Manpower Plan for Construction of X-Y House

Calculate the cost of hiring workers for the construction of a house based on the daily wage rates and number of days needed.

cfordham
Download Presentation

Manpower Plan for Construction of X-Y House

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. Manpower Plan Of X-Y File Group

  2. Group Members P.J. Mamacos Christy Mae Aquino

  3. Problem: A newly-wed couple plans to construct a house. The couple has already a house plan from their friend engineer. The plan of the house is illustrated below. 1m Laboratory 2m Bedroom 2m Dining Room Comfort room 1.5m 3m Living Room Master Bedroom 2.5m 3m 3m

  4. Workers needed for this project We need 1 foreman, 2 skilled workers and 4 unskilled workers to build the house that the couple want.

  5. Daily wage of the workers • Skilled worker--------------------P350.00/day • Foreman------------------------------P400.00/day • Unskilled worker-----------------P250.00/day

  6. Days needed for the project to be done 30 Days

  7. Computation of the cost of the entire job

  8. Computation of daily cost Let m be the cost of the job daily 52 200 pesos = m month 1 day 52 200 pesos = m 30 days 1 day (30 days) m = (52 200 pesos) 1 day 30 days 30 days m = 1740 pesos/day

  9. References: • http://www.bbisd.org/pages/uploaded_images/carpenter_lathe_carving_lg_nwm.gif • http://kmvb.weboldala.net/elsosegely/2.gif • http://www.autopozicovna-nz.sk/images/worker.gif • http://www.pattanakit.net/images/1193720269/architect_reading_blu_a_ha.gif • http://www.francisxaviers.com/web2012/images/under_construction.gif • http://www.svdpri.org/under_construction_worker.gif • http://msmcclure.com/wp-content/uploads/2010/09/animated-construction-workers1.gif

  10. Computation Let x be the total wage of the foreman in a month x = daily wage X entire days = 400 pesos X 30 days 1day = 400 pesos X 30 days 1day 1 month = 12000 pesos/ month

  11. Computation Let y be the total wage of the skilled worker in a month y = daily wage X entire work days = 350 pesos X 30 days 1day = 350 pesos X 30 days 1day 1 month = 10500 pesos/ month 2y = 2 ( 10500 pesos/ month) = 21000 pesos/ month

  12. Computation Let z be the total wage of the unskilled worker in a month z = daily wage X entire work days = 250 pesos X 30 days 1day = 250 pesos X 30 days 1day 1 month = 7500 pesos/ month 4z = 4 ( 7500 pesos/ month) = 30000 pesos/ month

  13. Computation of the cost of the entire job Let n be the total cost of the entire job n = x + 2y + 4z = 1200 pesos + 21 000 pesos + 30 000 pesos month month month = 52 200 pesos/ month