Solar PV In Lebanon Is it Finally feasible? Facts and Hopes

Solar PV In Lebanon Is it Finally feasible? Facts and Hopes. By: Ramzi AbouSaid President of the Lebanese Energy Society . The domain . In a country exhausted with utility blackouts exceeding 30% of daily hours with little hopes for a near future change for this sad reality

carlo
Download Presentation

Solar PV In Lebanon Is it Finally feasible? Facts and Hopes

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Solar PV In LebanonIs it Finally feasible? Facts and Hopes Solar PV In Lebanon/ Ecorient 2012 By: Ramzi AbouSaid President of the Lebanese Energy Society

  2. The domain Solar PV In Lebanon/ Ecorient 2012 In a country exhausted with utility blackouts exceeding 30% of daily hours with little hopes for a near future change for this sad reality In a country where electrical energy bill contributes almost 6% of GDP. In a country where the public utility budgetary heavily falls under devastating deficit of over $2B/annum In a supposedly “touristic” country where environment and clean means of generating energy is another essential virtue. In a county where diesel backup generator is one other default household appliance. In a country blesses with long solar hours of over 2000 h/year With the overwhelming decrease in PV prices along with the acceptable local Financial facility and Grants. SOLAR PV is no more a Luxury, it is simply Successful Feasible Alternative

  3. International PV price graph Solar PV In Lebanon/ Ecorient 2012

  4. System Price graph Solar PV In Lebanon/ Ecorient 2012

  5. Optimum System Configuration and Costs • Off grid • Cost about $10K/Kwp • Best used in very remote places( rarely found in Lebanon) • Sized against the worst months of the year • Examples: Remote areas such as resorts, Communications BTS, protected area • On-Grid • Cost about $3K/Kwp and no batteries are needed • Best for net metering • There should always be a backup generator running during utility blackouts. • Sizing is made against maximum power generation. • Example: Power plants, Industrial facilities, Micro grids in private compounds, ext. • Interactive (Combination between On and Off-Grid) • Cost about $5K/KWp • Best for Home and small application with limited power requirement • Acts as a good backup system during blackouts • Surplus energy will be injected to the grid when available. • Storage capacity is reduced due to limited Autonomy requirement. • Examples: Households, Schools, offices, etc.. Solar PV In Lebanon/ Ecorient 2012

  6. Interactive System RE Energy Generator - ~ Energy Flow Solar PV In Lebanon/ Ecorient 2012 Net Meter Utility Load Back UP Generator Battery

  7. Local Solar Resource (Lebanon) Average Solar Insolation: 5.4Kwh/sqm/year Average Temperature: lower 20C Average Specific Production (Lebanon): 1450Mwh/Kwp/Year Solar PV In Lebanon/ Ecorient 2012

  8. Solar Energy Cost (Rough Estimate) Cost of Energy = Initial system cost / amount of production over Life time Kwh = cost of Kwp / production(Kwh/Kwp/year) System Life time Cost of Solar KWh from on-grid solar= $3000 / 1450 /25= about $0.085 While Current Cost of KWh from EDL ranges between $0.08-0.12~$0.10!!!!! Solar PV In Lebanon/ Ecorient 2012

  9. Energy Cost (Actually Paid) Actual Energy Cost for consumers working both on EDL and Back up diesel Generator* • 100% Diesel Generator: $0.35-0.5/ KWh • 50% EDL, 50% Diesel Generator: about $0.30/Kwh • 70% EDL, 30% Diesel Generator: about $0.22/Kwh • 100% EDL about $0.10/Kwh * Application specific and may vary due to Diesel price and the amount of blackout periods as well as various load curves. Solar PV In Lebanon/ Ecorient 2012

  10. Pay back Period (Different Scenarios) $0.30/KWh Solar PV In Lebanon/ Ecorient 2012 $0.22/KWh Incentives are Critically important: loans and Grants (NEEREA)

  11. Facility and Grants NEEREA Scheme (10-14years loan, 15% grant) for 25KWp Solar PV System: (Rough Estimate) $0.3/Kwh cost: $0.22/Kwh cost: Solar PV In Lebanon/ Ecorient 2012

  12. Existing Projects There might be a gap for an accurate statistical information about existing project and types integrated locally. A rough estimate would be as follows: • Privately funded project sector: ~ 300Kwp • Externally Funded project (UNDP, USAIS, UNIFIL, GTZ….): ~ 500Kwp • Public Sector: <30KWp Total installed capacity all over Lebanon is disappointedly less than 1MWp all in all Solar PV In Lebanon/ Ecorient 2012

  13. 40Kwp On-Grid (Micro-Grid environment) 3-4Years pay back period against 100% diesel @ $0.75/Kwh Solar PV In Lebanon/ Ecorient 2012

  14. 70Kwp On-Grid (Micro-Grid environment) 3-4Years pay back period against 100% diesel @ $0.75/Kwh Solar PV In Lebanon/ Ecorient 2012

  15. 2Kwp interactive (Back up with Net-metering) 8-10Years pay back period Solar PV In Lebanon/ Ecorient 2012 2Kwp interactive (Back up with Net-metering) 8-10Years pay back period

  16. Solar PV In Lebanon/ Ecorient 2012

  17. Solar PV In Lebanon/ Ecorient 2012

  18. FEED in Tariff (Never Too Early) • Going one step Further with Net Metering and merge the scheme with some “Lebanese customized” FET (Feed in Tarrif) practice: as to have a hybrid N.M-FET system: In such a case only surplus power be sold to EDL at a higher rate above the break even value ($0.22-0.25/KWh exported from net balance). • Average EDL actual cost $0.17-$0.18/Kwh Ex-factory, while the maximum cost for EDL is as high as $0.38 (according to the 2010 MOPE National plan with current diesel price ). Why not buy RE energy at this already existing prices?? • According to the MOPE plan the selling price of Kwh will have to rise to about $0.15/Kwh as of 2014. why not start increasing the RE price portion to encourage implementation.?? • Each KWp installed by the consumer will help increasing the National grid Capacity already in sever deficit. Thus reducing the cost of investment required to increase this Capacity from the government side. Solar PV In Lebanon/ Ecorient 2012

  19. Privet RE Plants (It is the correct time) • With the significant decrease in PV price, the energy produced from a good solar PV plant located in somehow low land cost, may currently achieve a cost of production of about USD$0.10-$0.15! • The Utility is in urgent need of each additional MW to increase local capacity and accepting to buy Energy as high as $0.25 and to produce it with diesel at shocking cost of $0.35/Kwh • If the government is not willing, or the least not capable, to engage in proper investment, then why not open the door for the private sector to conclude this job? All it takes is to accept to buy RE at reasonable price lower than EDL maximum cost but higher than the subsidized rates. Setting a buying rate with long term contracts while setting a Cap for production. BOT is one simple approach!!! Solar PV In Lebanon/ Ecorient 2012

  20. Conclusions and Recommendations • Net Metering is an excellent startup and is a MUST to realize big RE systems, but is certainly not enough!! • Net Metering is more effective in niche sectors such as industrial and commercial applications where energy is needed and cost most. • Currently Net Metering is more Feasible when the actual cost of energy from the consumer side is above $0.2/Kwh. Further steps to push the sector forward: • Additional Financial incentives • More grants proportion to encourage the first few systems. Hopefully Arriving to 30-50% with Special funding with grant for few pilot projects.. • Obligatory codes and attractive incentives should be imposed in the Building law to encourage the use of RE. • Taxation and Facilities especially for industrial and commercial projects. • Additional incentives from EDL especially for big size systems. • Ultimately FIT or Modified FIT schemes should be adopted Solar PV In Lebanon/ Ecorient 2012

  21. Lebanese Solar Energy Society (LSES) 1) To get together associations of professionals, as well as individuals interested in the development of solar energy in all its various aspects. 2) To develop education programs and training sessions regarding the various applications of renewable energies in general and more particularly direct solar energy. 3) To set up gradually "Quality Label" with a view to guarantee the quality of services linked to the design, manufacturing, installation and exploitation of solar energy fields. 4) To encourage development and protection of the manufacturing of solar systems, in order to achieve a good quality of the equipment for the benefit of the users. 5) To inform and lead the public opinion on any matters regarding solar energy for the benefit of the national economy and environment in Lebanon. 6) To take part in scientific activities and to participate in appropriate exhibitions and seminars. 7) To back any initiatives to elaborate laws and to improve the existing ones, with the aim of developing the solar energy market, as well as other renewable energies. In Short: LSES main objectives focus on developing solar energy in all its aspects and gradually guarantee a “Quality Label” linked to the design, manufacturing, installation, exploitation, education programs, training , marketing, awareness , etc.. WWW.LSES-LB.ORG Solar PV In Lebanon/ Ecorient 2012

  22. THANK YOU Contact Info: Ramzi AbouSAID President of Lebanese Energy Society ras@lses-lb.org www.lses-lb.org Solar PV In Lebanon/ Ecorient 2012