Guidance for using the New LRE Bridge Component

July 2010. Guidance for using the New LRE Bridge Component. Training Outline. Part 1 Cost-per –SF and Detailed Estimate Pay Item Detailed Estimate Segments Bridge Level Data Segment Level Data Supports Part 2 Sketches Supporting Tables and Other Information.

Download Presentation

Guidance for using the New LRE Bridge Component

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. July 2010 Guidance for using the New LRE Bridge Component

  2. Training Outline • Part 1 • Cost-per –SF and Detailed Estimate • Pay Item Detailed Estimate • Segments • Bridge Level Data • Segment Level Data • Supports • Part 2 • Sketches • Supporting Tables and Other Information

  3. Cost-per-SF & Item Details • Two methods are now available for estimating bridges: • Cost-per-square foot (no change from previous) • Pay item detailed • You can choose to use either or both:

  4. Primary Bridge Estimate • If you choose to have both a cost-per-square foot and a detailed estimate, you must designate one as the Primary: • For reporting and review (similar to Primary Version designation); • Not limited to LRE Coordinators; • Can be changed at any time (if the project is not in Blocked status).

  5. Cost-per-Square Foot Method • The cost-per-square foot method will remain the same as it was previously. • Screen is the same, except the fields for Superstructure and Substructure types have been removed. • For projects that had bridges prior to the implementation of the detailed component, the implementation did not affect (or change) the existing costs-per-square foot.

  6. The remainder of this presentation will apply to the Pay Item Detailed method of estimating bridges...

  7. Pay Item Detailed Method • Designed for common bridge types (the “90%”) • Pay item detailed component is not intended for estimating “specialty” bridges • Specialty bridges can be estimated by the cost-per-square foot method, or as X-Items.

  8. Bridge Segments • Bridges that havevarying types (or heights)can be separated intoSegments for moreaccurate estimating. • A bridge can have oneSegment, or many. • For each segment:Superstructure, Substructure and Foundation types are selected from a list.

  9. First and Last Segments • When you initiate a detailed estimate, the system assumes there is one segment. • The first segment created is automatically designated as the “First” and “Last” segment: • End Bents are automatically added to the segments designated as “First” and “Last”.

  10. Bridge Segments • If multiple segments are created, you must designate “First” and “Last” Segments so that end bent quantities will be appropriately generated:

  11. Bridge Segments • Example of a bridge requiring multiple segments for variations in height:

  12. Bridge Level and Segment Level Data • Data that remains consistent through all segments is input on the “Bridge Level” screen. • Bridge level data relates primarily to the type of construction and the characteristics of the bridge deck (typical section, railings, etc.). • Data that changes between segments is input on the “Segment Level” screen. • Segment Level data relates primarily to dimensions, and types for superstructure, substructure and foundation.

  13. Bridge Level Data • User Input / Selection: • Bridge Typical Section • Construction Type • Average Skew Angle • Sidewalk Widths • Railings, Left & Right • Traffic Separator Width • Generated Values: • Total Cost and Cost/SF • Approach Slabs • Total Length and AverageWidth (from Segments) • Quantities for Displayed Pay items

  14. Bridge Typical Sections

  15. New Bridge Defaults • When you create a newbridge a single segmentis created, with defaultmeasurements andcharacteristics. • The Bridge Level Detailscreen will display the InitialSegment Default values. • These values will not beaccurate for your bridge; • They are there because LREmust have a “starting point”; • You can change them here or on the Segment Details screen.

  16. Segment Level Data • User Input, per Segment: • Segment Dimensions & Clearance • Over Land or Water • Number of IntermediateSupports • Superstructure, Substructure,Foundation Types (selected) • Calculated Values: • Average Pile Length • Span Length • Quantities for all relatedpay items

  17. Segments & Intermediate Supports • The “Number of Intermediate Supports” is an input value on the segment, estimated by the coder. • There will be a default value for the first segment, based on total bridge length and other factors (bridge loads, etc.). The default value can be changed. • If additional segments are created, there will not be a default number of intermediate supports. The number will have to be estimated by the coder and manually entered. • This value has a significant impact on the quantities calculated!

  18. Example of Segments and Supports • The example bridge below has been separated into 3 segments, for differing heights; • Intermediate Support numbers, per segment are: • Segment 1 = 0, Segment 2 = 2, Segment 3 = 0 • Don’t count end bents! (Automatically included.) These piers are counted as input values in Segment 2 The program automatically adds the quantities for this pier into Segment 3 The program automatically adds the quantities for this pier into Segment 2

  19. Bridge Optional Tab • This tab contains input fields for several items that are commonly used on bridge projects, but do not have generated quantities. • Removal of Existing Structures • Sheet piling • Protection of Existing Structures • Navigation Lights, Fender System, Fiberglass Piles • Slope Protection • Expansion Joints • Takes the place of X-Items for these items. • Quantities must be included, but prices will be generated.

  20. Bridge Widening Rules • The program requires that one of the widening types shown here be selected. • If the specific widening type falls outside of these options, the estimate should be based on the square foot cost or by using X-items.

  21. Bridge Widening Rules • Widening Two Sides- The program is set up for widening on one side of the bridge. If the project requires widening on both sides, run as separate bridges and sum the quantities. • Match Existing - In general, the superstructure type of the bridge widening should always match the existing.

  22. Sketches and Supporting Information

  23. Typical Creek/Canal Crossings Flat Slab 18” Pile Bent Florida I- Beams 48” Dia. Drilled Shaft Bent

  24. Typical Overpass Bridges Florida U-Beam Multi-column Pier Steel H-Piles Florida I-Beam Drilled Shaft Bent 48” Dia. Drilled Shafts Steel I-Beam Multi-Column Pier 18” Prestressed Piles

  25. Multi Column Piers Multi-Column Piers Come in Different Shapes

  26. Typical Overpass Bridges • Some overpass structures can be a long simple span (number of intermediate supports = 0). • Here is an example of a long steel plate girder overpass span:

  27. Typical Interchange Ramps Steel Box Hammerhead 24” Prestressed Piles Steel I-Beam Hammerhead 24” Prestressed Piles

  28. Hammerhead Piers Hammerhead Piers come in different shapes

  29. Hammerhead Pier Options For high-level water crossings, two hammerhead piers set side-by-side may be a cost effective design solution given the wide bridge width. This can be approximated in the program by inputting one-half of the structure with a single hammerhead pier, then doubling the quantities. Short land piers are more likely to use multi column intermediate supports. The program assumes a single hammerhead pier for a given bridge cross section and limits the bridge width to less than or equal to 70 ft.

  30. Superstructure Sketches

  31. Substructure Types

  32. Foundation Elements

  33. Span Length Guidelines * When the calculated average span length exceeds 130’, verify feasibility of hauling FIB to the bridge site.

  34. Bridge Screens Flow • Bridges Tab • Bridge Summary Screen • Segments Tab • Bridge Level Detail Screen • Edit Detail Cost • Segments Summary • Edit Cost / SF • Optional Items Tab • Segment Detail • Optional Items Screen • Bridge $ / SF Screen • End(Back to Summary or Bridge Tab) • End(Back to Summary or Bridge Tab)