An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Gamma-ray Large Area Space Telescope Performance & Safety AssuranceCost to Complete GLAST Large Area Telescope: Darren Marsh Stanford Linear Accelerator Center Performance & Safety Assurance Manager Marsh@slac.stanford.edu 650-926-4577

  2. Cost Estimate • 10/31/04 Baseline Cost Estimate • $2,935K • Performance Assurance activities performed on a level of effort basis • Cost estimate covered quality engineering and inspection staff through 1/31/05 • Lien identified for $552K for staff funding through 7/14/05 • 11/17/04 Rebaseline Plan • $3,894K ($959K Delta) • Change in LAT delivery date to NRL 9/28/05 • Schedule delays of subsystem hardware deliveries • Quality problems associated with critical components and assemblies

  3. Change Detail • Quality Engineering (+$594K) • Addition of Software Quality Engineer (.5 FTE) through end of 9/28/05 • Assigned QE to address MCM workmanship issues and support Tracker Engineering staff on quality issues • Source inspection (+$122K) • Extension of Tracker MCM and DAQ box assembly source inspection personnel to reflect completion of work • Dedicated individual to Tracker flex cable fabrication activities due to supplier problems • Quality Inspectors (+159K) • Internal rework procedure development and inspections • Continued inspections of Tracker and DAQ parts • DAQ harness inspection at vendor facility • Management, calibration and travel (+$84K)

  4. Increased Cost Summary