School District of Osceola County Facilities, Planning, Maintenance & Construction. Monthly Update – June 2007 Construction Workshop 26 June 2007. Report Contents. Planning Services Division Update Property Acquisition Summary General Issues Update Permitting Services Division Update
E N D
School District of Osceola CountyFacilities, Planning, Maintenance & Construction Monthly Update – June 2007 Construction Workshop 26 June 2007
Report Contents • Planning Services Division Update • Property Acquisition Summary • General Issues Update • Permitting Services Division Update • Activity Report – Permits, Inspections, C.O.’s • General & Administrative Issues • Design and Construction Services Division Update • 2006-2007 Goals • Capital Outlay Planned Projects Update • Major Projects Highlight Reports • Projects in Design & Bidding • Tax Savings Summary – New Schools • General Issues Update • Maintenance • Introduction
Planning Services – Property Acquisitions • Elementary I (Anthem Park) • Property acquisition has been closed. School is scheduled to open in August ’07. • Annexation into City of St. Cloud pending. • Elementary J (Harmony) • Closing for site acquisition is completed. • Comprehensive Development Plan Application has been submitted to Osceola County for Approval. 3. Elementary K (Flora Ridge) • Ownership of school site to be transferred from EFBD to SDOC after construction of school. • Elementary L (Poinciana) • Contract with Avatar Properties for acquisition of the school site pending. • Staff working to determine scope and budget for adjacent intersection improvements required by Osceola County. • Comprehensive Development Plan Application has been submitted to Osceola County for Approval. • Middle CC (Westside DRI) • Developer will convey the property to the SDOC through their EFBD in July 2007. Assessments will be used to fund the site acquisition at no cost to SDOC. • Site Due Diligence Underway • Coordination with Osceola County Parks and Recreation on Shared Park Facilities is on-going • Comprehensive Development Plan Application has been submitted to Osceola County for Approval.
Permitting – Activity Report Activity Report May - June 2007 YTD • Inspections Performed 30 396 • Inspection Hours 36 405 • Certificates of Occupancy 0 99 • Certificates of Completion 3 102 • Permits Issued 13 100
Permitting Services Update General Issues • All 761 existing portable inspections have been completed. No major deficiencies have been noted that would prevent usage. • Public Shelter Inspections (EHPA’s) have been completed. All eleven (11) designated shelter school sites have satisfactorily passed inspection. • L.P. tank inspections are complete. 34 code violations are being resolved by the Maintenance Department and our supplier Amerigas. All corrections performed by Amerigas are at no expense to SDOC. Administrative Issues • All portable additions have permits. Of the 100+ new additions for the opening semester, 80% are currently in place and inspections are currently being performed.
Design & Construction Services Goals • Completion/Start of all Capital Outlay Planned Projects within the fiscal year. • Completion/Start of 90% of ’06-’07 projects by July Workshop. • Construction complete and open new schools for August ’07. • Substantially Complete HS “EEE” July ’07. • Substantially Complete ES “I” July ‘07. 3. Design and start construction for new schools opening in ’08. • Start construction on ES “J” by July ’07. • Start construction on ES “L” by July ’07, pending site acquisition and approvals. • Substantially Complete ES “K” October ’07. • Start construction on Sports Authority Conversion in 3rd Quarter, pending resolution on re-zoning with City of Kissimmee. 4. Implement Management Initiatives. • Publish a Process & Procedures Manual; 50% 1st draft copy for January ’07. • Development & implementation of programs to assist in department operations and project administration.
Capital Outlay Program Status – ’06-’07 • The data provided reflects Capital Outlay amounts based on Board approved budgets for planned projects for renovation, remodeling, and other cyclical renewal projects only. • 97% of the Planned Project Capital Program is either completed or started. The Not Started Projects are planned Summer Projects.
Design & Construction – Request for Services 1. RFQ’s under development – to Purchasing June/July 2007 . • Geotechnical & Materials Testing for: OCSA and Middle School CC • HVAC Test & Balance for: OCSA and Middle School CC • CM @ Risk for HVAC Renovations at the Osceola County School for the Arts • CM @ Risk for Middle School CC • CM @ Risk for Schools Master Plan 2. Advertised RFQ’s – June 2007. • Continuing Services for Real Estate Appraisals • Continuing Services for Survey and Mapping 3. In Review/Selection Process • Continuing Services “CM” at Risk for Miscellaneous Minor Projects • A/E Services for HVAC Renovations at the Osceola County School for the Arts • Continuing Services for Civil Engineering • Continuing Services for Permit/Plan Review and Building Code Inspections
Design & Construction – Owner Direct Purchase Program Tax Savings Summary – New Schools