Overview of activities • Update of CO2 Sources • Source-Sink matching • One-to-one matching • Transport cost package • Injection cost package • Many-to-many optimisation (Los Alamos National Laboratory collaboration) Aleks Kalinowski MIT Laboratory for Energy and the Environment
Updating the CO2 sources database Aleks Kalinowski MIT Laboratory for Energy and the Environment
Calculating CO2 Transportation Cost Three parts: • Module to calculate pipeline diameter (D) • Module to identify the least-cost path connecting a CO2 source to a given sink (L) • Using national transportation obstacle layers • Economic module to calculate the total and annualized CO2 pipeline transportation cost Aleks Kalinowski MIT Laboratory for Energy and the Environment
Determining the least-cost path • Pipeline construction costs vary considerably • Terrain • Crossings (waterways, railways, highways) • Protected areas • Populated areas • Obstacle grid layers (1x1km) are used to determine the least-cost pipeline route. • Current version: • identify the least-cost path • calculate its length • One-to-one matching Aleks Kalinowski MIT Laboratory for Energy and the Environment
Example of obstacle layers Aleks Kalinowski MIT Laboratory for Energy and the Environment
Obstacle conditions & relative cost factors Aleks Kalinowski MIT Laboratory for Energy and the Environment
Aggregate cost factor map Aleks Kalinowski MIT Laboratory for Energy and the Environment
Least-cost Path Example Matching CO2 Sources to Oil Fields with EOR Potential in Eastern Texas Aleks Kalinowski MIT Laboratory for Energy and the Environment
Land Construction Cost (LCC) 1. MIT correlation LCC = a × D × L Where: a = $33,853 (per inch per mile) D: pipeline diameter (inches) L: pipeline path length (miles) Aleks Kalinowski MIT Laboratory for Energy and the Environment
Land Construction Cost (LCC) 2. CMU correlation LCC = a × Dx × Ly × z Where: z = region weight a = $42,404 x = 1.035 y = 0.853 Aleks Kalinowski MIT Laboratory for Energy and the Environment
MIT-CMU correlations • MIT Correlation: $33,853/in/mile • CMU Correlation: ($/in/mile) For SECARB region: Aleks Kalinowski MIT Laboratory for Energy and the Environment
Pipeline: Calculating Annualized Cost General Equation: Annualized Cost = LCC × Capital Charge Factor + O&M Cost Where: • LCC = land construction cost • Capital Charge Factor: Use 0.15 by default • O&M Cost = $5,000 × Length (miles) (per year) Aleks Kalinowski MIT Laboratory for Energy and the Environment
Tutorial: Transportation Package V1.0 Aleks Kalinowski MIT Laboratory for Energy and the Environment
Current work • Refining transport package • Update obstacle layers • Completing & implementing injection costs package • Many-to-many sources-sinks matching Aleks Kalinowski MIT Laboratory for Energy and the Environment