Tiers 3 & 4 (adults) substance misuse tender - Briefing on timeline for existing providers

Tiers 3 & 4 (adults) substance misuse tender - Briefing on timeline for existing providers. Joe Apea Commissioning & Contracts Manager Northamptonshire County Council Health & Adult Social Services Tel 01604236595 Email japea@northamptonshire.gov.uk. Key dates.

catrin
Download Presentation

Tiers 3 & 4 (adults) substance misuse tender - Briefing on timeline for existing providers

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Tiers 3 & 4 (adults) substance misuse tender - Briefing on timeline for existing providers Joe Apea Commissioning & Contracts Manager Northamptonshire County Council Health & Adult Social Services Tel 01604236595 Email japea@northamptonshire.gov.uk

  2. Key dates Existing provider event – October 2011 Further cabinet approval – November 2011 Issue contract extension letters/ variations – End of November 2011 TUPE forms – issue by end of October. Return by 23 November 2011 Web pages for information sharing – by mid November 2011 Expert group day – by mid November 2011

  3. Key dates • Analyse TUPE forms and seek clarification – between 23 and 30 November 2011 • Treatment planning day – by 14 December 2011 • Provider open day – by 16 December 2011 • Analysis of current activity to inform – by 31 Dec 2011 • Finalise tender documentation – by 31 Dec 2012 • Bravo training – agree date with providers where required

  4. Key dates • Pre-qualifying Questionnaire (PQQ) go live – by 23 Jan 2012 • PQQ closing date – 20 Feb 2012 • PQQ evaluation – by 05 March 2012 • Invitation to Tender(ITT) go live – 12 March 2012 • Tender assessment panel briefings – by 12 April 2012

  5. Key dates • ITT close and return – by 20 April 2012 • Tender evaluation – by 07 May 2012 • Select and notify preferred bidder – 14 May 2012 • Alcatel (standstill period) – 10 working days from 14 May 2012 – 28 May 2012 • Contract award – by 11 June 2012 • Mobilisation, transition and implementation – 11 June 2012 – 30 Sept 2012 • Contract commencement – 01 Oct 2012

  6. Questions?