210 likes | 432 Views
~ Module 6 ~ CMGC Contracting at UDOT Program, Projects & Lessons Learned. Michelle A. Page, P.E. & Teri Newell, P.E. UDOT CMGC Program. FHWA - SEP 14 & Stewardship Agreement Centralized Roles Procurement FHWA Reporting De-Centralized Roles Procurement Design Construction
E N D
~ Module 6 ~ CMGC Contracting at UDOT Program, Projects & Lessons Learned Michelle A. Page, P.E. & Teri Newell, P.E.
UDOT CMGC Program • FHWA - SEP 14 & Stewardship Agreement • Centralized Roles • Procurement • FHWA Reporting • De-Centralized Roles • Procurement • Design • Construction • Project Closeout
UDOT Committed Funds by Delivery Methodby Year of Advertisement Date ($ in Millions)
UDOT Development of CMGC CMAR Concept Owner Contract Manager At-Risk Subs Designer Contractor CMGC Concept Owner Designer Contractor Specialty Sub Specialty Sub
CMGC Team Approach • Partnering • Build Trust • All Project Challenges Identified • Contractor Bids Actual Line Items CMGC Team Contractor UDOT Designer
Fair Price Strategy • Engineer’s Estimate • Typically based on State Averages • Contractor’s Estimate • Prepared for specific project bid items • Typically based on production rates and unit price • Independent Cost Estimate (ICE) • Cost Validation • Reflects Current Market Conditions
UDOT Lessons Learned - General • Build & Develop Trust • Team Building, Partnering Requirements, & Dispute Resolution • Co-Location • Partnering • Project Level • Executive Level • Communication • Project Manager • Project Team • Senior Leaders • Site Visits • Project Staffing Plan
UDOT Lessons Learned – Procurement • Project Goals • RFP “Boiler Plate” • Well Defined Selection Criteria & Scoring Method • Focus on the differentiators • What are the minimum qualifications? • Project Specific
UDOT Lessons Learned – Procurement • Blinding of the Oversight Committee • Technical Evaluation Team presents as Proposer A, B, C, etc. • Oversight Committee provides an unbiased perspective • Always leave an option for interviews • Include a Consultant & Contractor as a member of the evaluation team • Documented Selection Process
UDOT Lessons Learned - Design • Decision Making • Contractor Input • Risk Identification & Management • Important to watch Scope, Schedule, & Budget • Set goals to keep the team focused • Know your schedule limitations • Have candid budget discussions • Value Engineering • Procurement vs. Design
UDOT Lessons Learned - Design • Price Strategies • GMP, TMP, Lump Sums, Unit Pricing, Provisional Sums • Blind Bid Opening • Documentation • Decisions, Risk, Pricing, Comment Resolution, Etc.
UDOT Lessons Learned - Construction • Quantities • Payment • Early NTP • Risk Management Strategies • Change Order • Severable Packages • Order Girders • Order State Furnished Equipment • Build Haul Road • Clear & Grub • Early Utility Work • Stockpile Material
~ Module 6 ~ Mountain View Corridor Teri Newell, P.E.
MVC Project Overview • Salt Lake County (2010 to 2013) • CMGC • 15 mile segment • Two lanes in each direction • Utah County (2010 to 2011) • Low bid • 3 mile segment • Two lanes in each direction
CMGC Innovation • $25M savings through alternative design analysis and construction innovation – DART Process • $12M cost reduction in utility relocation – protect in place, means and methods analysis with utility owners • $6M savings due to schedule compression • $9.5M savings due to elimination of a rail bridge
Why was CMGC Right for MVC? • Stagger the contractor selection for I-15 CORE and MVC, while maintaining similar construction schedules • Flexibility to develop and implement mutually beneficial solutions for communities, utility companies, land owners, and UDOT • Innovative solutions that saved time and money • Flexibility to add or delete scope to project with a firm understanding of pricing due to open book process • Informed decisions about future needs vs. initial construction (phasing) based on contractor’s constructability review and estimate • Risk had time to be mitigated due to early identification by the team of owner, designer and contractor • Construction schedule coordination throughout the design process allowed for prioritization of key right of way purchases
Benefits of CMGC • Deliver the Best Transportation Project at the Best Value • Owner Makes Informed Decisions • Optimize Innovations • Risks Managed Throughout Project Delivery
Reference Materials & Questions • UDOT Annual CMGC Reports, and other related documents available online at www.udot.utah.gov • Questions?