An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. COLONEL Jose Aguilar District Commander Portland District 2 October, 2014 PNWA Conference Update

  2. Projects • Mouth of the Columbia (MCR) Jetties • Columbia River Status • Coastal Dredging • Navigation Structures • 2017 Navigation Lock Work at The Dalles

  3. Mouth of the Columbia (MCR) Jetties

  4. North Jetty - construction

  5. South Jetty – Dune Stabilization • FY13 O&M Funding • Prevents further dune erosion and Pacific Ocean connecting to Trestle Bay • Completed 30 October 2013 • Dynamic cobblestone revetment: over 35,000 CY of stone placed

  6. North Jetty Lagoon Fill and Critical Repairs (O&M) • FY14 & Proposed FY 15 O&M funds: • North Jetty Lagoon Fill: Completion June 2015 • North Jetty Critical Repairs: Completion September 2016 Critical Repairs Stabilization Areas Oct. 2012

  7. MCR Jetty Major Rehabilitation FY14 “New Construction” start for Major Rehab Project $257M project includes repairs to all 3 jetties $1M received in FY14 to start Jetty A repairs $1M in FY15 PBUD to initiate North Jetty repairs

  8. Coastal Dredging • FY14 “Funding Pot” Allocation & Work: • Yaquina Dredging: • Chetco River- 9,101CY in June • Rogue River- 39,155CY in June • Coquille River- 28,177CY in July and September • Umpqua River- 169,634CY in July and September • Siuslaw River- 74,670CY in June • Yaquina Bay –156,442CY in April through September • Coast Clamshell Contract: • Port Orford – 34,774CY in July • Charleston – 40,630 CY in July • Yaquina Bay – 238,245 CY in August • State Funded: • Rogue River- 15,000CY in July • Winchester Bay- 26,302CY in August • USCG Funded – Rogue River SARDET 5,766Cy in July

  9. Oregon MOA for Low-Use Harbor Maintenance • MOA signed on August 28, 2013 • Up to $5 million a year for 5 years • State funds leverage Appropriations and USCG funds • FY14 Accomplishments • Over 360,000 cubic yards dredged in a clamshell contract (Rogue, Port Orford, Charleston, Winchester Bay, and Yaquina Bay) • 641,633 cubic yards dredged with the dredge Yaquina (Chetco, Rogue, Coquille, Umpqua, Siuslaw, Yaquina Bay and Skipanon) • Estimated 45,000 cubic yards to be dredged with a pipeline contract (Depoe Bay and Garibaldi Boat Basin) HME Yaquina HME

  10. Columbia River Channel Status Astoria Longview Kalama Portland & Vancouver 03 October 2014

  11. Coastal Structures District Portfolio: 44 Jetty and Breakwater Structures Over 230 Pile Dike Structures Condition: 14 have a structural condition rating of D or lower (D = An extensive portion of the structure has deteriorated to a condition that repairs are required) Need to protect the Federal investment and maintain function

  12. Pile DikesPassive Channel Maintenance • Pile Dikes: decreased dredging requirements and increased habitat creation • Focusing Attention – 2013 OCA review of 4 most critical near Mouth of the Columbia River • Poor condition and expensive rehab requirements

  13. The Dalles 2017 Extended Lock OutagePlan • Scope of work limited to critical items • Improve life safety concerns • Improve lock reliability • 2017 Scope: • Replace downstream gate gudgeon hardware • Replace upstream gate • Upgrade controls • Current Status (Fall 2014) • Completing Design Reports • Initiating Plans & Specifications

  14. COLONEL Jose Aguilar District Commander Portland District 2 October, 2014 PNWA Conference Update