Program Management Systems Committee (PMSC)

Program Management Systems Committee (PMSC). Contractual Requirements/Issues Sub-Team. Update 7 August 2007. Sub-Team. Team Members Mike Martin - P&W Rocketdyne (Team Lead) Beverly Solomon - Northrop Grumman Gay Infanti - Northrop Grumman

cate
Download Presentation

Program Management Systems Committee (PMSC)

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Program Management Systems Committee (PMSC) Contractual Requirements/Issues Sub-Team Update 7 August 2007

  2. Sub-Team • Team Members Mike Martin - P&W Rocketdyne (Team Lead) Beverly Solomon - Northrop Grumman Gay Infanti - Northrop Grumman Eleanor Haupt - Consultant to the Institute for Defense Analyses Dave Muzio - MCR Peter Schwarz - MDA Jeff Poulson - Raytheon Linda Nobel - Raytheon Mike Pelkey – OSD Randy Steeno – Boeing Debbie Tomsic – OSD Larry Axtell – OSD Ivan Bembers – NGA Fred Meyer – DCMA EV Center • 8 Meetings conducted to date / 1 Face to Face on 12 June • Reviewed all previously identified issues to focus efforts. • Selected highest payback issues.

  3. Issues List • Currently working 4 issues. * See backup charts – pages 7 and 8

  4. Order of Precedence Suppliers have been contractually-directed by customers to depart from their validated EVM Systems to manage their contracts via • Section H – Special Provisions • Section C – Statement of Work requirements • In addition to inclusion of FAR or DFARs EVMS clauses in Section I The central issue is whether and by what means and to what extent can a supplier be rightfully required to violate the requirements of its validated EVM System. • Issue could arise between Customer and Prime and may or may not be flowed down to the Subcontractors • Issue could also arise between Prime and Subcontractors Issue Recommendations Existing contracts: • Issues identified must be resolved, bilaterally, by the buyer and seller • PCO’s and ACO’s must agree with the resolution. • Resolution may involve adjustments to price and/or other changes to the T’s & C’s of the contract . New acquisitions: • Involve all stakeholders in decision-making early in the acquisition process • Suppliers seek clarification of issues identified in RFPs using prescribed process • Issues identified after ATP must be resolved, bilaterally, by the buyer and seller • Conduct communication and training • Conduct RFP reviews within DoD / Primes and engage the EV Center for clarification when necessary Impact • DCMA issuing corrective action request (CAR) to Supplier for failing to follow Supplier’s validated EVMS • This finding appears inconsistent with the Contract Order of Precedence • Supplier cannot unilaterally resolve conflict in the contract nor can Supplier fail to comply with contract requirements

  5. Order of Precedence – T’s & C’s Contract Example Part I – The Schedule C) Description/specifications /statement of work EVM SOW text (infrequent) H) Special Provision clauses H) Special Contract Requirements Part II – Contract Clauses Suppliers EVM System Description I) 252.242-7002 Part III – List of Documents, Exhibits, and Other Attachments IMS or CPR DIDs J) List of Documents, CDRLs/SDRLs Part IV – Representations and Instructions (Solicitations only, excluded from the Contract)

  6. Integrated Subcontract EVMS Implementations • The use of a single EVMS by all program participants to manage large programs involving major subcontractors may be viewed as non-compliant to the DFARS EVMS clause by the new DCMA EV Center • This approach also referred to as badgeless, virtual, or gray badge • Characterized by adoption of a single validated system to manage the effort (typically the prime’s EVMS), use of a common tool set, integrated schedules and performance reporting Issue Recommendations • Contracts Working Group define valid options for EVMS flow down to subcontractors considering: • Different subcontract types • Roles and responsibilities • Validation requirements for prime and subcontractors • Reporting CDRLs (CPR and IMS) • Submit matrix for approval to the full PMSC • Submit for concurrence by OSD and DCMA EV Center • Conduct communication and training • Incorporate guidance into EVMIG • Incorporate modified guidance into NDIA Guides, as required Impact • Potential of DCMA Corrective Action Request (CAR) • The risk to the Subcontractors’ EVM System validation is still unclear at this time.

  7. Ownership and Control of Management Reserve • Direction has been given to prime contractors and subcontractors to use their Management Reserve (MR) for purposes other than the intent expressed in the ANSI/EIA-748 Standard. • MR is sometimes viewed as a contingency to eliminate in negotiations or to use for out-of-scope work. • Government involvement in MR approval process Issue Discussion • Decisions for the use of MR have been the province of the contractor within the confines of its approved use in accordance with the ANSI Standard • Misuse of MR is on the DCMA EV Center “Watch List” as a serious concern. Impact • Use of MR for out-of-scope work violates accepted contracting procedures and is tantamount to constructive change to the contract. • Improper use of MR distorts the Performance Measurement Baseline (PMB) resulting in skewed data and indices. Recommendations • Contractors should object to direction for the use of MR that deviates from accepted ANSI standard. • Contracting officers and prime should be alert to instances of improper contract direction.

  8. Subcontractor Compliance, Validation and Surveillance • Conduct a formal workshop with DCMA EV Center and Industry Reps • Results of workshop would require the development and / or modification of policy / guidance. Issue Discussion • There is confusion regarding the responsibility of subcontractor Compliance, Validation and Surveillance. Inconsistency between EVMIG , ANSI and DCMA Policy. • DCMA? • or • Prime Contractor? • < $20M • > $20M - < $50M • > $50M • Current policy / guidance can be interpreted in a variety of ways. • DCMA’s position is that they are responsible. • Industries position is that they are responsible. • Represents a paradigm shift in the Prime / Subcontracting relationship. Impact • Confusion between Prime and Subcontractors regarding oversight responsibilities. • Implementation responsibility gaps could cause significant compliance issues to go unnoticed. • May drive different implementation policies and procedures (e.g. DoD vs. Non DoD). Recommendations

  9. Path Forward • Understand stakeholders positions • Include DCMA EV Center, DoD and Industry Contracting SMEs to discuss our primary issues • Consider “Unintended Consequences” • Further Define and Prioritize Issues • Seek Corporate Guidance • Achieve consensus • Communicate, Communicate, Communicate • Develop and publish articles • Personal presentations • Revise Requirements as needed