CPP for SEZ. MIHAN, Nagpur - 09.Apr.2005 Banmali Agrawala. CPP for SEZ. SEZ 1300 Hectares. Manufacturing. Health City 60 Acres. IT Park 200 Acres. Total Power Demand 100MW. Textile Garment Pharma Etc. CPP for SEZ. Techno-commercial Perspective
E N D
CPP for SEZ MIHAN, Nagpur - 09.Apr.2005 Banmali Agrawala Banmali Agrawala/09-Apr-2005
CPP for SEZ SEZ 1300 Hectares Manufacturing Health City 60 Acres IT Park 200 Acres Total Power Demand 100MW • Textile • Garment • Pharma • Etc.
CPP for SEZ • Techno-commercial Perspective • Regulatory / Business Perspective • Options
CPP for SEZ • Power Demand Cogen Need • Health City Peaking/ Steam • Intermediate Air Conditioning • Hot Water • IT Park Peaking Air Conditioning • Industry Depends on type Depends on type • Textile • Garment • Pharma • Jewellery, etc • PEAKING / INTERMEDIATE LOAD
CPP for SEZ Techno-Commercial Comparisons
CPP for SEZ • Other factors to be considered • Rate of growth of SEZ (sizing of plant) • Power Plant near airport • - Stack • - environmental etc • c) Water Availability (Coal based) • (1,500 tons/day – air condenser • (11,000 ton/day – w/o condenser) • Ash disposal : - 500 tons/day • - 80 – 100 acres land
CPP for SEZ • Commercial Factors • Operating plf • Sale of excess power during non-peak hours • c) Pricing of sale of excess power • Ownership of the Power Plant
CPP for SEZ • Business Factor • Who will take the risk of growth of SEZ? • - Power Developer – No • - SEZ Developer – Maybe • - Government Agency ?
CPP for SEZ • Options • - MSEB Power • - NTPC Power • - CPP in SEZ with sale of excess power to MSEB • - Right kind of CPP in phases • - 3 CPPs for each activity?