1 / 25

Mississippi Roadbuilders Association Design-Build Conference February 23, 2004

Design-Build in the Federal-aid Highway Program. Mississippi Roadbuilders Association Design-Build Conference February 23, 2004. Jeffrey W. Kolb, PE Assistant Division Administrator FHWA Mississippi Division Jackson, Mississippi (601) 965-4215 Jeff.Kolb@fhwa.dot.gov.

carl
Download Presentation

Mississippi Roadbuilders Association Design-Build Conference February 23, 2004

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Design-Build in the Federal-aid Highway Program Mississippi Roadbuilders Association Design-Build ConferenceFebruary 23, 2004 Jeffrey W. Kolb, PE Assistant Division Administrator FHWA Mississippi Division Jackson, Mississippi (601) 965-4215 Jeff.Kolb@fhwa.dot.gov

  2. Design-Build Contracting • Overview and Background • Characteristics and criteria • Advantages and Concerns • Conclusion

  3. Historical Background – The Low Bid Concept • Design-Build is not new! It is relatively new to transportation • Prior to mid-1800’s – “The Master Builder Concept” was frequently used. • Mid-1800’s - many States adopt “low bid” requirements to protect taxpayers from extravagance, corruption and other improper practices by public officials. • 1938 Federal Highway Act required competitive bidding • 1968 Federal Highway Act revised Title 23 USC to award construction contracts “ . . . only on the basis of the lowest responsive bid”

  4. Contract Administration“Before 1990” • One Size Fits All • 100% Complete Plans, Specifications, & Engineering • All Qualified Bidders • Award to Lowest Bidder • No Warranties

  5. TRB Task Force A2T51 – Innovative Contracting • Compile information on contracting practices • Assess how current practices affect quality, progress, and cost • Suggest measures for improving contracting practices and promoting quality in construction • December 1991 – TRB Circular #386 – Innovative Contracting Practices

  6. Special Experimental Project No. 14Innovative Contracting • Initiated 2/13/90 • Objective – Evaluate project specific contracting practices which • Maintain product quality • Reduce life cycle cost • Practices proposed for evaluation • Cost-plus-time Bidding (A+B Bidding) • Lane Rental • Warranty Procedures • Design-Build

  7. What is Design-Build? • When a single entity provides both design and construction through a single contract between the owner agency and the entity.

  8. TEA-21 Design-Build LegislationSection 1307 • Required FHWA to develop design-build regulations • New D/B regulations published in 12/10/02 Federal Register • States can now use design-build without HQ approval for “Qualified Projects” • ITS projects > $5 million • Other projects > $50 million • SEP-14 will continue for smaller projects • Flexibility within broad parameters • FHWA must report to Congress on the effectiveness of Design-Build

  9. Section 1307 Report to Congress • an assessment of the effect of design-build contracting on project quality, project cost, and timeliness of project delivery; • recommendations on the appropriate level of design for design-build procurements; • an assessment of the impact of design-build contracting on small businesses; • assessment of the subjectivity used in design-build contracting

  10. FHWA’s Design-Build Experience Under SEP-14 NYCDOT Reno ReTRAC DC TCA Nashville Milwaukee Texas Turnpike Authority

  11. SEP-14 Design-Build Projects December 2002 FHWA SEP-14 data http://www.fhwa.dot.gov/programadmin/contracts/sep14a.htm

  12. Critical Characteristics for Successful Public Sector Design-Build Projects • Well Defined Scope • Shared Understanding of Scope • Owner’s Construction Sophistication • Adequate Owner Staffing • Established Budget • Established Completion Date

  13. Suitability for Design-Build • NEPA and major ROW and utility issues must be clear • Should have a “strong design component” • Reasons for selection should not be: • Obligation of funds • Compensate for inadequate agency resources

  14. Design-Build Selection Procedures • Low Bid • Adjusted Bid • Highest Composite Score • Best Value • Best Value/Fixed Budget

  15. Procurement / Selection Spectrum Price Based Factors Best Value: Subjective, Qualitative and Quantitative Factors Subjective and Qualitative Factors Sole Source Negotiated Source Selection Low First Cost Bidding Bridging Weighted Criteria Two-Step Sealed Bidding Competitive Selection Fixed Budget / Best Design Brooks A/E Selection

  16. Why Owners Choose Design-Build* *University of Colorado/National Science Foundation survey (1=highest rank) 108 respondents, representing 90 owners, 1,683 projects, 83% buildings

  17. Utah’s Interstate 15 Reconstruction • 17 mile, $1.35 Billion, 4.5 year project • Completed on time and on budget • Estimated time savings of 4 years • Road user cost savings roughly estimated in the hundreds of millions

  18. FHWA EFLHD Design-Build in Mississippi • 2 Natchez Trace Parkway design-build projects • Awarded on price (30%) and non-price factors(70%); • The low bid is not necessarily the best-value • Bid cost and completion time • Both projects are currently on-budget and on-schedule • Project NATR 3X5 • $26.4 million – Hill Brothers (Falker, MS) • 2 other proposers – T. L. Wallace, Eutaw Construction • Low bid also best technical proposal

  19. FHWA EFLHD Design-Build in Mississippi Natchez Trace Parkway Project NATR 3P13 • $6.9 million – T.L. Wallace (Columbia, MS) • 2 other proposers – Angelo Iafrate, WG Yates & Sons • Low bid also best technical proposal

  20. Reported Advantages of Design-Build • Single Point of Responsibility • Quality/Innovation • Potential Time or Cost Savings • Improved Risk Management • Earlier Knowledge of Firm Costs • Lower Incidence of Claims • Reduced Project Administration

  21. Potential Concerns with Design-Build • Contracting Agencies • Fear of loss of control, significant change in business relationships • Construction Contractors • Increased risk, potential design liability, warranty/operational requirements, subjective selection process, impact on smaller contractors • Engineering Consultants • Changing business relationship with owners, more risk, increased emphasis on schedule, building trust

  22. Potential Concerns with Design-Build • Requires significantly more up-front effort and expertise by owner • Requires streamlined (flexible and responsive) “acceptance” organization by owner for oversight of Design and Construction activities

  23. General Lessons Learned To Date • Pick the right project • The scope of work MUST be clear!! • A two-step selection process is recommended • Prequalification to no more than 5 firms • Selection based on price and technical proposals

  24. 1980 Project Delivery Techniques Design-bid-build Current Project Delivery Techniques Design-Bid-Build Design-build DB, DBO, DBOM, FDBO, DBW, Concessions, etc. Other innovative integrated service contracts (SEP-14) Construction Manager at Risk, Performance contracts, best-value, etc. In conclusion . . . . Design-build - It’s another tool in the tool box!

  25. Additional Resources for Design-Build Contracting • FHWA HIPA-30 web page • http://www.fhwa.dot.gov/programadmin/contracts/d_build.htm • Utah State University web page • http://www.ic.usu.edu/ • AASHTO Design-Build Task Force • Current Practices Report • http://www.transportation.org/committee/design/tf_designbuild.html

More Related