1 / 15

BPM Upgrade

BPM Upgrade. Presented by: Nadine Kurita Contributors: S. Smith, S. Ecklund, J. Sebek, D. Martin, R. Hettel, R. Johnson, N. Reeck, M. Kosovsky, D. Arnett. Outline. BPM Upgrade project overview 2005 upgrade/testing LER Arc BPM’s IR2 BPM’s Summary. BPM Upgrade Overview.

chaela
Download Presentation

BPM Upgrade

An Image/Link below is provided (as is) to download presentation Download Policy: Content on the Website is provided to you AS IS for your information and personal use and may not be sold / licensed / shared on other websites without getting consent from its author. Content is provided to you AS IS for your information and personal use only. Download presentation by click this link. While downloading, if for some reason you are not able to download a presentation, the publisher may have deleted the file from their server. During download, if you can't get a presentation, the file might be deleted by the publisher.

E N D

Presentation Transcript


  1. BPM Upgrade Presented by: Nadine Kurita Contributors: S. Smith, S. Ecklund, J. Sebek, D. Martin, R. Hettel, R. Johnson, N. Reeck, M. Kosovsky, D. Arnett

  2. Outline • BPM Upgrade project overview • 2005 upgrade/testing • LER Arc BPM’s • IR2 BPM’s • Summary Vacuum System p.2

  3. BPM Upgrade Overview • There are 3 styles of BPM’s in the PEP-II machine. • LER Arc BPM’s • Helicoflex sealed, SS housing • HER Arc BPM’s • Welded, CuNi housing • LER/HER Straight BPM’s • Welded, SS housing • Thermal and experimental models show that the BPM buttons could be approaching temperatures around 800 to 1000 C from HOM heating. • HOM heating has numerous parameters (i.e. bunch current, total current, beam position, chamber geometry). • Two areas are of major concern due to the high current and BPM position relative to beam. • LER arc BPM’s • IR2 BPM’s Vacuum System p.3

  4. Current Upgrades - 2005 Downtime (cont.) • Four sets of modified LER Arc BPM’s at ARC 1, • Goal – to reduce HOM power. • 7 mm molybdenum button • Welded tabs on buttons and pressed them off. • 50-150 lbs, • average was ~ 60 lbs (excluding outliers). • Pressed molybdenum buttons • 100-600 lbs • Test push ~850 lbs  leak tight. • One set has a 5 mm gap between button and housing. • One set has a 1 mm gap between button and housing. • Laser welded SS insert Vacuum System p.4

  5. short Current Upgrades - 2005 Downtime (cont.) • 7mm button reduces power dissipated and transmitted by the BPM’s. (S. Ecklund) • Factor of 2 – 4? • Data indicate that the 7mm button with the 1mm gap absorbs the least amount of power. • Shorted button to housing • 3 mm wide x 6.3 mm long, .4 mm thick Inconel strip • resistance welded • 0.25 mm of copper for thermal conductivity. • T increase by ~ 23 X • For, Q = 10W, T = 200C • Issues • Overheated the attenuators that were added for the additional HOM power that would be coming out of the transmission line. • Resistance welds may fail and lead to arcing. • Does not appear to be a viable solution. Vacuum System p.5

  6. 2006 LER Arc BPM Upgrade • Option 1 – Retrofit existing Borosilicate Glass BPM’s. • Successfully completed this downtime. • 7mm button reduces power dissipated and transmitted. • Signal meets precision/accuracy requirements for stored beam at high current. • Signal is sufficient for single turn high current beam. • Downtime experience • Welded tabs on buttons and pressed them off. • 50-150 lbs, • average was ~ 60 lbs (excluding outliers). • Pressed molybdenum buttons • 100-600 lbs • Test push ~850 lbs  leak tight. • Pin diameter tolerance +/-.002” • Press fit tolerance is +/-.0001” • Pins were measured and buttons were match machined – forces were still larger than anticipated. • Errors in QC data lead to failures. Button partially pressed on. • Fit tolerance on small diameters make this task difficult & costly. Vacuum System p.6

  7. Design – BPM Retrofit • Current Plan • Re-design press fit to reduce force and increase tolerance band. • Taper and reduce press fit region. • Pros • Does not require significant design effort. • Cons • Requires manufacturing downtime work. • Could encounter difficulties and failures • Buttons diffusion welded from high temperatures? • Glass seal failing from removing buttons or pressing buttons (low risk – from tests). • Partially pressed on buttons – difficult to recover BPM if this occurs. • Thermal conductivity – 8 to 20 X worse than alumina. • Contingency cost could run higher (SLAC labor versus fixed cost). • Cost Estimate (N. Reeck) – consistent with AIP budget • Retrofit of the BPM • Indirect Cost: $339.65 each including 28% contingency • Installation • Indirect Cost: $168 each • Cost does not include helicoflex seal Vacuum System p.7

  8. Design – Alumina BPM • Option 2 Saint Gobain Feedthru • SSRL/SPEAR3 – working on purchasing these for a small gap undulator chamber. • Preliminary cost estimate $245 each for 20 pieces. • Bake out/leak check - +$60 each. • Specification and drawings near completion 90%. • Pros • design exists • Alumina – better thermal conductivity • Cost is competitive with retrofitting. • New - $305, does not include destructive & electrical testing cost. • Total cost within AIP budget – potential less risk of overrun due to fix cost. • Retrofit - $340 • Cons • Needs testing • Dielectric constant 2 X higher than glass. • New vendor – not much reliability data. • Not electrically equivalent to remaining BPMs • Schedule Vacuum System p.8

  9. Alumina Feedthru Layout Drawing Vacuum System p.9

  10. Major Milestones – option 1 - Retrofit • Dec ’05 - Complete scope of project – critical decision. • Jan ’05 - Complete new design • Feb ‘05 - Push pull tests • Mar ‘06 - Order Parts • May ’06 - Receive buttons • Aug ’06 - Remove & modify 200 feedthrus, 2-3 people/month • Sep ’06 - Remove & modify 200 feedthrus • Oct ’06 - Remove & modify 200 feedthrus • Nov ’06 - Remove & modify 200 feedthrus • Dec ’06 - Complete re-installation Vacuum System p.10

  11. Major Milestones – option 2 • Dec ’05 - Complete scope of project – critical decision. • Dec ’05 - Complete design specification • Dec ‘05 - Order Prototype • Feb ‘06 - MAFIA/RF simulations • Mar ’06 - Receive Prototypes • May ‘06 - Destructively test • May ‘06 - Order production units • Aug ‘06 - Receive 1st lot (100 units) • Nov ’06 - Receive last lot (200 units/month?) • Sep ’06 - Install 1st lot • Dec ’06 - Install last lot Vacuum System p.11

  12. Major Milestones • Dec ’05 - Complete scope of project. • Dec ’05 - Complete design specification • Dec ‘05 - Order Prototype • Feb ‘06 - MAFIA/RF simulations • Mar ’06 - Receive Prototypes • May ‘06 - Destructively test • May ‘06 - Order production units • Aug ‘06 - Receive 1st lot (100 units) • Nov ’06 - Receive last lot (200 units/month?) • Sep ’06 - Install 1st lot • Dec ’06 - Install last lot Vacuum System p.12

  13. IR2 BPM Upgrade Plan • Remove 15 mm button and leave 2.4 mm center pin as button. • Attempt to remove buttons in situ without removing chambers if possible. • Buttons will be leak checked from the reverse side if space permits. • If failure occurs during attempt (leak or failure to remove button). • Replace with copper blank. • Replace with new helicoflex sealed BPM similar to the new LER arc BPM. Vacuum System p.13

  14. BPM Removal Tool Vacuum System p.14

  15. Summary • HER arcs and LER/HER straights BPM’s do not require an upgrade at this time. • There is an upgrade plan for LER arcs and IR2. • Need to determine if BPM’s can be pulled in-situ. If not a decision to remove the chambers or leave the BPMs “as is” will have to be made. • Will need full support from physicists for RF/HOM analysis because the design & procurement cycle is long for new BPMs. Vacuum System p.15

More Related