Equipment Condition, Liability Assessment

Equipment Condition, Liability Assessment. DISCUSSION TOPICS. Equipment Condition Liability Assessment Long – term Planning & Equipment Recommendations Facility Health Report Summary Questions . EQUIPMENT CONDITION.

Download Presentation

Equipment Condition, Liability Assessment

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Equipment Condition, Liability Assessment

  2. DISCUSSION TOPICS • Equipment Condition • Liability Assessment • Long – term Planning & Equipment Recommendations • Facility Health Report • Summary • Questions

  3. EQUIPMENT CONDITION Develop Strategy for Determining Equipment Condition • Focus on Critical Equipment Examples: Turbines, Boilers, Critical Piping Systems, Feedwater Heaters, Condensers, Cooling Towers, Boiler Feedwater Pumps, Electrical Transformers, Precipitators, Circulating Water Pumps • Beneficial to Evaluate Equipment Condition on a Fleet-wide Basis for Consistency of Evaluation • Equipment Condition Evaluation to Consider Numerous Factors Examples: Age, Design, Performance, Operation & Maintenance History, Heat Rate Impact, Expected Life

  4. LIABILITY ASSESSMENT Conduct Liability Assessment Based on Equipment Condition Evaluation • Create Long-term (10+ Years) Equipment Recommendations for Critical Equipment • Recommendations include Predictive Maintenance Programs, Preventative Maintenance Programs, Specific Repair Program or possible Equipment Replacement • Critical Equipment Condition Liability Assessment Recommendations evaluated by respective Plant and integrated into their Long-term Planning & Budgeting

  5. LIABILITY ASSESSMENT

  6. LIABILITY ASSESSMENT

  7. FACILITY HEALTH REPORT • Facility Health Report (FHR) provides a Comprehensive Overview for all AEP Coal-fired Units for Critical Equipment Liabilities and Recommendations for Liability Remedy • Identifies Current and Projected Equipment Condition, Degree of Liability and related Unit Outage Probability over a 10+ Year Timeframe

  8. FACILITY HEALTH REPORT (…continued) • Liability Remedy Projection includes and considers Major Projects and Scheduled Unit Outages • Developed in Spreadsheet and segregated by Critical Systems and Equipment • Equipment Condition is Assigned a Liability Rating using Three (3) Colors (Red, Yellow or Green). Major Planned Unit Outage Years are also identified as an Orange Color • Color Definitions: Red – High Outage Probability, Yellow – Moderate Outage Probability and Green – Low Outage Probability

  9. FACILITY HEALTH REPORT (…continued) • Information Developed Collectively by Corporate Engineering Equipment Groups, Regional Engineering and Plants • Liability Remedy Projection includes and considers Major Projects and Scheduled Unit Outages • Developed in Spreadsheet and segregated by Critical Systems and Equipment

  10. FACILITY HEALTH REPORT • Spreadsheet on Generating Unit basis:Example 600 Mw Super-critical Coal-fired Unit)

  11. FACILITY HEALTH REPORT

  12. FACILITY HEALTH REPORT (…continued) • Intended to be Useful Reference Guide for Respective plant to prepare Long-term Budget Plan and Useful in Defining Unit Outage Duration to complete Major Projects • Additionally, intended to be Useful to Senior Management when considering Project Improvement Proposals as well as Long-term Budget and Planning

  13. SUMMARY • Equipment Condition • Liability Assessment (including Long – term Planning & Equipment Recommendations) • Facility Health Report • Questions ??

  14. CONCLUSION Thank You! Muskingum River Plant Unit 5