration of VFE temperature Monitoring • In the FSM • PS and SPD • Collect temperature readings in RACKs • Cooling plant ECS • New Framework components soon available Calo Commissioning Meeting - Xvc
Main Goals Calo Commissioning Meeting - Xvc
Moving to Linux • Efficiency reasons • Test PC available cadaqhv01 • Test main elements • Priority is on a working detector • Only SPECS DAQ PCs • Software Compatibility • PVSS should be OK • CAT base should be OK but needs to be checked • CAT developments • Other ? • Groups check their software on the test PC Calo Commissioning Meeting - Xvc
4FEB – Goals and Tasks I Calo Commissioning Meeting - Xvc
4FEB – Goals and Tasks II - PRS Calo Commissioning Meeting - Xvc
Move to Linux • Lower Priority Calo Commissioning Meeting - Xvc
03MAR plans • Finish any pending on the C-side • Install missing DAQ parts • Install CAT server on PVSS • If possible – evaluate the migration to linux • Test and integrate Calo Commissioning Meeting - Xvc