An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. 2006 Hurricane Season Preparedness Briefing Gulf Power Company June 5, 2006

  2. Transmission Inspections • All critical lines have been inspected. • The complete system has been inspected aerially twice since January, 2006. • Comprehensive walking/climbing and groundline inspections are underway as part of the 6 year inspection program. • By August will be 80% complete.

  3. Vegetation Management • Transmission: • 230kV ROW vegetation inspections are complete and all hazard tree conditions have been addressed. • 115kV ROW vegetation inspections are 60% complete and crews are currently working on hazard trees. Completion Date: July 31st • 46kV ROW vegetation patrols and hazard tree removals are scheduled. Completion Date: August 31st.

  4. Vegetation Management • Distribution: • 3 phase ROW vegetation trim and removal of hazardous conditions are 85% complete.Completion Date: June 17th • Working well with home owners and land owners.

  5. Sweeps and Backlogged Repairs • Transmission: • All repairs to the system that were caused by Ivan, Dennis and Katrina have been completed. There are no backlogged repairs pending. • Distribution: • Restoration process minimized post storm repairs. • Patrolled main line of all feeders. • Loose down guys • Slack primary • Leaning poles

  6. Summary • Gulf is fully prepared for the 2006 Hurricane Season. • System: Transmission and Distribution • Storm Recovery Plan: • Proven and battle tested. • Improved based on lessons learned. • Support: • S.E.E. Mutual Assistance • Southern Company – Logistics • Southern Company – TERP

  7. QUESTIONS?