Shepherd University WV Route 480 Pedestrian Underpass August 3, 2011
Topics to Be Covered • Plan • Rendering of Underpass • Profile • Plan of Detour • Schedule • Sample Pictures of Other Underpasses • Sample Pictures of Possible Facades • Lighting
Schedule • February 2012 • Begin Utility Relocation: Water, Sewer, Storm Sewer, & Overhead Utilities • March 2012 • Begin Detour Construction • April 2012 • Complete Utility Relocation • Complete Detour Construction • May 2012 • Close Road & Open Detour
Schedule • Mid-July 2012 • Complete Retaining Wall, Underpass Structure & Roadway • Open Rt. 480 to Traffic • August 2012 • Remove Detour at Campus Drive • Connect Campus Drive and Shepherd Grade to Rt.480 • Complete Excavation & Sidewalks on Both Sides of Underpass • Open Underpass for Student Use • September 2012 • Remove Detour & Restore Bavarian Inn Property • October 2012 • Complete Wall Restoration, Cleanup, Seeding & Closeout