160 likes | 172 Views
This report provides updates on the Nushagak Power Plant upgrade project, including the installation of new variable frequency drives, valves, piping, and heat exchangers. The project is on schedule and on budget.
E N D
NUSHAGAK POWER PLANTUPGRADE-2006 QUATERLY PROGRESS REPORT PROJECT No. 216-06
New variable Frequency Drives Set In Place, Conduit ran, Units not wired-Just received wire.
8” Valves Part of Plant 2 Cooling System UpgradeTo Be Connected to Plant 2 Radiators.
Insulated Supplemental Heat Piping, To reduce heat loss to end users.
Plant 2 Radiators Re-Piping and Valves, Reducing Excess Pipe To Make System More Efficient.
Intercooler Radiators Re-Piped to Reduce Excess Piping, And To Make System More Efficient
Plant 2 Cooling System Radiators Re-Piped and Valved to Reduce Excess Pipe, Making system more efficient.
New Piping and Heat Exchanger, For Supplemental Heat System.
One Of the 8” Tie Lines Between Plant 1 And Plant 2 Cooling Systems. The Other to Be Added This Week 1/29-2/1-07.
8” Pipe Penetration Into Plant 2, Second Pipe to Be Added This Week.
Insulated Supplemental Heat Piping, reducing Heat Loss to End-Users.
Insulated Pipe And Heat Exchanger For Supplemental Heat System.
Narrative SummaryProject No. 216-06Work Completed as of 1/30/2007. • VFD’S Set In Place Conduit Ran. (To Be wired in Feb. 2007) • 8” Piping and Valves installed For Plant 2 Cooling System Upgrade. Remainder to be installed by March 1st. 2007. • Supplemental Heat Piping and Heat ExchangerInsulated, to reduce Heat Loss to End-Users.
Work to be Completed in Spring of 2007. • 6” Fuel Line Extension from Header to New City All Tide Dock. • Replace Tank Farm Liner Completed by 7/15/2007. • Install 2 Ea. Pad Mount Transformers For Station Service. • Install 2 Ea. Caterpillar 3512C Generator sets, Units 14 and 15. (Units ordered) Expected Arrival by 7/2007 Installed by 12/01/2007. • Projects are on Schedule and on Budget, as of 1/30/2007.