SMD Market Rules and Manuals: “NEPOOL Presentation and Review Update”

Agenda Item #8 11/19&20/01 MC Mtg. SMD Market Rules and Manuals: “NEPOOL Presentation and Review Update”. November 20, 2001 Paul McCurley, ISO-NE. Agenda. Current status Updated plan for: “Manuals” Approach for review. Current Status of Plan.

catori
Download Presentation

SMD Market Rules and Manuals: “NEPOOL Presentation and Review Update”

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Agenda Item #8 11/19&20/01 MC Mtg. SMD Market Rules and Manuals:“NEPOOL Presentation and Review Update” November 20, 2001 Paul McCurley, ISO-NE

  2. Agenda • Current status • Updated plan for: • “Manuals” • Approach for review

  3. Current Status of Plan • The review of SMD Manuals with NEPOOL delayed pending clarification of FERC RTO Order and mediation process, internal development and review. • Overall plans for development and review for SMD Market Rules essentially unchanged at this point, but could be revisited. Current plan: • Develop and file “1X” (done, but must be re-evaluated); • Develop and file “2X” (SMD version of Market Rule 17 plus other monitoring and enforcement related rules)- Start in January 2002 • Revise “1X” (as needed)

  4. Status of Draft Manuals & Rules • Drafts represent our current best understanding of: • PJM/SMD Market Rules and Operations; • the market and operations software functionality. • New information and/or knowledge to be reflected as practical.

  5. Updated Plan For Manuals • Presentation and review plan for the remainder of 2001 and early 2002 will focus on the following “Group 1” Manuals: • M-11 (Scheduling Operations) • M-28 (Accounting/Settlements) • M-06 (FTR/ARR) • Note M-12 (Dispatching Operations) moved to “Group 2” • Development of “Group 2” will be addressed under RTO, or as needed • NEPOOL Operating Procedures will remain intact for as long as needed, and updated as necessary

  6. Updated Plan for Manuals (cont’d) • The following additional Group 1 Manuals developed under SMD project will be posted for NEPOOL review and comment. However, no formal presentation at MC. These are: • M-27 (Tariff Accounting) • M-29 (Billing) • M-33 (Admin Services) • M-35 (Terminology) • NOPs revised for SMD will be presented to NEPOOL for review in 2002

  7. The Approach • Review for the SMD Manuals and Market Rules has been adjusted to account for delays. • Manuals review will now begin at the November 19-20 MC meeting. • Review planned through the remainder of 2001 and early 2002. • Will do a high-level overview presentation of manual contents first, followed by detailed technical sessions, as needed.

  8. Questions?