An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. mechanised decline developmentM.M.S.(mechanised mucking system) excavator controls & power pack excavator in ‘park’ position under jumbo Bomar Projects (Pty) Ltd.

  2. mechanised decline developmentMMS Forward • Decline development is presently labour intensive • Speed of bringing shafts into operation is critical • Steep declines (15° or more) are slow & problematic Bomar Projects

  3. mechanised decline developmentMMSConcept & design considerations • Capable of operating in the range of 10 and 40° • Have a relatively fast mode of exchanging hoppers/skips • To improve safety • The ability to move with the advancing face under it’s own power • Have the option of conveyor belt utilisation for declines to 15° degrees Bomar Projects

  4. mechanised decline developmentMMSDescription • A self propelled unit that comprises of the following main components: • Hydraulically operated system, designed to move a platform and all the components mounted thereon • Built in facilities for rolling stock • Conveyor, if applicable, for declines of 15° or less • Hopper/skip exchange slave winch • Hydraulic lateral jacks to anchor the platform • Stop blocks for hoppers/skips • Hydraulic excavator • Blast protection chain screen • Up ramp and rail track installation apparatus • Hydraulic portal drill rig for mechanised drilling option or handheld drill machine bay • Safety features for excavator, hopper, drillrig movements • Water tanks & positive displacement pumps to dispose of water delivered by the face pump/s Bomar Projects

  5. mechanised decline developmentMMSGeneral Arrangement (with skips) Bomar Projects Rail magazine Skip in ‘park’ position Portal jumbo Skip being loaded Loader Hydraulic slide floor Blast screen For system with conveyor belt see video available on request

  6. mechanised decline developmentMMSSpecification • Max component size: 9.1m x 0.5m x 1.45m • Heaviest component: 5000kg • Installed power: 102kW (for drillrig add 40kW to 110kW, for pumps add 22kW to 75kW) • Hydraulics: 2 circuits/ 900 lt capacity. Pump pressure/flow compensated, piston • Operating pressure: 150 - 210 bar • Voltage: 525 - can be designed to suit • Excavator traverse speed: 1m per second • Speed of slide floor cylinders: 0.5m per minute • Excavator slew: Max 5 rpm, 45° + 45° • Effective mucking capacity per hour: (0.4m3 bucket - 20m3 or 32t); (0.5m3 bucket - 25m3 or 40t); (0.6m3 bucket - 30m3 or 49t) • Face shovel - bottom discharge • Totally enclosed sliding floor of 3 main section. Width & length to suit specific requirements. The width of the excavation will determine the set up of mucking i.e. conveyor or hopper for inclination of 15° or less; hopper or skip for greater inclinations. Hydraulic jacks incorporated in the main sections and are applied to the sidewalls when expanding the slide floor to follow face advance

  7. mechanised decline developmentMMSAncillary equipment • A submersible face pump to supply the permanent Tank/pump/s on the MMS via permanent floor pipes • Slave winch to lower the empty skip to excavator • Hydraulic lifting apparatus to shift skip from main line to wait line • Rail magazine situated at the rear of the sliding floor for easy and rapid installation of permanent rails • Slewing hydraulic crane at rear for material handling • Bays provided for tools, hoses, drilling consumables and spares.

  8. mechanised decline developmentMMS Safety • Excavator operator canopy • No lashing personnel required in front • Lock bell system for hopper/skip arrival/departure • Hopper/skip stop blocks, rails and switches • Excavator carriage - power off/out, brakes on • Advantages • Advance rates 100% faster in applications where the inclination is in excess of 15 degrees with capital and operating costs relatively lower than other methods now in use • The ability of the MMS to allow for the • installation of rail tracks and/or • conveyor concurrently with the sinking • to meet the permanent equipping • requirements of the client Bomar Projects (Pty) Ltd E.MAIL: info@bomar.co.za TEL: +27 (11) 234 3349 FAX: +27 (11) 234 3365