Agenda Review of Goals and Action Items from last time (O. Lupie)--5 min WFC3 and COS Instrument Development Status (G. Blue)--10 min WFC3 FSW Status and Schedule (G. Blue)--20 min WFC3 MOU & Ground System Development Status (O. Lupie & W. Baggett)--15 min Consolidated WFC3 Schedule (B. Rehm) --20 min Break 20 minutes COS FSW Status and Schedule (G. Blue) --20 min COS MOU & Ground System Development Status (C. Keyes & Wayne Baggett)--15 min WFC3 ICAL Status and Schedule (D. Fineberg) – 15 minutes Transition Planning (Grant Blue) --15 min Discussion & Lunch 1
Revisit Goals: Schedule and schedule drivers review. Provide forum for discussion. Linkages and Interface clarification. Improve Information flow. Next splinter meeting planning. Talk directly with team counterparts. Establish perspective – how each piece fits into whole. Renew commitment for timely information exchange. 2
Revisit Goals: Schedule and schedule drivers review. Provide forum for discussion. Linkages and Interface clarification. Improve Information flow. Next splinter meeting planning. Talk directly with team counterparts. Establish perspective – how each piece fits into whole. Renew commitment for timely information exchange. 3
Action Items from March 27th Splinter • Plan for WFC3 and COS splinter at Ball Summer 2001 CLOSED • Initiate Tracking of WFC3 FSW and Ground System Development CLOSED (Brian, Grant, Olivia, Wayne) [tracking and dependencies now included in Thai’s development schedule] • Initiate Tracking of COS FSW and Ground System Development OPEN (unassigned) • WFC3 and COS need updated schedules for the delivery of test data suites CLOSED (G. Blue) • Investigate merging of stimulus keywords with science data keywords – CLOSED – Plan OK (ICAL) • WFC3 MOU updated to reflect new schedules and March 27 splinter CLOSED - O. Lupie • WFC3 MOU to address real-time TV support and connection to STScI CLOSED – O. Lupie • Investigate COS and WFC3 Transition Plan Requirements IN WORK B. Friedman to present @ splinter. • Scrub DRD Delivery Dates CLOSED (G. Blue) • Get COS and WFC3 Timing Tests on Grant’s Schedule – Grant to work with Tom Wheeler INWORK • Address Fire-Wall issues for remote access to COS and WFC3 Telemetry CLOSED • Closed Actions from previous splinters: • Have SISEs participate in WOWG and COWG CLOSED (R. Henry, STScI) • Address details of Tom Wheelers’ support of ACS, COS< and WFC3 timing tests CLOSED (C. Blades, STScI) • Link from GSFC Private WFC3 pages to GSFC FSW/OPS site CLOSED (Ball) • Provide Instructions to Ball and GSFC for accessing the STScI OPR system CLOSED (W. Baggett, STScI) • DM-05 to be placed on Web CLOSED (M. Draugelis, Ball)
STScI - WFC3 Achievements since last time: Ops Telecon support: New error message review process is working well. Ground System: functionality available for basic UVIS Accum, IR Multi- Accum, Lamp Operation, Darks/Biases (Mike Robinson, Wayne Baggett). WFC3 Pipeline and Archive CDR – held on 10/16/2001 (Howard Bushouse) Delivery of AV-03 (Calibration Requirements) – October, 2001. TV Science Calibration report submission (Neill Reid, Frank Bartko). TV software support information gathering meeting – 08/2001. Recommendation for TV Data Handling System submission – 10/2001. Front-end Pipeline ICAL 5
STScI WFC3 Memorandum of Understanding: • Driven by Thermal Vac. • Documents interfaces/dependencies Ball, STScI, GSFC, ICAL. • Now focuses on two categories of STScI support: • Long-Term – OPUS Pipeline processing and long term Hubble Archive Storage. • Time-Critical- Specialized system for quick-look analysis with real-time archive. recent addition 6
Key MOU Items – version 10/15/2001 • 5. Delivery of WFC3 OPS Test Bench Images – March 1, 2002 • Source: Grant Blue, Ball • Recipient: WFC3 Science IPT • Completion of Code and Unit Test Build 3.0 – March 30, 2002Source: Grant Blue, BallRecipient: STScI – ESS (T. Wheeler & FSET ) • 7. Delivery of Images from the Integrated Optical Bench - June 1, 2002. • Source: Grant Blue, Ball • Recipient: WFC3 Science IPT • 8. Delivery of TV-Specific and Optical Stimulus Keywords • Initial version –October 31, 2001, Complete version – May, 2002 • Source: WFC3 ICAL • Recipient: WFC3 Science IPT 7
Key MOU Items – version 10/15/2001 9. Delivery of TV-Specific and Optical Stimulus Keywords Initial version 10/31/2001, Complete version 05/2002. Source: WFC3 ICAL Recipient: WFC3 Science IPT (H. Bushouse, WFC3 Pipeline and Archive) 11. OPUS Staging Disk Implementation – December, 2002 Source: WFC3 ICAL Recipient: STScI OPUS 12. Delivery of Beta Version of OPUS - June 1, 2002 (Final Version October 2002) Source: STScI OPUS Recipient: WFC3 Science IPT and WFC3 ICAL 8
SEPT, 2001 ICAL Development OPUS Keywords DM-06 – snapshot telemetry and internal header data OS, TV Keywords DEC, 2001 SMS timing trials Test Bench “Early” Images MAR, 2002 Test Bench Image Suite Science SMS Testing Begins Build 3 C/U Complete Integrated Optical Bench Images Beta OPUS JUN, 2002 ICAL Proto Testing SEPT, 2002 Final OPUS KEY Front End Archive Pipeline/Archive DEC, 2002 TV Cal Support TV Readiness Test TV Thermal VAC Version October 15, 2001 MAR, 2003 Complete SMS Testing for SMGT 9 SMGT JUN, 2003
STScI Ground System Development Linkages: 1yr between Build 3 C/U & SMGT 2mo between Full Suite Ops Bench Images and Beta OPUS 4mo between Beta OPUS and Final OPUS Deliveries Final Opus ready for TV ReadinessTest – Dec, 2002 2mo from TV ReadinessTest to start of TV. 10
SEPT, 2001 ICAL Development OPUS Keywords DM-06 OS, TV Keywords DEC, 2001 1-2 month slip SMS timing trials MAR, 2002 Test Bench “Early” Images Test Bench Image Suite Build 3 C/U Complete Start SMS Testing Integrated Optical Bench Images JUN, 2002 ICAL limited to test of real-time system ICAL Proto Testing BETA OPUS SEPT, 2002 KEY Minimal testing of Final OPUS; no ICAL tests Front End Pipeline/Archive Final OPUS DEC, 2002 TV Cal Support TV Readiness Test TV Archive not ready for TV Readiness. No test-time Archive Schedule-Incompatibility Thermal VAC @ GSFC MAR, 2003 Version November 1, 2001 Incomplete SMS testing. Risk final Phase development effort. SMGT JUN, 2003 Complete SMS Testing 11